FEDERAL COURT OF AUSTRALIA

Australian Building and Construction Commissioner v Construction, Forestry, Mining and Energy Union [2012] FCA 189

Citation: Australian Building and Construction Commissioner v Construction, Forestry, Mining and Energy Union [2012] FCA 189
Parties: AUSTRALIAN BUILDING AND CONSTRUCTION COMMISSIONER v CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION and SHAUN REARDON
File number: VID 948 of 2010
Judge: BROMBERG J
Date of judgment: 6 March 2012
Catchwords: INDUSTRIAL LAW – penalty hearing – admitted contraventions of s 38 of the Building and Construction Industry Improvement Act 2005 (Cth) – agreed penalty – relevant considerations in assessing appropriateness of agreed penalty
Legislation: Building and Construction Industry Improvement Act 2005 (Cth) ss 38, 69
Cases cited: Alfred v CFMEU [2011] FCA 556
BHP Steel (AIS) Pty Ltd v CFMEU [2001] FCA 336
Cahill v CFMEU (No 4) [2009] FCA 1040
Cozadinos v CFMEU [2010] FCA 48
Hoare v the Queen (1989) 167 CLR 348
Minister for Industry, Tourism and Resources v Mobil Oil Australia Pty Ltd [2004] FCAFC 72
NW Frozen Foods Pty Ltd v ACCC (1996) 71 FCR 285
Ponzio v B & P Caelli Constructions (2007) 158 FCR 543
R v Valentini (1980) 48 FLR 416
Stuart v CFMEU (2010) 185 FCR 308
Stuart- Mahoney v CFMEU [2008] FCA 1426
Temple v Powell (2008) 169 FCR 169
Veen v The Queen (No 1) (1979) 143 CLR 458
Veen v The Queen (No 2) (1988) 164 CLR 465
Wells v Locano Management Pty Ltd [2008] FCA 1034
Date of hearing: 11 October 2011
Place: Melbourne
Division: FAIR WORK DIVISION
Category: Catchwords
Number of paragraphs: 32
Counsel for the Applicant: Mr M Felman
Solicitor for the Applicant: Freehills
Solicitor for the Respondents: Mr M Sayers of Slater & Gordon

IN THE FEDERAL COURT OF AUSTRALIA

VICTORIA DISTRICT REGISTRY

FAIR WORK DIVISION

VID 948 of 2010

BETWEEN:

AUSTRALIAN BUILDING AND CONSTRUCTION COMMISSIONER
Applicant

AND:

CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION
First Respondent

SHAUN REARDON
Second Respondent

JUDGE:

BROMBERG J

DATE OF ORDER:

6 MARCH 2012

WHERE MADE:

MELBOURNE

THE COURT ORDERS THAT:

1.A penalty of $50,000 be imposed on the first respondent for engaging in unlawful industrial action on 20 November 2008 at the construction site at the Caroline Springs Square Shopping Complex, Caroline Springs, Victoria in contravention of s 38 of the Building and Construction Industry Improvement Act 2005 (Cth).

2.The penalty referred to in order 1 be paid into the Consolidated Revenue Fund within 28 days of the date of these orders.

3.There be no order as to costs.

4.The proceeding be otherwise dismissed.

Note:    Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

IN THE FEDERAL COURT OF AUSTRALIA

VICTORIA DISTRICT REGISTRY

FAIR WORK DIVISION

VID 948 of 2010

BETWEEN:

AUSTRALIAN BUILDING AND CONSTRUCTION COMMISSIONER
Applicant

AND:

CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION
First Respondent

SHAUN REARDON
Second Respondent

JUDGE:

BROMBERG J

DATE:

6 MARCH 2012

PLACE:

MELBOURNE

REASONS FOR JUDGMENT

  1. The proceeding is brought by the Australian Building and Construction Commissioner (“ABCC”).  The…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Australian Building and Construction Commissioner v Construc... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2012] FCA 189
Decision Date

CaseChat Overview and Summary

The case before the court involved the Australian Building and Construction Commissioner and the Construction, Forestry, Mining and Energy Union. The dispute centred around alleged contraventions of section 38 of the Building and Construction Industry Improvement Act 2005 (Cth), which pertains to unlawful industrial actions. The matter was heard in the Federal Court of Australia.

The primary legal issues the court had to address were the appropriateness of an agreed penalty for the admitted contraventions and the relevant considerations in assessing this penalty. The court needed to determine whether the agreed penalty of $50,000 was commensurate with the nature and seriousness of the unlawful industrial action taken by the union on 20 November 2008 at a construction site in Caroline Springs, Victoria.

In delivering its judgment, the court carefully considered the relevant factors, including the seriousness of the contraventions, the union's conduct, and the need to deter future unlawful industrial actions. The court found that the agreed penalty of $50,000 was appropriate given the circumstances of the case. The court emphasised the importance of striking a balance between deterrence and proportionality in setting penalties for such contraventions. Consequently, the court confirmed the agreed penalty and ordered it to be paid into the Consolidated Revenue Fund within 28 days. The court dismissed the proceeding without ordering costs for either party.

Orders

Orders of the court

1. A penalty of $50,000 be imposed on the first respondent for engaging in unlawful industrial action on 20 November 2008 at the construction site at the Caroline Springs Square Shopping Complex, Caroline Springs, Victoria in contravention of s 38 of the Building and Construction Industry Improvement Act 2005 (Cth).

2. The penalty referred to in order 1 be paid into the Consolidated Revenue Fund within 28 days of the date of these orders.

3. There be no order as to costs.

4. The proceeding be otherwise dismissed.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established