JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
ACT: STRATA TITLES ACT 1985 (WA)
CITATION: REILLY and PERKINS HOLDINGS (WA) PTY LTD [2025] WASAT 81
MEMBER: MS R PETRUCCI, MEMBER
HEARD: 10 FEBRUARY 2025
FINAL WRITTEN SUBMISSION FILED 8 MAY 2025
DELIVERED : 6 AUGUST 2025
FILE NO/S: CC 281 of 2024
BETWEEN: GAIL LORRAINE REILLY
First Applicant
PAUL JULIAN ROLLS REILLY
Second Applicant
AND
PERKINS HOLDINGS (WA) PTY LTD
First Respondent
THE OWNERS OF THE WESTRALIAN STRATA SCHEME 47949
Second Respondent
Catchwords:
Strata Titles Act 1985 (WA) - Application by proprietors seeking compliance with scheme by-laws - Standing - Alleged contravention of scheme conduct by-laws - Noise - Transmission of noise - Floor coverings - Amendment of floor coverings by-law after installation of different floor covering - Proper construction of 'floor coverings' by-law - Whether floor coverings sufficient to prevent transmission of noise likely to disturb other proprietors - Objective test - Whether breach of by-law established - Expert acoustic evidence - Role of strata company to enforce scheme by-laws - Lack of action by strata company - Factors to consider in exercising statutory discretion to make orders - Turns on own facts
Legislation:
Interpretation Act 1984 (WA)
State Administrative Tribunal Act 2004 (WA), s 9, s 32, s 84
Strata Titles Act 1985 (WA), s 39, s 39(b), s 44, s 45, s 45(2), s 45(4), s 46(j), s47(1)(a), s 47(1)(b), s 47(1)(c), s 47(3), s 47(3)(a), s 47(4), s 47(4)(b), s47(4)(c), s 47(5), s 47(5)(b), s 48, s 197, s 197(1)(a), s 197(2), s 197(2)(a), s197(2)(d), s197(4), s 200, s 200(2)(m), Pt 4, Div 4
Result:
Application partly successful
Category: B
Representation:
Counsel:
| First Applicant | : | Ms T Watson and Mr S Bell |
| Second Applicant | : | Ms T Watson and Mr S Bell |
| First Respondent | : | Mr DJ Pratt |
| Second Respondent | : | N/A |
Solicitors:
| First Applicant | : | Douglas Lawyers |
| Second Applicant | : | Douglas Lawyers |
| First Respondent | : | Jackson McDonald |
| Second Respondent | : | N/A |
Case(s) referred to in decision(s):
Ainsworth v Albrecht 2016 HCA 40; (2016) 261 CLR 167
Byrne v The Owners of Ceresa River Apartments Strata Plan 55597 [2016] WASC 153
Byrne v The Owners of Ceresa River Apartments Strata Plan 55597 [2017] WASCA 104
Coal and Allied Operations Pty Ltd v Australian Industrial Relations Commission [2000] HCA 47; (2000) 203 CLR 194
Erbrich and The Owners Of 125 Herdsman Parade Wembley (Strata Plan 38066) [2020] WASAT 109
Felcher v The Owners Strata Plan No 2738 [2017] NSWCATAP 219
Feletti v Eales [2018] NSWCATCD 66
Friday and Luck [2014] WASAT 109
Gao v Agosti [2009] NSWCTTT 175
George v Rockett [1990] HCA 26; [1990] 170 CLR 104
Kruger v The Commonwealth of Australia (1997) 190 CLR 1
Minister for Immigration and Citizenship v Li [2013] HCA 18
Nowak v Pellicciotti [2018] NSWCATAP 245
Opera House Investment Pty Ltd v Devon Buildings Pty Ltd [1936] HCA 14; [1936] 55 CLR 110
Schubert and Huang [2020] WASAT 63
Swannell v Lilliman [2004] WADC 72
The Owners - Strata…
Keep reading for free
Create a free CaseChat account to read REILLY and PERKINS HOLDINGS (WA) PTY LTD and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2025] WASAT 81
- Decision Date
CaseChat Overview and Summary
The court had to determine the proper construction of the 'floor coverings' by-law, whether the applicants' floor coverings were sufficient to prevent noise transmission, and whether the applicants had breached the by-law. The applicants argued that the by-law was ambiguous and that their floor coverings were adequate. They also contended that the strata company had not enforced the by-laws, which impacted the applicants' standing to seek enforcement. The court had to consider expert acoustic evidence and the role of the strata company in enforcing the by-laws.
