QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Rosecove Pty Ltd v Queensland Building and Construction Commission & Anor (costs) [2024] QCAT 520
PARTIES:
ROSECOVE PTY LTD (applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION (first respondent)
DIAMANTINA SHIRE COUNCIL
(second respondent)
APPLICATION NO/S:
GAR055-18
MATTER TYPE:
General administrative review matters
DELIVERED ON:
29 November 2024
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Member Gordon
ORDERS:
The application made by Diamantina Shire Council that Rosecove Pty Ltd pay its costs incurred in the proceedings, is refused.
CATCHWORDS:
ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – costs – builder’s application to review whether a direction to rectify should be issued by the Queensland Building and Construction Commission on the grounds of defective building work – where the Council as owner was joined as a party to the review – where the Council was legally represented and took an active role in the review proceedings – where the direction to rectify was confirmed by the tribunal – where the Council now applies for its costs to be paid by the builder – whether the interests of justice require the tribunal to make an order for costs
Acts Interpretation Act 1954 (Qld), s 32CA
Queensland Building and Construction Commission Act 1991 (Qld), s 71A, s 71J, s 72
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 100, s 102Queensland Civil and Administrative Tribunal Rules 2009 (Qld), r 86
Bell Lawyers Pty Ltd v Pentalow (2019) 269 CLR 333
Body Corporate for Riverside Hamilton v Queensland Building and Construction Commission & Anor [2020] QCAT 65
Brisbane Marine Pilots Pty Ltd (in liquidation) v General Manager of Maritime Safety Queensland, Department of Transport and Main Roads and Ors (costs) [2022] QCAT 225
Christiansen & Anor v Queensland Building and Construction Commission [2020] QCAT 57
Cowen v Queensland Building and Construction Commission [2021] QCATA 103
Health Ombudsman v du Toit [2024] QCA 235
Holgar v Chief Executive, Department of Justice and Attorney-General & Ors [2022] QCATA 27
Interlink Developments Pty Ltd v Queensland Building and Construction Commission [2020] QCAT 480
MacFarlane v Queensland Building and Construction Commission [2019] QCAT 408
Queensland Building and Construction Commission & Benton v Egan (No 2) [2023] QCATA 163
Rosecove Pty Ltd v Queensland Building and Construction Commission & Ors [2022] QCAT 235
Rosecove Pty Ltd v Queensland Building and Construction Commission & Anor [2023] QCAT 101
Tamawood Ltd & Anor v Paans [2005] QCA 111Urban Homes Pty Ltd v Queensland Building and Construction Commission [2016] QCAT 131
APPEARANCES & REPRESENTATION:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
Applicant:
Construct Law Group
First Respondent:
Did not make submissions about costs
Second Respondent:
L M Campbell, counsel, instructed by King & Company Solicitors
REASONS FOR DECISION
This is an application for costs in a tribunal review decision involving the Queensland Building and Construction Commission. The QBCC decided that some…
Keep reading for free
Create a free CaseChat account to read Rosecove Pty Ltd v Queensland Building and Construction Comm... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] QCAT 520
- Decision Date
CaseChat Overview and Summary
The tribunal considered the arguments presented by the builder, which included claims that the joinder of the Council to the proceedings unnecessarily extended the process and incurred further costs. The tribunal found that the builder neither consented nor objected to the Council’s joinder and had not objected to all parties being granted leave to be legally represented. The tribunal held that the legal representation was necessary for the efficient conduct of the proceedings and assisted in reaching the correct decision. The tribunal noted that while the proceedings could have been quicker without the Council, the Council’s involvement was not without purpose and its cross-examination of the builder’s director provided valuable insights.
Ultimately, the tribunal dismissed the Council’s application for costs. The tribunal concluded that while the Council’s involvement added complexity, it was not without merit and did not warrant an order for costs against the builder. The tribunal emphasised that the QBCC had the power to issue a direction to rectify despite the delay in the complaint, which diminished the builder's case.
Orders
Orders of the court
The application made by Diamantina Shire Council that Rosecove Pty Ltd pay its costs incurred in the proceedings, is refused.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
That there was merit in the application for review at least when considering the question of fairness is shown by the final submissions filed on behalf of the QBCC which stated:[21]The Commission acknowledges that the discretionary considerations are relatively finely balanced; however, for the reasons indicated herein, the Commissioner’s submission is that it is appropriate for the Applicant to be directed to rectify and therefore the appropriate decision is for the Tribunal to confirm the Commissioner’s decision to issue the Direction to Rectify to the Applicant.emphasis added[21]Final submissions 21 December 2022, paragraph 9. There was a technical issue raised by the builder, which if accepted, would have resulted in the direction to rectify being set aside. It was that the QBCC had no power to issue a direction to rectify in respect of defective work where there had been no complaint by the home owner within 12 months of becoming aware of the defective work as required by section 71J(4) of the Queensland Building and Construction Commission Act 1991 (QBCC Act) and by the 2014 Rectification Policy. This issue was made more difficult to resolve because the 12 months rule had been introduced in two stages straddling the events in this review. The statutory provision in section 71J(4) of the QBCC Act was enacted as from 10 November 2017, whereas the internal review decision to maintain the direction to rectify was on 12 December 2017. There was also a 12 month rule in the Rectification Policy introduced in 2014. Because of these two provisions applying a 12 month time limit for a complaint, there was argument between the parties as to whether these time limits applied in the review. The senior member decided that the QBCC was able to issue a direction to rectify for work even where the complaint was outside the 12 month period and so the answers to this preliminary issue became irrelevant when considering the QBCC’s power to issue a direction to rectify.[22] [22]Decision [35]-[38]. Having asked for submissions on the point, I had reached the same conclusion as the senior member in MacFarlane v Queensland Building and Construction Commission [2019] QCAT 408.[23] In this respect I note that in Urban Homes Pty Ltd v Queensland Building and Construction Commission [2016] QCAT 131 Member Hughes found that the QBCC could issue a direction to rectify even where there was no complaint at all,[24] and this had been cited and followed by Member Traves in Interlink Developments Pty Ltd v Queensland Building and Construction Commission [2020] QCAT 480,[25] and by Member Cranwell in Body Corporate for Riverside Hamilton v Queensland Building and Construction Commission & Anor [2020] QCAT 65 by reference to the 12 month rule. [23][21].[24][37]-[39].[25][23]. In the light of these decisions, it was always unlikely that the senior member could have been persuaded that the QBCC had no power to issue the direction to rectify here because of the delay in making the complaint as the builder submitted. So there was little merit in the builder’s case on this preliminary issue.