Perform (NSW) Pty Ltd v Mev-Aus Pty Ltd

Link copied
Case Copied 22 min read
CITATION: Perform (NSW) Pty Ltd v Mev-Aus Pty Ltd trading as Novatec Construction Systems [2009] NSWSC 416
HEARING DATE(S): 1 and 4 May 2009
JURISDICTION: Equity Division
Technology & Construction List
JUDGMENT OF: Rein J at 1
EX TEMPORE JUDGMENT DATE: 5 May 2009
DECISION: 1. The defendant be permanently restrained from taking any steps to prosecute any adjudication of the second payment claim.
2. The defendant to pay the plaintiff's costs of the proceedings.
CATCHWORDS: CONTRACTS – building, engineering and related contracts – other matters – Building and Construction Industry Security of Payment Act 1999 – second payment claim for items the subject of a previous claim – second claim is precluded by principles of estoppel and the provisions of the Act – appropriate for the Court to intervene prior to an adjudication determination to prevent such a claim from proceeding - ESTOPPEL – issue estoppel – adjudication under Building and Construction Industry Security of Payment Act 1999
LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999
CATEGORY: Principal judgment
CASES CITED: Australian Remediation Services Pty Ltd v Earth Tech Engineering Pty Ltd [2005] NSWSC 362
Boutique Developments Limited v Construction and Contract Services [2007] NSWSC 1042
Bryanston Finance Ltd v de Vries (No. 2) [1976] Ch 63
Buying Systems (Australia) Pty Ltd v Tien Mah Litho Printing Co (PTE) [1986] 5 NSWLR 317
Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69
Energetech Aust Pty Ltd v Sides Engineering Pty Ltd [2005] 226 ALR 362
John Goss Projects v Leighton Contractors & Anor [2006] NSWSC 798
Lifestyle Retirement Projects No.2 Pty Ltd v Parisi Homes Pty Ltd [2005] NSWSC 411
Walton v Gardiner (1993) 177 CLR 378
PARTIES: Perform (NSW) Pty Ltd (Plaintiff)
Mev-Aus Pty Ltd t/as Novatec Construction Systems (Defendant)
FILE NUMBER(S): SC 55033/09
COUNSEL: Mr N A Nicholls (Plaintiff)
Dr A J Greinke (Defendant)
SOLICITORS: Wilkinson Building & Construction Lawyers (Plaintiff)
Doyles Construction Lawyers (Defendant)

1

IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY & CONSTRUCTION LIST

Rein J

Date of Hearing: 1 & 4 May 2009
Date of Judgment: 5 May 2009

55033/09 PERFORM (NSW) PTY LTD v MEV-AUS PTY LTD T/AS NOVATEC CONSTRUCTION SYSTEMS


In this matter Perform (NSW) Pty Ltd (“Perform”), for whom Mr Nicholls of counsel appears, was a formwork contractor on two buildings jobs, one on the Sydney Airport car park (“car park”) and the other the City North Substation (“substation”). Perform hired formwork materials from the defendant company Mev-Aus Pty Ltd (“Mev”), for whom Dr Greinke of counsel appears.


2. There is no dispute that Perform accepted a quotation of 19 February 2007 from Mev addressed to somebody else: see p 10, tab 3 of the annexure to Mr Wilkinson’s affidavit dated 29 April 2009 (“Mr Wilkinson’s affidavit”), the plaintiff's solicitor, and that option (b) described as "MEVA FTA & HM" was chosen by Perform. There is no dispute that the contract was a construction contract within the meaning on the Building and…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Perform (NSW) Pty Ltd v Mev-Aus Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2009] NSWSC 416
Decision Date

CaseChat Overview and Summary

In the case of Perform (NSW) Pty Ltd v Mev-Aus Pty Ltd, the dispute involved a contractual arrangement between two companies within the construction industry. The central issue was whether a second payment claim could be made by Mev-Aus Pty Ltd for items already claimed in a previous payment claim. The matter was heard in the Supreme Court of New South Wales. The court was required to determine whether the principles of estoppel and the provisions of the Building and Construction Industry Security of Payment Act 1999 precluded the second payment claim.

The court examined whether issue estoppel could apply to prevent Mev-Aus Pty Ltd from reasserting claims that had already been adjudicated upon. The Act allows for an adjudication process to resolve disputes over payment claims, but the court held that it was within its purview to intervene prior to an adjudication determination when it was clear that a claim was precluded by estoppel. The court concluded that the second payment claim was indeed precluded by the principles of estoppel and the specific provisions of the Act. The court held that the second claim should not proceed as it was effectively res judicata due to the estoppel effect and the statutory framework.

The Supreme Court of New South Wales found in favour of Perform (NSW) Pty Ltd, ruling that the second payment claim by Mev-Aus Pty Ltd was precluded by issue estoppel and the provisions of the Building and Construction Industry Security of Payment Act 1999. The court's decision underscored the importance of the estoppel principles in preventing repetitive claims and maintaining the integrity of the adjudication process under the Act. Consequently, the court issued an order preventing Mev-Aus Pty Ltd from proceeding with the second payment claim, affirming the finality and binding nature of the initial adjudication.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.