FEDERAL COURT OF AUSTRALIA
Oceanic Coal Australia Pty Ltd v Parker [2010] FCA 1018
Citation: Oceanic Coal Australia Pty Ltd v Parker [2010] FCA 1018 Appeal from: Parker v Oceanic Coal Australia Pty Ltd (Chief Industrial Magistrate's Court of New South Wales, Case no. 2009/191059, 3 February 2010) Parties: OCEANIC COAL AUSTRALIA PTY LTD (ACN 003 856 782) v STEPHEN JAMES PARKER File number: NSD 176 of 2010 Judge: COWDROY J Date of judgment: 17 September 2010 Catchwords: INDUSTRIAL LAW – Appeal from decision of Chief Industrial Magistrate – Workplace agreement – Interpretation of West Wallsend Underground Mine Collective Agreement 2007 – ‘Accident Pay’ – Whether Chief Industrial Magistrate erred in not giving effect to the plain and ordinary meaning of ‘Accident Pay’ clause – Whether Chief Industrial Magistrate erred in not taking into account defined terms ‘Classification Rate’ and ‘Rostered Hours’ – Whether Chief Industrial Magistrate erred in taking into account extraneous principles of perceived injustice and apparent ‘purpose’ of ‘Accident Pay’ – Held – ‘Accident Pay’ clause unambiguous – Chief Industrial Magistrate erred in not giving effect to the plain and ordinary meaning of relevant ‘Accident Pay clause’ – Appeal allowed. Legislation: Workers Compensation Act 1987 (NSW)
Workplace Relations Act 1996 (Cth)Cases cited: Amcor Limited v Construction, Forestry, Mining and Energy Union and Others (2005) 222 CLR 241
Ansett Australia Limited (subject to Deed of Company Arrangement) v Australian Licensed Aircraft Engineers’ Association [2003] FCAFC 209
Automotive, Food, Metals, Engineering, Printing and Kindred Industries Union v Skilled Engineering Ltd [2003] FCA 260
City of Wanneroo v Holmes (1989) 30 IR 362
The Clothing Trades Award [1950] 68 CAR 597
Codelfa Construction Proprietary Limited v State Rail Authority of New South Wales (1982) 149 CLR 337
Kucks v CSR Limited (1996) 66 IR 182
Toll (FGCT) Pty Limited v Alphapharm Pty Limited and Others (2004) 219 CLR 165
Whittaker v Unisys Australia Pty Ltd (2010) 192 IR 311Date of hearing: 11 June 2010 Place: Sydney Division: FAIR WORK DIVISION Category: Catchwords Number of paragraphs: 68 Counsel for the Appellant: Mr J Murdoch SC Counsel for the Respondent: Mr T Slevin Solicitor for the Appellant: Corrs Chambers Westgarth Solicitor for the Respondent: Construction, Forestry, Mining and Energy Union
IN THE FEDERAL COURT OF AUSTRALIA
NEW SOUTH WALES DISTRICT REGISTRY
FAIR WORK DIVISION
NSD 176 of 2010
ON APPEAL FROM CHIEF INDUSTRIAL MAGISTRATES COURT OF NEW SOUTH WALES
BETWEEN: OCEANIC COAL AUSTRALIA PTY LTD (ACN 003 856 782)
AppellantAND: STEPHEN JAMES PARKER
Respondent
JUDGE:
COWDROY J
DATE OF ORDER:
17 SEPTEMBER 2010
WHERE MADE:
SYDNEY
THE COURT ORDERS THAT:
1.The Appeal is allowed.
2.The decision of Chief Industrial Magistrate Hart dated 3 February 2010 be quashed.
3.The Orders of Chief Industrial Magistrate Hart dated 24 February 2010 be set aside.
Note:Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.
The text of entered orders can be located using Federal Law Search on the Court’s website.
IN THE FEDERAL COURT OF AUSTRALIA
Keep reading for free
Create a free CaseChat account to read Oceanic Coal Australia Pty Ltd v Parker and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] FCA 1018
- Decision Date
CaseChat Overview and Summary
The Court examined the relevant case law on interpreting awards and industrial agreements, including Amcor Limited v Construction, Forestry, Mining and Energy Union and Others, and Toll (FGCT) Pty Limited v Alphapharm Pty Limited and Others. The Court noted that the object of interpreting such documents is to determine the intention of the parties from the words used, considering the context and surrounding circumstances. The Court found that the Chief Industrial Magistrate had erred in his interpretation of clause 12(b)(i) because it was contrary to the plain and ordinary meaning of the words. The Court also found that the Chief Industrial Magistrate's failure to apply the definitions of 'Classification Rate' and 'Overtime Rate' constituted an error of law. Therefore, the Court allowed the appeal, set aside the decision of the Chief Industrial Magistrate, and quashed the orders made by him.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Mr Parker submits that the objective intent of the parties is clear from the words used in the relevant clause. CONSIDERATION The approach to interpretation of awards and industrial agreements is considered in Amcor Limited v Construction, Forestry, Mining and Energy Union and Others (2005) 222 CLR 241. In Amcor at [30] their Honours Gummow, Hayne and Heydon JJ observed in relation to the relevant clause in question, cl 55.1.1:Clause 55.1.1 must be read in context. It is necessary, therefore, to have regard not only to the text of clause 55.1.1, but also to a number of other matters: first, the other provisions made by clause 55; secondly, the text and operation of the Agreement both as a whole and by reference to other particular provisions made by it; and, thirdly, the legislative background against which the Agreement was made and in which it was to operate. Accordingly the content of the relevant clause must be considered together with the relationship of that clause or other clauses, the text and operation of the award and the legislative background. Effect must be given to the meaning of the award (or industrial agreement) as expressed in the terms that it uses (see Amcor per Kirby J at [70]). Further, if ‘reasonably available’ the award should be construed to make it operate ‘fairly towards both parties’ (see Amcor per Callinan J at [131]). As stated by Finkelstein J in Automotive, Food, Metals, Engineering, Printing and Kindred Industries Union v Skilled Engineering Ltd [2003] FCA 260 at [21]:The object as always is to objectively determine the intention of the parties from the words of the document. That intention can manifest itself not only from words used but from words considered in light of the circumstances surrounding the transaction. In assessing the circumstances surrounding the transaction, Mason J’s observations in Codelfa Construction Proprietary Limited v State Rail Authority of New South Wales (1982) 149 CLR 337 are applicable. At 352 his Honour said:Consequently when the issue is which of two or more possible meanings is to be given to a contractual provision we look, not to the actual intentions, aspirations or expectations of the parties before or at the time of the contract, except in so far as they are expressed in the contract, but to the objective framework of facts within which the contract came into existence, and to the parties’ presumed intention in this setting. We do not take into account the actual intentions of the parties and for the very good reason that an investigation of those matters would not only be time consuming but it would also be unrewarding as it would tend to give too much weight to these factors at the expense of the actual language of the written contract. The above statement must be considered together with the observations of the High Court of Australia in Toll (FGCT) Pty Limited v Alphapharm Pty Limited and Others (2004) 219 CLR 165. At [40] the Court observed:It is not the subjective beliefs or understandings of the parties about their rights and liabilities that govern their contractual relations. What matters is what each party by words and conduct would have led a reasonable person in the position of the other party to believe. References to the common intention of the parties to a contract are to be understood as referring to what a reasonable person would understand by the language in which the parties have expressed their agreement. The meaning of the terms of a contractual document is to be determined by what a reasonable person would have understood them to mean. That, normally, requires consideration not only of the text, but also of the surrounding circumstances known to the parties, and the purpose and object of the transaction.[Footnotes omitted]