Ottoway Engineering Pty Ltd v Westpac Banking Corporation (No 3)

Link copied
Case Copied 45 min read

FEDERAL COURT OF AUSTRALIA

Ottoway Engineering Pty Ltd v Westpac Banking Corporation (No 3) [2017] FCA 1500

File number: SAD 90 of 2016
Judge: BESANKO J
Date of judgment: 13 December 2017
Catchwords: PRACTICE AND PROCEDURE – consideration of an application by the applicant seeking orders to prevent the respondent from enforcing a guarantee – where the applicant was the subcontractor on a construction project – where the applicant’s bank provided a guarantee to the main contractor’s bank – whether the guarantee secures the applicant’s obligations to the main contractor under a separate agreement – whether the guarantee secures the main contractor’s obligations to its bank.
BANKING AND FINANCIAL INSTITUTIONS – consideration of the proper construction of the guarantee – where the guarantee is in the nature of a performance bond or demand guarantee and not a contract of suretyship – where the true nature of the document is to be ascertained from its terms and conditions – where the guarantee was provided by the applicant’s bank to the main contractor’s bank – where there is no underlying agreement between the applicant and the respondent – where the guarantee places a primary obligation on the applicant’s bank to pay to the respondent the amount specified in a written demand in accordance with the guarantee – where the obligation under the guarantee is independent of the underlying agreements between the applicant and the main contractor.
CONSUMER LAW – whether the respondent engaged in misleading or deceptive or unconscionable conduct under the Australian Consumer Law in procuring or enforcing the guarantee – where the applicant sought to rely on what it claimed was a species of unconscionable conduct that arises where the assertion or reliance on a legal right is, in the circumstances, unconscionable – where there is very limited scope for holding unconscionable conduct in a case involving a performance bond or demand guarantee – where the respondent had no obligation to make further inquiries into the conduct of the main contractor before calling on the guarantee – where the respondent was not bound to pursue repayment of the amount secured by the guarantee through a term deposit also held by the respondent – where the respondent was entitled to take immediate action on the guarantee.
Legislation:

Australian Competition and Consumer Act 2010 (Cth), Schedule 2, ss 18, 20, 21, 22

Australian Investments and Securities Commission Act 2001 (Cth) ss 12CA, 12CB, 12CC

Corporations Act 2001 (Cth) s 182

Trade Practices Act 1974 (Cth) s 51AA

Cases cited:

AM Spicer and Son Proprietary Limited (In Liquidation) v Spicer and Howie (1931) 47 CLR 151

Ankar Proprietary Limited v National Westminster Finance (Australia) Limited (1987) 162 CLR 549

Arnold v Britton [2015] AC 1619

Australasian Conference Association Limited v Mainline Constructions Proprietary Limited (In Liquidation) and Others (1978) 141 CLR 335

Australian Broadcasting Corporation v Lenah Game Meats Pty Limited (2001) 208 CLR 199

Australian Competition and Consumer Commission v C G Berbatis Holdings Pty Limited and Others (2003) 214 CLR 51

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ottoway Engineering Pty Ltd v Westpac Banking Corporation (N... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] FCA 1500
Decision Date

CaseChat Overview and Summary

Ottoway Engineering Pty Ltd sought orders to prevent Westpac Banking Corporation from enforcing a guarantee. The dispute arose from a construction project where the applicant was a subcontractor to the main contractor, CITIC Pacific Mining Ltd. The guarantee was provided by the applicant’s bank to the main contractor’s bank and secured the main contractor’s obligations to its bank. The applicant argued that the guarantee also secured its own obligations to the main contractor under a separate agreement. The court was required to determine the proper construction of the guarantee and whether Westpac engaged in misleading or deceptive conduct under the Australian Consumer Law.

The court examined the terms and conditions of the guarantee to ascertain its true nature. It found that the guarantee was a performance bond or demand guarantee, not a contract of suretyship. The primary obligation under the guarantee was the applicant’s bank to pay a specified amount upon a written demand, independent of the underlying agreements between the applicant and the main contractor. The court held that there was no underlying agreement between the applicant and Westpac, and thus Westpac had no obligation to make further inquiries into the conduct of the main contractor before calling on the guarantee. Furthermore, Westpac was not bound to pursue repayment of the amount secured by the guarantee through a term deposit also held by Westpac.

