FEDERAL COURT OF AUSTRALIA
Stuart-Mahoney v Construction, Forestry, Mining and Energy Union [2008] FCA 1426
INDUSTRIAL RELATIONS – penalty hearing – admitted contraventions – civil penalty provisions – relevant considerations in determining appropriate penalty – penalty determined
WORDS AND PHRASES – ‘unlawful industrial action’, ‘involved’
Building and Construction Industry Improvement Act 2005 (Cth) ss 3, 36, 37, 38, 43, 48, 49, 69
Mornington Inn Pty Ltd v Jordan (2008) 247 ALR 714
Kelly v Fitzpatrick (2007) 166 IR 14
Trade Practices Commission v CSR Ltd [1991] ATPR 52,135 (41-076)
Construction, Forestry, Mining and Energy Union v Coal and Allied Operations Pty Ltd (No 2) (1999) 94 IR 231
Hadgkiss v Aldin (2007) 164 FCR 394
Furlong v Australian Workers Union (2007) 162 IR 171
Carr v Communications, Electrical, Electronic, Engineering, Information, Postal, Plumbing and Allied Services Union of Australia [2007] FMCA 1526
Cruse v Construction, Forestry, Mining and Energy Union [2007] FCA 1873
Leighton Contractors Pty Ltd v Construction, Forestry, Mining and Energy Union (2006) 164 IR 375
Australian Competition and Consumer Commission v IPM Operations Maintenance Loy Yang Pty Ltd (No 2) [2007] FCA 11
Finance Sector Union v Commonwealth Bank of Australia (2005) 147 IR 462
Australian Competition and Consumer Commission v ABB Transmission and Distribution Ltd [2001] ATPR 41-815
Australian Opthalmic Supplies Pty Ltd v McAlary-Smith (2008) 165 FCR 560
Australian Competition and Consumer Commission v Australian Safeway Stores Pty Ltd (1997) 145 ALR 36
Ponzio v B & P Caelli Constructions Pty Ltd (2007) 158 FCR 243KAREN STUART-MAHONEY v CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION, JOHN PARKER and CHARLES CORBETT
VID 1323 OF 2006
TRACEY J
19 SEPTEMBER 2008
MELBOURNE
IN THE FEDERAL COURT OF AUSTRALIA
VICTORIA DISTRICT REGISTRY
VID 1323 OF 2006
BETWEEN:
KAREN STUART-MAHONEY
ApplicantAND:
CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION
First RespondentJOHN PARKER
Second RespondentCHARLES CORBETT
Third Respondent
JUDGE:
TRACEY J
DATE OF ORDER:
19 SEPTEMBER 2008
WHERE MADE:
MELBOURNE
THE COURT DECLARES THAT:
1.Between 6 October 2005 and 12 October 2005 each of the respondents contravened s 38 of the Building and Construction Industry Improvement Act 2005 (Cth) by engaging in unlawful industrial action (being the imposition of an overtime ban).
2.Between 6 October 2005 and 12 October 2005 each of the respondents contravened s 43 of the Building and Construction Industry Improvement Act 2005 (Cth) by organising action (being the imposition of an overtime ban) with intent to coerce Hooker Cockram Projects Ltd to engage a person as a building employee.
THE COURT ORDERS THAT:
1.A penalty of $20,000.00 be imposed on the first respondent for contravening s 38 of the Building and Construction Industry Improvement Act 2005 (Cth).
2.A penalty of $35,000 be imposed on the first respondent for contravening s 43 of the Building and Construction Industry Improvement Act 2005 (Cth).
3.A penalty of $2,000 be imposed on the second respondent for contravening s 38 of the Building and Construction Industry Improvement Act 2005 (Cth).
4.A penalty of $6,000 be imposed on…
Keep reading for free
Create a free CaseChat account to read Stuart-Mahoney v Construction, Forestry, Mining and Energy U... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2008] FCA 1426
- Decision Date
CaseChat Overview and Summary
The court found that the overtime ban imposed by the CFMEU and its officials was serious and designed to coerce the employer to meet employment requirements, rather than pursuing lawful alternatives such as negotiations or dispute resolution. The ban resulted in no work being done on the project for six working days, which the court deemed to be a significant disruption. The court also noted that the conduct was deliberate and that the CFMEU had not exhibited contrition or taken corrective action. The court considered these factors along with the need for compliance, specific deterrence, and general deterrence in determining the penalty.