The court found that the by-law was clear and objective, requiring all floor space within a lot to be covered or treated to prevent noise transmission. The applicants' floor coverings did not meet the required standards, and the applicants had failed to provide the necessary acoustic report. The court rejected the applicants' argument that the strata company's inaction affected their standing, holding that the applicants had standing to seek enforcement of the by-laws. The court emphasised that the by-law was clear and objective, and that the applicants had failed to comply with it.
The court made orders requiring the applicants to rectify their floor coverings to meet the by-law standards, including obtaining necessary approvals and permits, and providing an acoustic report. The court also noted that the strata company had a role in enforcing the by-laws, but that the applicants' inaction did not affect their standing to seek enforcement. The court's decision emphasised the importance of clear and objective by-laws, and the role of the strata company in enforcing them.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
By-law 4 of Sch 2 of the management statement is relevant in that it required:4.Alterations to a lot4.1A proprietor shall not commence any structural alterations building or associated works of any kind to his lot before he has:4.1.1obtained all the necessary approvals and permits of the local authority;4.1.2obtained the consent of the strata company in the structural alternations are prescribed improvements within the meaning of section 7 of the Act.4.1.3given the strata company at least 14 days written notice of the proposed structural alterations and the date that work is to commence and true and complete copies of all relevant plans and specifications in respect thereto and the approvals and permits obtained from the local authority pursuant to bylaw 4.1.1.4.1.4indemnified the strata company in respect of any cost expense or liability that may be incurred by the strata company consequent upon the proprietor undertaking the structural alterations building or associated works which indemnity shall be in writing in a form reasonably by the strata company and prepared and stamped at the cost of the proprietor. On 21 January 2015 (by instrument M8902348) there were changes to the management statement. This included repealing the Sch 2 conduct by-laws and inserting a new Sch 2 conduct by-laws numbered 1 to 30 which included a new conduct by-law 16 regarding floor coverings as follows (by-law 16):16Floor coverings16.1Proprietors and occupiers must ensure that all floors within their lot (other than that comprising kitchen, laundry, lavatory and bathroom) is covered or otherwise treated to an extent sufficient to prevent the transmission from those floors to another lot of noise likely to disturb the peaceful enjoyment of the proprietor or occupier of another lot.16.2Without limiting the requirements of sub-bylaw 16.1, if a proprietor or occupier is utilising a floor covering other than carpet, then:16.2.1any floor finish must achieve single representative impact isolation to satisfy the BCA requirements or 40dB, whichever is the lower; and16.2.2the proprietors or occupier must provide the strata company with an acoustic report signed by an acoustic engineer or other appropriately qualified person certifying that the floor covering meets the requirements of this by-law. On 27 November 2020, (by instrument O568889), the scheme bylaws were consolidated (the by-laws). Various by-laws were repealed (including by-law 16) in the consolidation process and a new by-law 11 for flooring coverings was added as follows (by-law 11):11Floor coverings11.1Each proprietor must ensure that all floor space within its lot is covered or otherwise treated with materials approved by the strata company to an extent sufficient to prevent the transmission of noise likely to disturb other proprietors.11.2If the strata company reasonably determines that a proprietor is not complying with by-law 11.1, the strata company may (without limiting any of the strata company's other rights) issue the proprietor with a notice requiring the proprietor to advise the strata company of the rectification works that it proposes to undertake within 14 days (Rectification Works).11.3The Rectification Works must:11.3.1comply with all Australian Standards and the Building Code of Australia as applicable to sound proofing; and11.3.2any floor finish must achieve an LnT,w rating to satisfy the BCA requirements or 50 dB, whichever is the lower rating or meet any other minimum standard for acoustic performance set by the council of the strata company (Acoustic Standard).11.4The proprietor must arrange for the Rectification Works to be completed within 60 days of the strata company approving the Rectification Works.11.5Subject to by-laws 11.1 to 11.4, a proprietor:11.5.1must obtain the council's prior written consent before replacing the floor finish within the proprietor's lot; and11.5.2acknowledges that the council may withhold the consent where the replacement floor finish will not meet the Acoustic Standard.11.6Each proprietor will:11.6.1to the extent reasonably possible, only use footwear in its lot; and11.6.2if necessary, ensure that all furniture in its lot is fitted at all times with suitable floor pad,that will prevent the transmission of noise likely to disturb any other proprietor.