The court concluded that Westpac was entitled to take immediate action on the guarantee. The applicant’s argument that Westpac engaged in unconscionable conduct by asserting or relying on a legal right was dismissed. The court found that there was very limited scope for holding unconscionable conduct in a case involving a performance bond or demand guarantee. The respondent was not liable for misleading or deceptive conduct under the Australian Consumer Law.

ORDERS:
1. The respondent bring in draft minutes of order reflecting the conclusions in the reasons for judgment.

Orders

Orders of the court

1. The respondent bring in draft minutes of order reflecting the conclusions in the reasons for judgment.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

My statement of the facts is divided into three sections. First, I will set out the main facts over the relevant period which is the period from May 2014 to April 2016. Secondly, I will set out the facts in connection with the two extensions of the term of the Bill Facility provided to BCMC by the respondent. Thirdly, I will set out the facts concerning the repayment of the Bill Facility by BCMC to the respondent and the repayment by the applicant of the advance payment.The Main Facts over the Period from May 2014 to April 2016 Mr Young described the operations of the applicant and the Sino Iron project in the following terms. The applicant is a wholly owned subsidiary of E & A Limited (E & A) which is a publicly listed company. The company is a mechanical fabrication and installation company which provides specialised services to the oil and gas, mining, defence and water industries. It operates a number of fabrication workshops and the services it provides includes the fabrication of pipe spooling, pressure vessels, welding of all material grades, modular skid construction, machinery and material handling manufacture, light to heavy general steel and plate construction. The applicant has performed a number of site based construction projects throughout Australia. The following are examples: the fabrication of in excess of 36 km of carbon steel pipe spooling on the Western Mining Corporation/BHP Billiton Olympic Dam expansion; the fabrication of pipe spools for the Ravensthorpe Nickel project on behalf of AKER Kvaerner/Chemetics which included the fabrication of 800 tonne of spooling from a variety of materials; the fabrication and supply and erection of approximately 400 tonne of structural steel on platforms; and the fabrication and installation of carbon steel and stainless steel pipework at the Uranium One project north west of Broken Hill; and with respect to the Sino Iron project (described below) which involved a 450 MW Combined Cycle power plant operated by CITIC Pacific Mining Ltd (now known as CITIC Ltd) (CITIC), the applicant was one of the main subcontractors to CITIC and it installed turbines, boilers, stacks, fans, steelwork structures, piping, pumps and associated equipment. CITIC developed the Sino Iron project at Cape Preston. Cape Preston is 100 km south west of Karratha in Western Australia’s Pilbara Region and 14,090 km north of Perth. The project is the largest magnetite mining and processing operation in Australia. The operation has been designed with sufficient capacity to produce millions of tonnes per annum of final magnetite concentrate over a production life of 25 years. CITIC is incorporated in Hong Kong and is listed on the Hong Kong stock exchange. CITIC Pacific Mining Management Pty Ltd (CPM) and Sino Iron Pty Ltd (Sino Iron) are subsidiaries of the company. There are two dewatering buildings known as Dewatering Buildings 313 and 314 at a distance of approximately 25 km from the Sino Iron project mine site. The dewatering buildings are located in the concentrator area and their purpose is to dewater the concentrated magnetite from the slurry pumped from the concentrator prior to barging the extracted magnetite ore to ships for export.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

The applicant put an additional argument or case on fraud in its closing written submissions. As it is not pleaded, the applicant may not rely on it. In any event, the additional argument or case on fraud fails. The applicant relies on the respondent’s knowledge of the matters identified in the context of the applicant’s case on unconscionable conduct and the respondent’s decision to grant the second extension. If, as I have held, that did not render the respondent liable for unconscionable conduct, it cannot render the respondent liable in fraud or for involvement in fraud.CONCLUSION The respondent may enforce the Guarantee to the extent of the amount outstanding under the Bill Facility, but no further. I will hear the parties as to the orders necessary to give effect to these conclusions and costs.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.