SUPREME COURT OF QUEENSLAND
CITATION:
Securcorp Limited v Civil Mining & Construction P/L
[2009] QSC 249PARTIES:
SECURCORP LIMITED
(applicant)v
CIVIL MINING & CONSTRUCTION PTY LIMITED
(respondent)FILE NO/S:
BS 7475 of 2009
DIVISION:
Trial Division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
27 August 2009
DELIVERED AT:
Brisbane
HEARING DATE:
25 August 2009
JUDGE:
McMurdo J
ORDER:
Upon the undertaking by the respondent through its counsel that it will not serve any further payment claim under the Building and Construction Industry Payments Act 2004 (Qld) arising out of the project known as the Riverview Estate subdivision it will be ordered that:
1. The Originating Application is dismissed.
2. There will be no order as to costs.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – OTHER MATTERS – where the Building and Construction Industry Payments Act 2004 (Qld) sets out a regime for making a payment claim under a construction contract – where the respondent undertook not to serve any further payment claim – where the applicant seeks a declaration that it is not liable to pay the respondent for building work – where there is extensive evidence on behalf of the applicant that there is no basis for a claim by the respondent – where the lack of evidence to the contrary is due to the respondent’s being directed to file material only in the event that the adjudicator ruled in its favour, which did not occur – whether it should be declared that the applicant is not liable to pay the respondent for building work undertaken
PROCEDURE – COSTS – DEPARTING FROM THE GENERAL RULE – CONDUCT OF PARTIES – OTHER CONDUCT – where the applicant failed to obtain any relief sought in the proceedings – where the applicant argued that it was necessary to bring the proceedings to avoid judgment being entered against it – where the applicant should have waited for the adjudicator’s decision before commencing proceedings – where the respondent did not offer an undertaking not to make a further payment claim until late in the hearing – where the respondent’s initial claim has been held by an adjudicator to have been wrongly made – whether costs should be awarded
Building and Construction Industry Payments Act 2004 (Qld)
Australian Remediation Services Pty Ltd v Earth Tech Engineering Pty Ltd & Anor [2005] NSWSC 362, cited
BMD Major Projects Pty Ltd v Wagstaff Piling Pty Ltd & Anor, unreported, Philippides J, 7 June 2005, cited
Bucklands Convalescent Hospital v Taylor Projects Group [2007] NSWSC 1514, cited
Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69, considered
Energetech Australia Pty Ltd v Sides Engineering Pty Ltd [2005] NSWSC 1143; (2005) 226 ALR 362, cited
Perform (NSW) Pty Ltd v Mev-Aus Pty Ltd [2009] NSWSC 416, cited
COUNSEL:
R M Derrington SC for the applicant
M Hindman for the respondentSOLICITORS:
Tucker & Cowen for the applicant
Clayton Utz for the respondent
The respondent,…
Keep reading for free
Create a free CaseChat account to read Securcorp Limited v. Civil Mining & Construction P/L and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] QSC 249
- Decision Date
CaseChat Overview and Summary
The primary legal issue for the court was whether Securcorp should be declared not liable to pay Civil Mining & Construction for the work undertaken. The court considered the evidence presented by Securcorp and the absence of countervailing evidence from Civil Mining & Construction. The court also examined the procedural steps taken by the parties, including the timing of the proceedings and the conduct of the parties during the hearing. The court determined that while Securcorp had provided sufficient evidence to support its position, the procedural missteps and conduct of the parties warranted consideration in the costs assessment.
The court concluded that although Securcorp had not succeeded in obtaining any relief from the proceedings, it was not liable to pay Civil Mining & Construction for the building work. The court also found that the absence of costs order was appropriate given the circumstances, including the procedural missteps and the lack of an early offer by Civil Mining & Construction to cease further payment claims. The court's decision was influenced by the fact that Civil Mining & Construction had only made the offer to cease further claims late in the hearing, and its initial claim had been found to be wrongly made by an adjudicator.
The final orders of the court were that the originating application by Securcorp would be dismissed, and there would be no order as to costs. The dismissal of the application was contingent upon Civil Mining & Construction providing an undertaking through its counsel that it would not serve any further payment claims under the Building and Construction Industry Payments Act 2004 (Qld) arising from the Riverview Estate subdivision project.
Orders
Orders of the court
Upon the undertaking by the respondent through its counsel that it will not serve any further payment claim under the Building and Construction Industry Payments Act 2004 (Qld) arising out of the project known as the Riverview Estate subdivision it will be ordered that:
1. The Originating Application is dismissed.
2. There will be no order as to costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.