The court ultimately imposed penalties on the CFMEU and the two officials. The CFMEU was fined $55,000, with $20,000 for the contravention of section 38 and $35,000 for the contravention of section 43. The two officials were fined $8,000 each, with $2,000 for the contravention of section 38 and $6,000 for the contravention of section 43. The court suspended the penalties for one year on the condition that the CFMEU did not breach the relevant acts again within that period. If the condition was met, the penalties would not have to be paid. Each party was ordered to bear their own costs.
Orders
Orders of the court
1. A penalty of $20,000.00 be imposed on the first respondent for contravening s 38 of the Building and Construction Industry Improvement Act 2005 (Cth).
2. A penalty of $35,000 be imposed on the first respondent for contravening s 43 of the Building and Construction Industry Improvement Act 2005 (Cth).
3. A penalty of $2,000 be imposed on the second respondent for contravening s 38 of the Building and Construction Industry Improvement Act 2005 (Cth).
4. A penalty of $6,000 be imposed on the second respondent for contravening s 43 of the Building and Construction Industry Improvement Act 2005 (Cth).
5. Paragraphs 3 and 4 of these orders be wholly suspended for 12 months from the date of these orders. If the second respondent is not found to have breached any provision of the Building and Construction Industry Improvement Act 2005 (Cth) or the Workplace Relations Act 1996 (Cth) as a result of conduct occurring within 12 months of the date of these orders he shall not be obliged to pay the penalties.
6. Subject to paragraph 5, the penalties imposed in paragraphs 1 - 4 of these orders be paid into the Consolidated Revenue Fund within 30 days.
7. Each party bear his or its own costs in relation to the proceeding.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Established by: TRACEY J
The respondents submit that no penalty should be imposed against any of the respondents but do not oppose the Court making the declarations sought by the applicant. CONSIDERATION In Kelly v Fitzpatrick (2007) 166 IR 14 I set out a non-exhaustive range of considerations to which regard may be had in determining whether conduct calls for a penalty, and if so, the amount of such penalty. These considerations were derived from a number of decisions of this Court including Trade Practices Commission v CSR Ltd [1991] ATPR 52,135 (41-076) (which concerned contraventions of the Trade Practices Act 1974 (Cth)) and Construction, Forestry, Mining and Energy Union v Coal and Allied Operations Pty Ltd (No 2) (1999) 94 IR 231 (which concerned contraventions of Part XA of the WR Act). In my view, potentially relevant and applicable considerations for determining the appropriate penalty for a contravention of the BCII Act include: ·The nature and extent of the conduct which led to the breaches. ·The circumstances in which that relevant conduct took place. ·The nature and extent of any loss or damage sustained as a result of the breaches. ·Whether there had been similar previous conduct by the respondent. ·Whether the breaches were properly distinct or arose out of the one course of conduct. ·The size of the business enterprise involved.·Whether or not the breaches were deliberate. ·Whether senior management was involved in the breaches. ·Whether the party committing the breach had exhibited contrition. ·Whether the party committing the breach had taken corrective action. ·Whether the party committing the breach had cooperated with the enforcement authorities. ·The need to ensure compliance with minimum standards by provision of an effective means for investigation and enforcement of employee entitlements. ·The need for specific and general deterrence. cf Hadgkiss v Aldin (2007) 164 FCR 394 at [61]; Furlong v Australian Workers Union (2007) 162 IR 171 at [7] – [10]; Carr v Communications, Electrical, Electronic, Engineering, Information, Postal, Plumbing and Allied Services Union of Australia [2007] FMCA 1526 at [7]; and Cruse v Construction Forestry Mining and Energy Union [2007] FCA 1873 at [71].The nature and extent of the conduct The overtime ban meant that no work was performed on the project after 3.30 pm on any working day from Thursday 6 October 2005 to Wednesday 12 October 2005 - a total of six working days. The ban was only lifted once Hooker Cockram had agreed to meet the Employment Requirement, after being told three times that the ban would not be lifted until the Employment Requirement was met. In my view the conduct was serious and was designed to coerce Hooker Cockram (or, through it, one of its sub-contractors) to meet the Employment Requirement. The ban was imposed in preference to alternative, lawful, actions such as negotiations or resort to dispute resolution procedures which were available to the CFMEU and its members. Circumstances in which the conduct took place