Munkara v Santos NA Barossa Pty Ltd (No 3)

Link copied
Case Copied 72 min read

FEDERAL COURT OF AUSTRALIA

Munkara v Santos NA Barossa Pty Ltd (No 3) [2024] FCA 9   

File number: VID 907 of 2023
Judgment of: CHARLESWORTH J
Date of judgment: 15 January 2024
Catchwords: ENVIRONMENTAL LAW – where the respondent holds a pipeline licence issued under the Offshore Petroleum and Greenhouse Gas Storage Act 2006 (Cth) authorising it to construct a 262km long gas export pipeline in the Timor Sea – where the applicants are Aboriginal people from the Tiwi Islands – where the pipeline would pass the west coast of the Tiwi Islands within 7km at its closest point – where the respondent has an environment plan for the activity accepted by the National Offshore Petroleum Safety and Environmental Management Authority under the Offshore Petroleum and Greenhouse Gas Storage (Environment) Regulations 2009 (Cth) – whether the respondent is obliged to submit a revised environment plan in accordance with reg 17(6) of the Regulations because there has been an occurrence of a new significant environmental impact or risk – whether there is a risk of impact to the applicants’ spiritual connection to sea country through which the pipeline will pass because the pipeline will interrupt song lines or interfere with the travels of ancestral beings – whether there is a risk of impact to tangible cultural heritage in the vicinity of the pipeline route in the nature of artefacts evidencing human occupation and activity on the land before sea levels rose – whether on the proper construction of reg 17(6) of the Regulations there is a risk of environmental impact that is “new” and “significant” – application dismissed
Legislation:

Aboriginal Land Rights (Northern Territory) Act 1976 (Cth)

Acts Interpretation Act 1901 (Cth)

Environment Protection and Biodiversity Conservation Act 1999 (Cth) ss 3A, 18

Evidence Act 1995 (Cth) ss 72, 136, 140

Federal Court of Australia Act 1976 (Cth) s 23

Judiciary Act 1903 (Cth) s 39B

Native Title Act 1993 (Cth) ss 61, 223

Offshore Petroleum and Greenhouse Gas Storage Act 2006 (Cth) ss 3, 210, 211, 574, 576, 781, 782, 790

Offshore Petroleum and Greenhouse Gas Storage (Environment) Regulations 2009 (Cth) regs 3, 4, 6, 7, 8, 9, 9AA, 9AB, 9AC, 9A, 10, 10A, 11AA, 11A, 11B, 11C, 12, 13, 14, 15, 16, 17, 18, 21, 22, 23, 24, 25

Offshore Petroleum and Greenhouse Gas Storage (Environment) Regulations 2023 (Cth)

Greenhouse Gas Storage Amendment (National Regulator) Bill 2001 (Cth)

Aboriginal Land Act 1978 (NT) s 12

Civil Liability Act 2002 (NSW) s 5K

Northern Territory Aboriginal Sacred Site Act 1989 (NT)  

Cases cited:

BrisConnections Finance Pty Ltd v Arup Pty Ltd (2017) 252 FCR 450

Cooke v Federal Commissioner of Taxation (2002) 51 ATR 223

Cooper v National Offshore Petroleum Safety and Environmental Management Authority (No 2) [2023] FCA 1158

Fallas v Mourlas (2006) 65 NSWLR 418

Federal Commissioner of Taxation v Shell Energy Holdings Australia Ltd (2022) 288 FCR 193

He Kaw Teh v The Queen (1985) 157 CLR 523

Jones v Dunkel (1959) 101 CLR 298

Krajniw v…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Munkara v Santos NA Barossa Pty Ltd (No 3) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] FCA 9
Decision Date

