Supreme Court
New South Wales
Medium Neutral Citation: Nutek Constructions Pty Ltd v Slotwinski [2021] NSWSC 832 Hearing dates: 7 July 2021 Date of orders: 23 July 2021 Decision date: 23 July 2021 Jurisdiction: Common Law Before: Davies J Decision: (1) In proceedings 2020/327546, leave to appeal is refused.
(2) The summons in proceedings 2020/327546 is dismissed.
(3) The plaintiff is to pay the costs of those proceedings.
(4) In proceedings 2021/158356, leave to appeal is refused.
(5) The summons in proceedings 2021/158356 is dismissed.
(6) The plaintiff is to pay the costs of those proceedings.
Catchwords: APPEALS – leave to appeal – from the Appeal Panel of the New South Wales Civil and Administrative Tribunal – where plaintiff alleged that Appeal Panel took wrong approach in assessing damages – where issue raised by plaintiff in Supreme Court not argued before the Tribunal at first instance or the Appeal Panel – where plaintiff bound by how it conducted its case at first instance and on appeal to the Appeal Panel – where even if damages methodology was incorrect it was the plaintiff who led the Appeal Panel into error – summons dismissed
APPEALS – leave to appeal – whether plaintiff demonstrated anything more than error – no matter of principle – where two prior hearings and two appeals – no basis for leave demonstrated – leave to appeal refused
Legislation Cited: Civil and Administrative Tribunal Act 2013 (NSW) s 83
Home Building Act 1989 (NSW) s 48K
Local Court Act 2007 (NSW) s 40
Cases Cited: Ackerman v Morgan [2019] NSWSC 1250
Ashi Pty Limited v Karasco Investments Pty Ltd [2009] NSWSC 780
Be Financial Pty Ltd v Das [2012] NSWCA 164
Chapmans Ltd v Yandell [1999] NSWCA 361
Kostas v HIA Insurance Services Pty Ltd (2010) 241 CLR 390; [2010] HCA 32
Onik New Energy Australia Pty Limited v Henderson [2016] NSWSC 186
Pratten v Johns [2010] NSWSC 327
Slotwinski v Nutek Constructions Pty Ltd; Nutek Constructions Pty Ltd v Slotwinski [2019] NSWCATAP 158
Slotwinski v Nutek Constructions Pty Ltd [2020] NSWCATAP 216
Slotwinski v Nutek Constructions Pty Ltd [2021] NSWCATAP 113
Nutek Constructions Pty Ltd v Slotwinski [2021] NSWSC 274
Steak Plains Olive Farm Pty Ltd v Australian Executor Trustees Limited [2015] NSWSC 289
Stephen Kirkman v Commissioner Department of Corrective Services [2013] NSWSC 833
Texts Cited: Nil
Category: Principal judgment Parties: Nutek Constructions Pty Ltd (Plaintiff)
Julia Slotwinski (Defendant)Representation: Counsel:
Solicitors:
I Archibald (Plaintiff)
In person (Defendant)
Harrington Lawyers (Plaintiff)
Self-represented (Defendant)
File Number(s): 2020/327546 & 2021/158356 Publication restriction: Nil
Judgment
-
On 1 July 2015 Julia Slotwinski entered into a residential building contract with Nutek Constructions Pty Ltd for the construction of three apartments at 8 Jackson Street, Balgowlah for the contract price of $1,650,000.
-
After construction commenced, various disputes arose between the parties. Nutek repudiated the contract, and Ms Slotwinski accepted the repudiation and terminated the contract. At the date of termination the construction was about 25% complete.
-
Nutek commenced two proceedings in the…
Keep reading for free
Create a free CaseChat account to read Nutek Constructions Pty Ltd v Slotwinski and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2021] NSWSC 832
- Decision Date
CaseChat Overview and Summary
The legal issue before the Supreme Court was whether the plaintiff had demonstrated anything more than an error in the Appeal Panel's assessment of damages, such that the case involved a matter of principle warranting leave to appeal. The Court examined whether the plaintiff's failure to argue a particular issue before the Tribunal at first instance or the Appeal Panel precluded it from raising that issue in its appeal to the Supreme Court. The Court also considered whether the plaintiff's conduct at the prior hearings had contributed to any error made by the Appeal Panel.
The Court found that the plaintiff had not demonstrated anything more than an error in the Appeal Panel's assessment of damages. The Court held that the plaintiff was bound by how it had conducted its case at first instance and on appeal to the Appeal Panel. The Court further held that even if the damages methodology was incorrect, it was the plaintiff who had led the Appeal Panel into error. The Court found that there was no basis for leave, given the two prior hearings and two appeals. Consequently, the Court refused leave to appeal.