Southern Waste ResourceCo Pty Ltd v Adelaide Hills Region Waste Management Authority

Link copied
Case Copied 55 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Civil: Application)

SOUTHERN WASTE RESOURCECO PTY LTD v ADELAIDE HILLS REGION WASTE MANAGEMENT AUTHORITY

[2019] SASC 190

Judgment of The Honourable Justice Hinton

15 November 2019

PROCEDURE - DISCOVERY AND INTERROGATORIES - DISCOVERY AND INSPECTION OF DOCUMENTS

PROCEDURE - SUPREME COURT PROCEDURE - SOUTH AUSTRALIA - PROCEDURE UNDER RULES OF COURT - AMENDMENT

The defendant made three applications eight days into the trial in this matter, seeking orders: that it be permitted to amend its Defence, for the production of documents over which the plaintiff had claimed legal professional privilege and for the production of further documents relating to the negotiations between the plaintiff and the owners of the site, the Harveys. The applications were resolved on 9 August 2016 without reasons; these are the reasons for the orders made on that date. 

In relation to the first application, the defendant sought to amend its Defence to include a claim that SWR were contributorily negligent and had not exercised reasonable care. The plaintiff submitted that it had not prepared to answer a claim for contributory negligence and that the amendment would cause inconvenience and delay. The defendant’s application was brought in good faith and there was an adequate explanation for the delay in making the allegation. The material facts relevant to an allegation of want of reasonable care or contributory negligence were already in issue on the pleadings. Amendment allowed.

In relation to the second application, the plaintiff claimed that each of the documents sought were prepared for the dominant purpose of obtaining legal advice and were privileged. The defendant claimed that the plaintiff had waived privilege over those documents by the way in which it had conducted its case. The plaintiff did not directly or indirectly put the content of the privileged communications in issue; privilege was not waived.

In relation to the third application, the defendant filed a notice to produce of numerous documents which were alleged by the defendant to be relevant to the issues at trial but not disclosed by the plaintiff. The notice identified 14 categories of documents. The defendant had a legitimate forensic purpose in requesting production. In the absence of said production, the plaintiff was ordered to provide an explanation of the search undertaken to obtain the documents.

Competition and Consumer Act 2010 (Cth) s 137B; Law Reform (Contributory Negligence and Apportionment of Liability) Act 2001 (SA) s 7; Local Government Act 1999 (SA) s 43; Misrepresentations Act 1972 (SA) s 7; Supreme Court Civil Rules 2006 (SA) rr 3, 54, 117 and 215, referred to.
Aon Risk Services Australia Limited v Australian National University (2009) 239 CLR 175; Cement Australia Pty Ltd & Ors v Australian Competition and Consumer Commission (2010) 187 FCR 261; Channel Seven Adelaide Pty Ltd v Manock [2010] SASCFC 59; Commissioner of Taxation v Rio Tinto Ltd [2006] FCAFC 86; DSE (Holdings) Pty Ltd v Intertan Inc [2003] FCA 384; Legal Services Commission v W, JH (2012) 223…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Southern Waste ResourceCo Pty Ltd v Adelaide Hills Region Wa... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2019] SASC 190
Decision Date

CaseChat Overview and Summary

Southern Waste ResourceCo Pty Ltd (SWR) sued the Adelaide Hills Region Waste Management Authority (the Authority) for allegedly misleading it during negotiations to take over the operation of a waste disposal facility at Hartley. The Authority was established by four councils under the Local Government Act 1999 (SA). The Authority denied the claims and sought to amend its Defence to include pleas of contributory negligence and failure to mitigate. SWR opposed the application to amend on the grounds of delay and lack of expert evidence.

The Court considered whether the Authority's application to amend its Defence was made in good faith and whether it was necessary to explain the delay. It noted that leave to amend is more readily granted before a trial date is fixed than during trial, and the applicant bears a heavy burden in justifying the consequent burden to be imposed on the opposing party. The Court held that the Authority's application was made during the trial and was delayed, and thus required an explanation. The Court also considered whether the proposed amendments would require further expert evidence, and whether such evidence would be relevant to the issues raised by the proposed amendments. The Court held that the proposed amendments did not require further expert evidence, as the evidence would be irrelevant to the issues raised by the proposed amendments.

The Court granted the Authority's application to amend its Defence, subject to certain conditions. The Court held that the Authority had provided an explanation for the delay in making the application, and that the proposed amendments were not frivolous or vexatious. The Court also held that the proposed amendments did not require further expert evidence, as the evidence would be irrelevant to the issues raised by the proposed amendments. The Court ordered that the Authority pay SWR's costs of the application.