CaseChat Overview and Summary

Simon Munkara, an Aboriginal person from the Tiwi Islands, brought an action against Santos NA Barossa Pty Ltd, which holds a pipeline licence under the Offshore Petroleum and Greenhouse Gas Storage Act 2006 (Cth) to construct a 262km gas export pipeline in the Timor Sea. The pipeline route passes the west coast of the Tiwi Islands within 7km at its closest point. Munkara's claim sought an injunction to prevent Santos from undertaking the construction, alleging that the pipeline would cause significant environmental harm by interrupting song lines and interfering with the travels of ancestral beings, thus impacting the spiritual connection to sea country. Additionally, the claim argued that there was a risk of impact to tangible cultural heritage in the form of artefacts evidencing human occupation and activity on the land before sea levels rose. The primary legal issue before the court was whether Santos was obliged to submit a revised environment plan in accordance with reg 17(6) of the Offshore Petroleum and Greenhouse Gas Storage (Environment) Regulations 2009 (Cth) because there had been an occurrence of a new significant environmental impact or risk.

The court found that the evidence did not establish that the obligation under reg 17(6) had been triggered. It was concluded that on the proper construction of the regulation, the risk of environmental impact that is “new” and “significant” had not been proven. The court dismissed the amended originating application, discharged the interlocutory injunction, and ordered that the applicants pay the respondent’s costs, to be assessed by a Registrar of the Court on a lump sum basis. Any application to vary or substitute the costs order must be filed and served on or before 29 January 2024, accompanied by an affidavit in support and written submissions not exceeding five pages. If an application is filed, the respondent, if so advised, must file and serve an affidavit in opposition and written submissions not exceeding five pages by 14 February 2024. The application is to be set down for hearing on a date to be fixed, not before 19 February 2024.

Orders

Orders of the court

1. The originating application is dismissed.

2. The order with injunction granted on 15 November 2023 is discharged.

3. Subject to these orders, the applicants are to pay the respondent’s costs, such costs to be assessed by a Registrar of the Court on a lump sum basis.

4. Any application to vary or substitute the order in paragraph 3 is to be filed and served on or before 29 January 2024, such application to be accompanied by:

(a) an affidavit in support; and

(b) written submissions not exceeding five pages.

5. In the event that an application is filed and served in accordance with paragraph 4, on or before 14 February 2024 the person served is, if so advised, to file and serve:

(a) an affidavit in opposition; and

(b) written submissions not exceeding five pages.

6. In the event that an application is filed and served in accordance with paragraph 4, the application is to be set down for hearing on a date to be fixed, not before 19 February 2024.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

For the reasons that follow the evidence does not establish that the obligation under reg 17(6) (properly construed) has been triggered. It follows that the amended originating application must be dismissed.THE TRIAL AND EVIDENCE This action was commenced by originating application filed on 30 October 2023, accompanied by an interlocutory application seeking urgent injunctive relief. Simon Munkara was at that time the sole applicant. Argument on his application for interim relief extended into the evening of 1 November 2023. On the following day, the Court granted a short term injunction to restrain all work on the pipeline until 13 November 2023. Orders were made setting the matter down for more detailed argument on the question of whether there should be an ongoing injunction pending final judgment in the case. Oral reasons were given and written reasons followed: Munkara v Santos NA Barossa Pty Ltd [2023] FCA 1348 (Munkara No 1). In Munkara No 1, I explained why I was satisfied that the Court had jurisdiction to grant the relief then sought by Simon Munkara, and why I was satisfied at that time that he was a person who had standing to apply for it (at [39] – [55]). The interim injunction remained in force until 15 November 2023. On that day, the Court granted an interlocutory injunction of a more limited kind. The order had the effect of restraining Santos from undertaking works on all but the northernmost 86km of the pipeline route and was expressed to remain in force until 15 January 2024, or such later date as the trial judge may determine: Munkara v Santos NA Barossa Pty Ltd (No 2) [2023] FCA 1421 (Munkara No 2). At the time of those orders, the final relief sought on the originating application was confined to an injunction. The claim for declaratory relief was later added by amendment. In Munkara No 2, I addressed again the questions of jurisdiction and standing, including by rejecting a new argument raised by Santos on those questions. Questions of jurisdiction and standing have not been re-agitated and I remain of the views expressed in Munkara No 1 and Munkara No 2 on those interrelated topics. An important feature of these proceedings is that the application for the interlocutory injunction was unsupported by any undertaking as to damages given by Simon Munkara or any person on his behalf. I concluded that it was in the interests of justice to proceed expeditiously to trial and judgment. That is principally because of conclusions I had previously drawn as to where the balance of convenience lay with respect to the injunctive relief, considered in light of the absence of the usual undertaking, and having regard to an earlier indication from Simon Munkara’s Counsel that he and other likely applicants were ready to proceed to trial. In addition, contractual terms relating to the pipeline’s construction were such that Santos’s losses were likely to significantly increase if the restraint were to remain in force for a longer period of time.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

