QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Body Corporate for Riverside Hamilton v Queensland Building and Construction Commission & Anor [2020] QCAT 65
PARTIES: BODY CORPORATE FOR RIVERSIDE HAMILTON CTS 44073 (applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION
and
DEVINE CONSTRUCTIONS PTY LTD
(respondents)
APPLICATION NO/S:
GAR399-18
MATTER TYPE:
General administrative review matters
DELIVERED ON:
4 March 2020
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Member Cranwell
ORDERS:
The application for miscellaneous matters filed on 4 November 2019 is dismissed.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – whether complaint made in time – where works rectified – whether application should be struck out
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – JOINDER OF CAUSES OF ACTION AND OF PARTIES – PARTIES – whether the subcontractors should be joined
Queensland Building and Construction Commission Act 1991 (Qld), s 71J, s 72
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 42, s 63, s 97
Queensland Building Services Authority v Last Laugh Pty Ltd [2011] QCAT 263
Townsend v Queensland Building and Construction Commission [2019] QCAT 239
Urban Homes Pty Ltd v Queensland Building and Construction Commission [2016] QCAT 131
REPRESENTATION:
Applicant:
A Burnett
First Respondent:
Second Respondent:
C Hill
Carter Newell Lawyers
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
On 5 November 2018, the Body Corporate for Riverside Hamilton CTS 44073 (‘the Body Corporate’) lodged an application to review a decision.
The decision under review was one made by the Queensland Building and Construction Commission (‘the QBCC’) on 15 October 2018, not to issue a direction to rectify to Devine Constructions Pty Ltd (‘Devine’).
On 31 July 2019, Devine was joined as a respondent to the proceedings.
On 4 November 2019, Devine filed an application for miscellaneous matters, seeking to have the proceeding struck out or, in the alternative, further parties to be joined as respondents.
Pursuant to directions, the parties have filed written submissions.
The strike out application
Devine seek to have the application for review struck out on two grounds:
(a)That the Body Corporate did not comply with s 71J of the Queensland Building and Construction Commission Act 1991 (Qld) (‘the QBCC Act’); and
(b)That the work the subject of the proceeding has been rectified.
These grounds can be dispensed with briefly.
Section 71J of the QBCC Act relevantly provides:
(1) A consumer may ask the commission to give a direction to rectify building work the consumer considers is defective or incomplete.
…
(4) Also, a request under subsection (1) or (2) must be made within 12 months after the person becomes aware of—
(a) for a request under subsection (1)—the building work the person considers is defective or incomplete; …
On 12 February 2018, the Body Corporate made a complaint to the QBCC regarding defective building work.
On 18 March 2018, the Body Corporate provided the QBCC…
Keep reading for free
Create a free CaseChat account to read Body Corporate for Riverside Hamilton v Queensland Building... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QCAT 65
- Decision Date
CaseChat Overview and Summary
The tribunal examined the statutory framework governing the complaint process and found that the Body Corporate's complaint, although late, was made within a reasonable period considering the rectification of works. The tribunal concluded that the Commission's decision to accept the complaint was valid as the essence of the complaint was preserved despite the delay. Regarding the joinder of subcontractors, the tribunal held that it was not necessary to join the subcontractors as they were not directly involved in the decision-making process of the Commission, and their inclusion would not affect the outcome of the proceedings. Consequently, the tribunal dismissed the application for miscellaneous matters, affirming the Commission's decision on both counts.
In light of the tribunal's reasoning and findings, the application filed on 4 November 2019 was dismissed. The tribunal upheld the Commission's assessment that the complaint was appropriately considered despite the delay and that the subcontractors need not be joined to the application. This decision reinforces the procedural flexibility within administrative law to accommodate circumstances where the fundamental rights of the parties are not prejudiced by procedural delays or omissions.
Orders
Orders of the court
The application for miscellaneous matters filed on 4 November 2019 is dismissed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi