Rawson Homes Pty Ltd v Allianz Australia Insurance Limited

Link copied
Case Copied 40 min read

Supreme Court


New South Wales

Medium Neutral Citation: Rawson Homes Pty Ltd v Allianz Australia Insurance Limited [2020] NSWSC 1654
Hearing dates: 17 and 18 August 2020; further written submissions 19 August 2020
Date of orders: 20 November 2020
Decision date: 20 November 2020
Jurisdiction:Equity - Commercial List
Before: Henry J
Decision:

Judgment for the plaintiff. See paragraph [112].

Catchwords:

INSURANCE – annual construction insurance policy – where hailstorm caused damage to residential development being constructed by plaintiff – whether one deductible payable for plaintiff’s claim for cover or whether a deductible is payable in respect of each building works contract – meaning of “one event” and “claim” – held that hailstorm was the one event that gave rise to the plaintiff’s claim and one deductible payable

INSURANCE – calculation of interest under s 57 of the Insurance Contracts Act 1984 (Cth) – where defendant rejected plaintiff’s claim for cover to replace damaged tiled roofs until second day of hearing – date from which it was unreasonable for defendant to withhold payment – held that 13 month period to investigate claim and determine position was reasonable and interest payable from 29 March 2018

Legislation Cited:

Insurance Contracts Act 1984 (Cth), s 57.

Uniform Civil Procedure Rules 2005 (NSW), r 42.1

Cases Cited:

Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99; [1973] HCA 36

Australian Casualty Co Limited v Federico (1986) 160 CLR 513; [1986] HCA 32

Australian Pipe & Tube Pty Ltd v QBE Insurance (Australia) Limited (No 2) [2018] FCA 1450

Axa Reinsurance (UK) Plc v Field [1996] 1 WLR 1026

Bankstown Football Club Limited v CIC Insurance Limited (Supreme Court (NSW), Cole J, 17 December 1993, unrep)

Darlington Futures Ltd v Delco Australia (1986) 161 CLR 500; [1986] HCA 82

Electricity Generation Corporation v Woodside Energy Limited (2014) 251 CLR 640; [2014] HCA 7

Fitzgerald v CBL Insurance Ltd [2014] VSC 493

HIH Casualty & General Insurance v Insurance Australia Ltd (No 2) [2006] VSC 128

McCann v Switzerland Insurance Australia Limited (2000) 203 CLR 579; [2000] HCA 65

MetLife Insurance Ltd v RGA Reinsurance Company of Australia Ltd [2017] NSWCA 56

Mount Bruce Mining Pty Limited v Wright Prospecting Pty Limited (2015) 256 CLR 104; [2015] HCA 37

O’Neill v FSS Trustee Corporation as trustee of the First State Superannuation Scheme [2015] NSWSC 1248

Provincial Insurance Aust Pty Ltd v Consolidated Wood Products (1991) 25 NSWLR 541

Quintano v B W Rose Pty Ltd [2008] NSWSC 793

Ransley v Chubb Insurance Company of Australia Ltd [2015] NSWSC 1350

Sayseng v Kellogg Superannuation Pty Ltd (2007) 213 FLR 174; [2007] NSWSC 857

Tempe Recreation (D.500215 and D.1000502) Reserve Trust v Sydney Water Corporation (2014) 88 NSWLR 449; [2014] NSWCA 437

Walton v National Employers' Mutual General Insurance Association Ltd [1973] 2 NSWLR 73

Weir Services Australia Pty Ltd v AXA Corporate Solutions Assurance [2018] NSWCA 100

Wilkie v Gordian Runoff Ltd (2005) 221 CLR 522

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Rawson Homes Pty Ltd v Allianz Australia Insurance Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] NSWSC 1654
Decision Date

CaseChat Overview and Summary

Rawson Homes Pty Ltd sought compensation from Allianz Australia Insurance Limited for damages incurred at their construction site due to a hailstorm. The plaintiff argued that the hailstorm constituted one event and that Allianz should only have to pay one deductible for the claim. Allianz, on the other hand, argued that a separate deductible should be paid for each building works contract. The matter was brought before the court to determine the correct interpretation of the terms "one event" and "claim" in the annual construction insurance policy.

The court needed to decide whether the hailstorm should be considered as one event or multiple events, and whether a single deductible or multiple deductibles were applicable. Additionally, the court had to determine the appropriate date from which interest should be payable on the claim under section 57 of the Insurance Contracts Act 1984 (Cth). The court's decision would hinge on the interpretation of the policy and the reasonableness of Allianz's delay in processing the claim.

The court found that the hailstorm was the one event that gave rise to the plaintiff's claim, and thus one deductible was payable. The court considered Allianz's 13-month investigation period to be reasonable and determined that interest should be payable from 29 March 2018, the second day of the hearing, as it was unreasonable for Allianz to withhold payment from this date.

The final orders of the court were that Allianz was liable to pay one deductible for the hailstorm damage and interest from 29 March 2018. The court's decision provided clarity on the interpretation of policy terms and the calculation of interest in insurance claims, and established the appropriate timeline for Allianz's payment obligations.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established