Application to deal with a dispute - Application of clause 32 of the Agreement in relation to redundancy - Obligation to consult - Finding that BHP has not met obligations to consult in relation to redundancies - Order issued.

BACKGROUND

[1] This decision arises from a dispute between the Construction, Forestry, Mining and Energy Union - Mining and Energy Division (CFMEU) and BHP Coal Pty Ltd (BHP) in relation to the implementation of redundancies. The CFMEU has made a number of applications to the Fair Work Commission (the Commission) asserting that BHP has not met its obligations under the Agreement to consult the CFMEU and Employee representatives about the redundancies and their effect. Conferences of the parties have been conducted on 21 February and 6 March 2014. Processes put into place at those conferences for the provision by BHP of further information in relation to the redundancies, have not resolved the dispute.

[2] The application subject of this decision was listed for mention on Thursday 20 March 2014 following correspondence from the CFMEU dated 17 March 2014 stating:

    “The Applicant respectfully requests that a listing be set aside for this matter as a matter for conciliation, and if necessary arbitration.

    In respect of the urgency of this matter the Applicant notes that the Respondent has provided a notice that it intends to dismiss a large number of employees starting the week of 24 March 2014 (next week). ...

    The decision of the Respondent to dismiss the employees by way of voluntary redundancy is contrary to the consultation obligations contained in clause 32 of the Agreement. The Applicant is seeking ... orders by either agreement between the parties or by way of arbitrated determination. The Applicant has today written to the Respondent requesting their agreement in relation to the matters covered in the proposed orders. However, the Applicant respectfully requests that the Commission provide a precautionary listing for later this week.”

[3] The matter was listed for mention on 20 March 2014. The parties tendered a significant amount of material and Directions were issued for further material to be filed and served. BHP indicated that it intended to accept applications for voluntary redundancy on Tuesday 25 March 2014. Given the urgency of the matter, it was listed for hearing on Monday 24 March 2014. Evidence in support of the application was given by Mr Chris Brodsky, District Vice President of the CFMEU. Evidence on behalf of BHP was given by Ms Leonie Anne Carlile, Manager Human Resources at the Saraji Peak Downs Mines.

[4] The hearing concluded at 6.00 pm on that date and an ex tempore decision and Order were issued at 7.30 pm. An edited version of that Decision is set out below. I also indicated that the ex tempore Decision…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Construction, Forestry, Mining and Energy Union v BHP Coal P... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] FWC 2062
Decision Date

CaseChat Overview and Summary

The matter before the court involved the Construction, Forestry, Mining and Energy Union, acting on behalf of its members, and BHP Coal Pty Ltd. The dispute centred around the application of clause 32 of an industrial agreement concerning redundancy processes. The Union alleged that BHP Coal had failed to comply with its obligations to consult with employees and the Union before implementing redundancy measures, as required by the agreement. The court was tasked with determining whether BHP Coal had breached its consultation obligations under clause 32.

The court considered whether BHP Coal had adequately consulted with the Union and affected employees prior to implementing the redundancy measures. The Union argued that the company failed to provide sufficient information and opportunity for meaningful consultation, thus breaching the agreement. The court examined the requirements of clause 32, including the necessity of providing detailed information, allowing time for consultation, and considering the Union's input. The court found that BHP Coal did not meet its obligations to consult, as the information provided was insufficient, and the consultation process did not allow for meaningful engagement.

Having determined that BHP Coal had breached its obligations, the court issued an order requiring the company to engage in proper consultation with the Union and affected employees. The order mandated that BHP Coal provide detailed information about the proposed redundancies, allow adequate time for consultation, and consider the Union's input in making decisions. This decision underscored the importance of adhering to agreed consultation processes in industrial relations and highlighted the court's role in enforcing these obligations. The court's order aimed to ensure that future redundancy processes would comply with the terms of the agreement and provide fair treatment to affected employees.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.