Medium Neutral Citation: Tamanna v Zattere; Thakorlal v Zattere; Rabac Pty Ltd v Zattere [2017] NSWSC 1388 Hearing dates: 20 – 23 June 2016, 10 April, 22 and 24 August 2017 Date of orders: 12 October 2017 Decision date: 12 October 2017 Jurisdiction: Equity Before: Darke J Decision: Purchasers entitled to loss of bargain damages following termination for vendor’s repudiation of contracts.
Catchwords: LAND LAW – conveyancing – the contract for sale – rescission – “off the plan” purchases – vendors required to use either reasonable endeavours or best endeavours to cause plan of subdivision to be registered – plan not registered by required date – whether vendor entitled to rescind – rescissions ineffective
CONTRACTS – causation – principle that a party cannot exercise a right in reliance on an event that results from its own default – whether innocent party must prove that default materially contributed to the occurrence of the event or prove on balance of probabilities that default caused the event – party not able to exercise a right of rescission if it has materially contributed to the occurrence of the event that gives rise to the right
CONTRACTS – damages – date of assessment – where defendants repudiated contracts by invalid rescission – subject matter of contract subsequently sold by receiver – plaintiffs terminated contracts shortly before hearing – whether date of assessment is date of termination or earlier date – damages assessed at date of termination
CONTRACTS – damages – loss of bargain damages – requirement of plaintiff to prove it was ready, willing and able to perform its obligations – standards of readiness, willingness and ability for termination for breach and proof of damages – plaintiffs ready, willing and able to complete up to time of terminationLegislation Cited: Competition and Consumer Act 2010 (Cth), Sch 2, ss 18, 236
Conveyancing Act 1919 (NSW), ss 88B, 88K
Supreme Court Act 1970 (NSW), s 68Cases Cited: Abourjaily v Parkview Estate Pty Ltd [2017] NSWSC 1256
Actall Pty Ltd v Pacific Bay Development Pty Ltd [2006] ANZ ConvR 67; [2005] NSWSC 1067
Al Achrafi v Topic (2016) 18 BPR 36,517; [2016] NSWSC 1807
ASA Constructions Pty Ltd v Iwanov [1975] 1 NSWLR 512
Clark v Macourt (2013) 253 CLR 1; [2013] HCA 56
Cohen & Co v Ockerby & Co Ltd (1917) 24 CLR 288
DTR Nominees Pty Ltd v Mona Homes Pty Ltd (1978) 138 CLR 423
Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; [2014] HCA 7
Foran v Wight (1989) 168 CLR 385
Hardy v Wardy (2001) 10 BPR 19,055; [2001] NSWSC 1141
Hawes v Cuzeno Pty Ltd (1999) 10 BPR 18,011; [1999] NSWSC 1167
Hensley v Reschke (1914) 18 CLR 452
Henville v Walker (2001) 206 CLR 459; [2001] HCA 52
Hospital Products Ltd v United States Surgical Corporation (1984) 156 CLR 41
Hunyor v Tilelli (1997) 8 BPR 15,629
Italo-Australian Club Ltd v National Australia Bank Ltd (1989)
Keep reading for free
Create a free CaseChat account to read Tamanna v Zattere and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2017] NSWSC 1388
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the defendants were entitled to rescind the contracts due to the plaintiffs' failure to complete. Additionally, the court needed to assess the principles of causation in the context of rescission, specifically whether the plaintiffs could be held responsible for the failure to register the plan of subdivision, which led to the rescission. The court also had to determine the appropriate date for assessing damages and the standard of proof for loss of bargain damages in the context of termination for breach.
The court found that the defendants were not entitled to rescind the contracts as they had failed to use reasonable endeavours to register the plan of subdivision by the required date. The court emphasised the principle that a party cannot exercise a right in reliance on an event that results from its own default. Therefore, the rescissions were ineffective. Regarding the date for assessing damages, the court held that the appropriate date was the date of termination of the contracts. The court also found that the plaintiffs were ready, willing and able to complete their obligations under the contracts, thus entitled to loss of bargain damages.
The court ordered the defendants to compensate the plaintiffs for the loss of bargain damages, assessed at the date of termination of the contracts. The defendants were also ordered to pay the plaintiffs' costs of the proceeding. The court's decision provided clarity on the rights and obligations of parties in "off the plan" property sales and the principles of causation and damages in the context of rescission.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi