Rosecove Pty Ltd v Queensland Building and Construction Commission (costs)

Link copied
Case Copied 49 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Rosecove Pty Ltd v Queensland Building and Construction Commission & Anor (costs) [2024] QCAT 520

PARTIES:

ROSECOVE PTY LTD

(applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(first respondent)

DIAMANTINA SHIRE COUNCIL

(second respondent)

APPLICATION NO/S:

GAR055-18

MATTER TYPE:

General administrative review matters

DELIVERED ON:

29 November 2024

HEARING DATE:

On the papers

HEARD AT:

Brisbane

DECISION OF:

Member Gordon

ORDERS:

The application made by Diamantina Shire Council that Rosecove Pty Ltd pay its costs incurred in the proceedings, is refused.

CATCHWORDS:

ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – costs – builder’s application to review whether a direction to rectify should be issued by the Queensland Building and Construction Commission on the grounds of defective building work – where the Council as owner was joined as a party to the review – where the Council was legally represented and took an active role in the review proceedings – where the direction to rectify was confirmed by the tribunal – where the Council now applies for its costs to be paid by the builder – whether the interests of justice require the tribunal to make an order for costs

Acts Interpretation Act 1954 (Qld), s 32CA

Queensland Building and Construction Commission Act 1991 (Qld), s 71A, s 71J, s 72
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 100, s 102

Queensland Civil and Administrative Tribunal Rules 2009 (Qld), r 86

Bell Lawyers Pty Ltd v Pentalow (2019) 269 CLR 333

Body Corporate for Riverside Hamilton v Queensland Building and Construction Commission & Anor [2020] QCAT 65
Brisbane Marine Pilots Pty Ltd (in liquidation) v General Manager of Maritime Safety Queensland, Department of Transport and Main Roads and Ors (costs) [2022] QCAT 225
Christiansen & Anor v Queensland Building and Construction Commission [2020] QCAT 57
Cowen v Queensland Building and Construction Commission [2021] QCATA 103
Health Ombudsman v du Toit [2024] QCA 235
Holgar v Chief Executive, Department of Justice and Attorney-General & Ors [2022] QCATA 27
Interlink Developments Pty Ltd v Queensland Building and Construction Commission [2020] QCAT 480
MacFarlane v Queensland Building and Construction Commission [2019] QCAT 408
Queensland Building and Construction Commission & Benton v Egan (No 2) [2023] QCATA 163
Rosecove Pty Ltd v Queensland Building and Construction Commission & Ors [2022] QCAT 235
Rosecove Pty Ltd v Queensland Building and Construction Commission & Anor [2023] QCAT 101
Tamawood Ltd & Anor v Paans [2005] QCA 111

Urban Homes Pty Ltd v Queensland Building and Construction Commission [2016] QCAT 131

APPEARANCES & REPRESENTATION:

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)

Applicant:

Construct Law Group

First Respondent:

Did not make submissions about costs

Second Respondent:   

L M Campbell, counsel, instructed by King & Company Solicitors

REASONS FOR DECISION

  1. This is an application for costs in a tribunal review decision involving the Queensland Building and Construction Commission. The QBCC decided that some…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Rosecove Pty Ltd v Queensland Building and Construction Comm... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] QCAT 520
Decision Date

CaseChat Overview and Summary

Rosecove Pty Ltd sought review of a decision of the Queensland Building and Construction Commission (QBCC) to issue a direction to rectify for defective building work. The Diamantina Shire Council, as the owner of the building, was joined as a party to the review proceedings. The Council sought its costs from the builder, Rosecove, for the legal representation it had in the proceedings. The central legal issue was whether the interests of justice required the tribunal to make an order for costs.

The tribunal considered the arguments presented by the builder, which included claims that the joinder of the Council to the proceedings unnecessarily extended the process and incurred further costs. The tribunal found that the builder neither consented nor objected to the Council’s joinder and had not objected to all parties being granted leave to be legally represented. The tribunal held that the legal representation was necessary for the efficient conduct of the proceedings and assisted in reaching the correct decision. The tribunal noted that while the proceedings could have been quicker without the Council, the Council’s involvement was not without purpose and its cross-examination of the builder’s director provided valuable insights.

Ultimately, the tribunal dismissed the Council’s application for costs. The tribunal concluded that while the Council’s involvement added complexity, it was not without merit and did not warrant an order for costs against the builder. The tribunal emphasised that the QBCC had the power to issue a direction to rectify despite the delay in the complaint, which diminished the builder's case.

Orders

Orders of the court

The application made by Diamantina Shire Council that Rosecove Pty Ltd pay its costs incurred in the proceedings, is refused.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

The answer to this in submissions in reply is:[84][84]Submissions in reply on costs 17 August 2023 paragraph 11.In this regard, the District Court proceedings (which are of a broader scope, concern different issues (being for contract and negligence) and another party (the engineer) is of no relevance to whether costs should be awarded in this proceeding. and(the builder) contends that the joinder of the Council to the proceeding unnecessarily lengthened the proceeding and caused further costs to be incurred, and that the joinder of the Council had no utility or purpose due to the District Court proceedings that have been commenced. Again this submission is without basis.By solicitors letter to the Tribunal dated 15 January 2020, (the builder) neither consented nor objected to the Council be joined .. Further, it has never objected to all parties being granted leave to be legally represented. Given the number of issues the Tribunal was required to determine, made clear form the Reasons for the decision, the costs of that legal representation was reasonably incurred and necessary for the efficient conduct of, and assistance to, the Tribunal in reaching the correct and preferable decision.AndThe evidence and submissions provided by Council (and by all the parties) assisted the Tribunal in reaching the correct and preferable decision in respect of the myriad of legal, engineering and factual issues, reflecting the factually intensive nature and substantial complexity of the dispute that was required to be determined.emphasis added Whilst showing appropriate respect for counsel, I regret that I do not agree with the submissions highlighted in bold. From my reading of the file and material before the senior member in the hearing, and from my reading of the transcript of the hearing except for the last day, it is my view that if the active parties had been limited to the builder and the QBCC, the result of the review would have been the same but would have been reached much more quickly. It is my view for example that the builder and the QBCC would have been able to reach consensus about the preliminary issues and probably also the facts, which would have saved a lot of time, and the evidence would probably have been limited to the builder, the QBCC inspector and two experts, so that the hearing would have been much shorter. It is true that, as can be seen from the transcript, the member was assisted by the Council’s cross examination of the builder’s director but it seems to me that the information which assisted the member would have emerged in other ways if that cross examination had not taken place. It is true that the senior member was assisted by the opinions of the Council’s expert, but the QBCC’s expert and the Council’s expert agreed on most points. I do not think there was any need for three experts. It is not compulsory for a party joined to review proceedings to take an active role in the proceedings. As Judicial Member Peter Murphy SC said in Queensland Building and Construction Commission & Benton v Egan (No 2) [2023] QCATA 163, it was ‘entirely open’ for a builder who was supported by the QBCC in an appeal to the Appeal Tribunal to adopt the QBCC’s submissions and have limited representation at the hearing, and doing so is entirely consistent with sections 3(b) and 4(c) of the QCAT Act.[85][85][51].

Ratio Decidendi

Legal Principle Established

That there was merit in the application for review at least when considering the question of fairness is shown by the final submissions filed on behalf of the QBCC which stated:[21]The Commission acknowledges that the discretionary considerations are relatively finely balanced; however, for the reasons indicated herein, the Commissioner’s submission is that it is appropriate for the Applicant to be directed to rectify and therefore the appropriate decision is for the Tribunal to confirm the Commissioner’s decision to issue the Direction to Rectify to the Applicant.emphasis added[21]Final submissions 21 December 2022, paragraph 9. There was a technical issue raised by the builder, which if accepted, would have resulted in the direction to rectify being set aside. It was that the QBCC had no power to issue a direction to rectify in respect of defective work where there had been no complaint by the home owner within 12 months of becoming aware of the defective work as required by section 71J(4) of the Queensland Building and Construction Commission Act 1991 (QBCC Act) and by the 2014 Rectification Policy. This issue was made more difficult to resolve because the 12 months rule had been introduced in two stages straddling the events in this review. The statutory provision in section 71J(4) of the QBCC Act was enacted as from 10 November 2017, whereas the internal review decision to maintain the direction to rectify was on 12 December 2017. There was also a 12 month rule in the Rectification Policy introduced in 2014. Because of these two provisions applying a 12 month time limit for a complaint, there was argument between the parties as to whether these time limits applied in the review. The senior member decided that the QBCC was able to issue a direction to rectify for work even where the complaint was outside the 12 month period and so the answers to this preliminary issue became irrelevant when considering the QBCC’s power to issue a direction to rectify.[22] [22]Decision [35]-[38]. Having asked for submissions on the point, I had reached the same conclusion as the senior member in MacFarlane v Queensland Building and Construction Commission [2019] QCAT 408.[23] In this respect I note that in Urban Homes Pty Ltd v Queensland Building and Construction Commission [2016] QCAT 131 Member Hughes found that the QBCC could issue a direction to rectify even where there was no complaint at all,[24] and this had been cited and followed by Member Traves in Interlink Developments Pty Ltd v Queensland Building and Construction Commission [2020] QCAT 480,[25] and by Member Cranwell in Body Corporate for Riverside Hamilton v Queensland Building and Construction Commission & Anor [2020] QCAT 65 by reference to the 12 month rule. [23][21].[24][37]-[39].[25][23]. In the light of these decisions, it was always unlikely that the senior member could have been persuaded that the QBCC had no power to issue the direction to rectify here because of the delay in making the complaint as the builder submitted. So there was little merit in the builder’s case on this preliminary issue.