CITATION: Lifestyle Retirement Projects No 2 Pty Ltd v Parisi Homes Pty Ltd & Anor [2005] NSWSC 411
HEARING DATE(S): 22 April, 2005
JUDGMENT DATE :
22 April 2005JURISDICTION: Equity Division
JUDGMENT OF: Palmer J
DECISION: Application for interlocutory injunction refused.
CATCHWORDS: BUILDING AND CONSTRUCTION - ADJUDICATION - INJUNCTION - Plaintiff alleges facts which, if proved, would result in invalidity of adjudication under Building and Construction Industry Security of Payment Act 1999 - Plaintiff seeks interlocutory injunction restraining any further step in adjudication process until final hearing of question of validity.
LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999 - s.13(4), s.14(4), s.17(1), s.25(1)
CASES CITED: - Australian Mediation Services Pty Ltd v Earth Tech Engineering Pty Ltd [2005] NSWSC 362
- Brodyn Pty Ltd v Davenport [2004] NSWCA 394PARTIES: Lifestyle Retirements Projects No 2 Pty Ltd - Plaintiff
Parisi Homes Pty Ltd - First Defendant
Mediate Today Pty Ltd - Second DefendantFILE NUMBER(S): SC 2521/05
COUNSEL: I. Roche - Plaintiff
E. Olsson - First DefendantSOLICITORS: Hancock Alldis & Roskov - Plaintiff
Philip Davenport - Second Defendant
LOWER COURT JURISDICTION:
1 The Plaintiff seeks an injunction restraining any further step being taken in an adjudication under the Building and Construction Industry Security of Payment Act 1999 . 2 The basis of the application is that there is a dispute as to whether a payment claim was served by the First Defendant within the time prescribed under s.13(4) of the Act and whether a payment schedule served by the Plaintiff was served within the time prescribed by s.14(4) of the Act. If the payment claim is found to have been served outside the time prescribed by s.13(4) then, of course, the subject matter of that payment claim may not be agitated in the present adjudication. If the payment schedule is found to have been served within the time prescribed by s.14(4) then the First Defendant was not entitled to apply, as it did, for an adjudication under s.17(1)(b). 3 The Plaintiff says that if either of the contested facts is found in its favour an essential foundation for the validity of the adjudication will be lacking; it submits that the Court should now entertain an application for an interim order restraining any further step in the adjudication until final determination in this Court of the question whether or not the adjudication will be valid. 4 I think that the Plaintiff’s application should be declined. It has been made clear by McDougall J in Australian Remediation Services Pty Ltd v Earth Tech Engineering Pty Ltd [2005] NSWSC 362 and in the authorities to which his Honour there refers that the existence of a fact necessary for the validity of an adjudication is a matter within the competence of the adjudicator to determine. If an adjudicator erroneously finds a fact essential to jurisdiction and an adjudication certificate issues accordingly, it is always open to a party adversely affected to seek to set aside any judgment sought to be entered under s.25(1) of the Act on the ground that the adjudication was, in truth, a nullity because an essential ingredient of jurisdiction was absent: Brodyn Pty Ltd v Davenport [2004] NSWCA 394, at para 42 per Hodgson JA, with whom the other members of the Court agreed. 5 In the present case the adjudicator may find that the payment claim was served outside the prescribed time or that the payment schedule was served within the prescribed time. In either case, the Plaintiff would have no complaint about jurisdiction. If the adjudicator found either fact adversely to the Plaintiff, the Plaintiff still has the chance to set aside any judgment entered under s.25(1) in the way I have explained. 6 In these circumstances, it seems to me to be contrary to authority and contrary to the policy of the Act to entertain this application. I respectfully adopt what was said by McDougall J in Australian Remediation Services Pty Ltd v Earth Tech Engineering Pty Ltd (supra) at para.13:Ex tempore
7 The application is, therefore, dismissed. I order that the Plaintiff pay the First Defendant’s costs of the application.
In circumstances where the legislature has enacted the legislation to provide, as s.3 of the Act makes clear, a scheme to ensure that any person who undertakes to carry out construction work or supply related goods and services is entitled to recover, and is able to recover, progress payments, I think that this Court should think long and hard before interfering in the implementation, in a particular case, of that statutory scheme.”“… the legislature has made it quite clear that it is adjudicators under the Act who are the primary organs for the resolution of these disputes. The power of this Court comes in either to enforce the determination (a power shared with other courts) or, in the limited circumstances described in Brodyn , to restrain enforcement of the determination. The whole scheme of the Act, as Palmer J said in Multiplex Constructions Pty Ltd v Luikens & Anor [2003] NSWSC 1140, is one of ‘pay now, argue later’ . It is clear from the provisions of s.32 of the Act that the time for final adjustment of rights and remedies is later.
– oOo –
- AGLC
- Lifestyle Retirement Projects No 2 Pty Ltd v Parisi Homes Pty Ltd [2005] NSWSC 411
- Case
- [2005] NSWSC 411
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the plaintiff's allegations, if established, would indeed render the adjudication invalid, and if so, whether an interlocutory injunction was appropriate to restrain further steps in the adjudication process until the final hearing. The court was tasked with determining the balance between the rights of the parties under the Security of Payment Act and the potential prejudice that could result from allowing the adjudication to proceed.
The court considered the statutory framework of the Security of Payment Act, which aims to ensure timely payments in the building and construction industry. It emphasised the importance of prompt adjudication to maintain cash flow and avoid significant financial disruption. The court also noted that the Act provides a relatively quick and inexpensive mechanism for resolving payment disputes. Balancing these considerations with the need to protect the rights of the parties, the court found that the plaintiff's allegations, even if proven, did not necessarily render the adjudication invalid. Consequently, the court declined to grant the interlocutory injunction, allowing the adjudication process to continue.
The court's decision was based on the premise that the adjudication process should not be unduly hindered unless there was a clear risk of irreparable harm or significant injustice. The court concluded that the plaintiff had not demonstrated such a risk, and thus, the interlocutory injunction was denied. The court's ruling underscored the importance of adhering to the statutory framework designed to facilitate timely dispute resolution in the construction industry.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.