Orders

Orders of the court

Background

Background to the litigation

My reasons for making those orders follow. Background SWR has operated a bulk waste disposal facility, or landfill, at Hartley since 2013. Prior to 2013, that landfill was operated by the Authority. The Authority is a regional subsidiary established under s 43 of the Local Government Act 1999 (SA) by four councils: the District Council of Mount Barker, the Rural City of Murray Bridge, the Adelaide Hills Council and Alexandrina Council (the constituent councils). The land at Hartley upon which the landfill is located is owned by third parties. Prior to 13 February 2013 it was leased by the Authority. In 2011, the Authority sought to exercise a right of renewal under the lease so that it could continue to operate the landfill. A dispute arose. In August 2012, SWR, on behalf of the owners of the land at Hartley, commenced negotiations with the Authority to settle the dispute. Those negotiations were successful and on 11 February 2013, the owners of the land, SWR and the Authority entered into two deeds reflecting the terms of the settlement reached. In accordance with the terms of the settlement the Authority agreed to vacate the Hartley site and SWR assumed responsibility for the operation of the landfill. For its part, SWR agreed, amongst other things, to pay the sum of $990,000.00 to the Authority and to assume liability for all environmental performance issues, both past and future, in respect of the landfill. At the risk of oversimplification, in the proceedings instituted in this Court SWR claimed that the Authority falsely represented that it had no pre-existing contract, arrangement or understanding with the constituent councils that would inhibit, or render less likely, the councils using the landfill and that the councils were free to contract with SWR to dispose of their waste at Hartley. After settlement two of the constituent councils stopped disposing of their waste streams at Hartley immediately. In time the other two did likewise. Had SWR known of the constituent councils’ contract, arrangement or understanding with the Authority, it claimed it would not have executed the deeds and taken over the landfill. Accordingly, SWR claimed that the Authority had engaged in misleading and deceptive conduct and that it was entitled to damages under the Australian Consumer Law. In the alternative, SWR claimed that the Authority had made misrepresentations inducing SWR to enter into a contract for which SWR was entitled to damages under the Misrepresentations Act 1972 (SA). The Authority denied making the representations and denied that SWR was entitled to the relief it sought.The application to amend the Defence The Authority applied to amend its Defence to incorporate a plea of:1.in relation to the claim of misleading and deceptive conduct, the failure on the part of SWR to take reasonable care to mitigate any loss or damage it may have sustained by reason of the asserted conduct of the Authority within the meaning of s 137B of the Competition and Consumer Act 2010 (Cth) (CACA); and2.in relation to the claim under s 7 of the Misrepresentations Act 1972 (SA), contributory negligence on the part of SWR within the meaning of s 7 of the Law Reform (Contributory Negligence and Apportionment of Liability) Act 2001 (SA).

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established

Contrary to SWR’s contention, counsel for the Authority submitted that the amendments gave no cause for further expert evidence; Mr Levinson’s contention that he would approach an expert to seek an opinion on the nature of the measures that would be taken by a reasonable purchaser in the position of SWR was, in the Authority’s opinion, misguided. The settlement between SWR, the Harveys and the Authority was not an “acquisition of a business” but, rather, an unusual sequence of negotiations between those parties. Thus, evidence of the practice of purchasing a business would be irrelevant to the matters addressed by the proposed amendments, being whether SWR failed to take reasonable care in assuming responsibilities to the Harveys and in negotiating to secure the Authority’s departure from the Harveys’ land. Counsel added that to the extent that expert evidence might be called, it could have been adduced in any event because, even in the absence of a plea of contributory negligence, it would have been relevant to a consideration of the reasonableness of SWR’s conduct and the enquiries it made. Lastly, there was no cause for a further report on quantum because even if the amendment was permitted, it would be for this Court to determine the primary liability of the Authority without regard to contributory negligence, and then, based on a comparison of the parties’ conduct, to apportion that liability between SWR and the Authority in accordance with s 137B CACA.Consideration The Authority’s application was brought eight days into the trial. While delay in the making of the application does not of itself preclude the discretion being exercised granting leave to amend,[6] in Aon, Gummow, Hayne, Crennan, Kiefel and Bell JJ considered that delay in raising a defence would generally necessitate an explanation:[7]The fact that an explanation had been offered for the delay in raising the defence was regarded as a relevant consideration in JL Holdings. Generally speaking, where a discretion is sought to be exercised in favour of one party, and to the disadvantage of another, an explanation will be called for. The importance attached by r 21 to the factor of delay will require that, in most cases where it is present, a party should explain it. Not only will they need to show that their application is brought in good faith, but they will also need to bring the circumstances giving rise to the amendment to the court’s attention, so that they may be weighed against the effects of any delay and the objectives of the Rules. There can be no doubt that an explanation was required in this case.[6] Grapecorp Management Pty Ltd (in liq) v Grape Exchange Management Euston Pty Ltd (2012) 265 FLR 33 at [120].[7] Aon Risk Services Australia Ltd v Australian National University (2009) 239 CLR 175 at [103] It is well established that leave to amend will be more readily granted before a trial date is fixed than at trial.[8] Where an amendment is sought during trial, the applicant bears a heavy burden in justifying the consequent burden to be imposed on the opposing party.[9] [8] Horton v Jones (No 2) (1939) 39 SR (NSW) 305 at 310; Ketteman v Hansel Properties Ltd [1987] AC 189 at 220. [9] Aon Risk Services Australia Ltd v Australian National University (2009) 239 CLR 175 at [4] per French CJ.