It was sometimes said by Tiwi witnesses that they did not speak in western concepts of boundaries. Those statements are to be understood in their proper context. The weight of the evidence is that there was a very strong sense among all witnesses that there existed such a thing as clan country. Map 1 demonstrates that the clan estates can and have been represented by the Tiwi Islanders themselves in a cartographic way, at least for some purposes. A good portion of the evidence focussed on the topic of who might have authority to speak for “Jikilaruwu country” or “Malawu country” or “Munupi country”, no witness questioning that such distinct places existed. That is hardly surprising given the territorial focus of the clans within the Tiwi social structure described by Dr Corrigan. Understood in their proper context, and at least when applied to land, assertions such as “we don’t speak in boundaries” may usually be understood as a reluctance to speak in terms of hard lines, absolute terms, modern measurements or two dimensions. But there is plainly such a thing as clan country: the Court was invited to assume the boundaries as depicted on Map 1 and to draw inferences about their natural extension into the sea. Registration of sacred sites The Northern Territory Aboriginal Sacred Site Act 1989 (NT) applies to the dry areas of the Tiwi Islands and the Northern Territory seas (extending about 2km from the shoreline). The Tiwi Land Council has been instrumental in recording and registering sacred sites under that regime, resulting in a map depicting many sacred sites on the land including around the coast. I accept that is an ongoing process. At present, the registered sacred sites do not include any place beyond the coast and into the vicinity of the pipeline, but that is no doubt explained by the territorial limit of the legislation.Cultural authority and the right to speak for country The topic of cultural authority was all pervasive during the course of the trial. It arises in part because the Court has before it conflicting accounts about what constitutes “culture” in light of differing views among Tiwi people as to whether the pipeline will have the impact the applicants assert. The applicants in particular sought to address that issue by inviting the Court to identify those who could, in accordance with Tiwi custom, speak authoritatively on a topic and to afford little or no weight to those who did not. The topic of cultural authority at times was equated with the question of which person had a right to speak for which country. The issue most often arose in the form of questions in cross-examination, putting the proposition that only Jikilaruwu can speak for Jikilaruwu country or song lines. Those questions did not get to the nub of the matter. They belied some complexity as to who could have an interest in (for example) Jikilaruwu country other than by way of patrilineal descent. They did not assist the Court to identify what song lines were exclusive to any particular clan. They were peculiar in a sense because the applicants themselves sought to draw on evidence of less senior Jikilaruwu people in preference over the evidence of those more senior, and to some extent draw on the evidence of non-Jikilaruwu people in relation to song lines that they say are exclusively Jikilaruwu. Perhaps most importantly, they do not assist the Court to grapple with the stark reality in the evidence that there were conflicting accounts given by Jikilaruwu clan members (including senior members of the same family group) about the content of song lines and the impact of the pipeline upon them. It will be necessary to return to the question of cultural authority and the related question of dissent. It is an issue infiltrating nearly all of the broader issues in dispute.Spiritual beliefs, Dreamings and song lines