Paul Wayne Townsend v Queensland Building and Construction Commission

Link copied
Case Copied 19 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Paul Wayne Townsend v Queensland Building and Construction Commission  [2019] QCAT 239

PARTIES: PAUL WAYNE TOWNSEND T/AS MRT’S HANDYMANS & LANDSCAPES

(applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(respondent)

APPLICATION NO/S:

OCR131-18

MATTER TYPE:

Occupational regulation matters

DELIVERED ON:

19 August 2019

HEARING DATE:

30 January 2019

31 July 2019

HEARD AT:

Brisbane

DECISION OF:

Member Gardiner

ORDERS:

1.   The decision of the Queensland Building and Construction Commission made on 26 April 2018, to issue a direction to Paul Wayne Townsend to cause the rectification of building work is confirmed.

CATCHWORDS:

PROFESSION AND TRADES – BUILDERS, LICENCES AND REGISTRATION – WHERE unlicensed builder built defective block wall – WHERE direction to rectify issued – WHERE wall remediated by a third party – WHERE no defects for builder to rectify – WHERE builder reviews direction – WHERE question arose as to what point in time the review should be based - before or after remediation by third party – WHETHER review should proceed under QBCC Act or QCAT Act

Acts Interpretation Act 1954 (Qld): s14
Queensland Building and Construction Commission Act 1991 (Qld): s72, s86
Queensland Civil and Administrative Tribunal Act 2009 (Qld): s20, s24, s28
Queensland Building and Construction Regulation 2018: Sched 1, Sched 2

Davis & Santelli v The Body Corporate Westminster House Clayfield [2016] QCATA 132
Freeman v Secretary, Department of Social Security (1989) 87 ALR 506
Hospital Benefit Fund of Western Australia Inc v Minister for Health, Housing and Community Services (1992) 111 ALR 1
Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355

Shi v Migration Agents Registration Authority (2008) 235 CLR 286

APPEARANCES & REPRESENTATION:

Applicant:

Self-represented

Respondent:

N Glen, In house lawyer for the Queensland Building and Construction Commission

REASONS FOR DECISION

  1. On 26 April 2018, the Queensland Building and Construction Commission issued Mr Paul Wayne Townsend, an unlicensed building contractor, with a written direction to rectify certain building work under section 72(2)(a) of the Queensland Building and Construction Commission Act 1991 (the “QBCC Act"). The work was a block retaining wall on a house site.

  2. The defective work has been completely remediated by a third party who now has responsibility for the ongoing work under the QBCC Act, not Mr Townsend. There is no work to be remediated by Mr Townsend.

  3. On 16 May 2018, Mr Townsend filed a review of the decision to issue the direction to rectify.

  4. The purpose of the review is to produce the correct and preferable decision. The review is determined by way of a fresh hearing on the merits.[1] 

    [1]          Queensland Civil and Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’), s 20

  5. At the first day of hearing of this review application on 30 January 2019, the Tribunal posed the following question and sought submissions from both parties as to the direction the Tribunal should take:

    “In circumstances where a direction to rectify has been issued by the Queensland Building and Construction Commission (QBCC) and…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Paul Wayne Townsend v Queensland Building and Construction C... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] QCAT 239
Decision Date

CaseChat Overview and Summary

Paul Wayne Townsend, an unlicensed builder, was involved in a dispute with the Queensland Building and Construction Commission (QBCC) concerning a defective block wall he had constructed. Following an inspection, the QBCC issued a direction to Mr Townsend to rectify the defective work. However, before Mr Townsend could comply, a third party had already remediated the defect. Consequently, when the QBCC reviewed the direction, there were no defects remaining for Mr Townsend to rectify. The central issue before the court was determining the appropriate point in time for the review of the direction to proceed – whether it should be based on the state of affairs before or after the third party's remediation. The court had to consider whether the review should proceed under the provisions of the Queensland Building and Construction Commission Act 1999 or the Queensland Civil and Administrative Tribunal Act 2009.

The court examined the legislative framework to ascertain the correct point in time for the review. It determined that the review should be based on the state of affairs at the time the direction was issued, rather than the time of remediation by the third party. The court found that the QBCC's decision to issue the direction to Mr Townsend to rectify the defective work was valid, as the defect existed at the time of issuance. Despite the third party's remediation, the court confirmed that the decision of the QBCC made on 26 April 2018, to issue a direction to Paul Wayne Townsend to cause the rectification of building work, remained valid and should be upheld.

The court's decision affirmed the Queensland Building and Construction Commission's authority to issue a direction to rectify defective work, even if the defect has already been remedied by a third party. The court held that the QBCC's decision should be based on the state of affairs at the time the direction was issued, rather than the time of remediation. This ruling underscores the importance of timely compliance with building regulations and the consequences of failing to obtain the necessary licenses and registrations.

Orders

Orders of the court

1. The decision of the Queensland Building and Construction Commission made on 26 April 2018, to issue a direction to Paul Wayne Townsend to cause the rectification of building work is confirmed.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.