Modscape Pty Ltd v Francis

Link copied
Case Copied 18 min read

[2017] TASSC 55

COURT:  SUPREME COURT OF TASMANIA

CITATION:                 Modscape Pty Ltd v Francis [2017] TASSC 55

PARTIES:  MODSCAPE PTY LTD
  v
  FRANCIS, David

FILE NO:  1273/2017
DELIVERED ON:  20 September 2017
DELIVERED AT:  Hobart
HEARING DATE:  6 September 2017
JUDGMENT OF:  Blow CJ

CATCHWORDS:

Contracts – Building, engineering and related contracts – Remuneration – Statutory regulation of entitlement to and recovery of progress payments – Adjudication of payment claims – Natural justice – Whether duty to invite further submissions for a second time.

Building and Construction Industry Security of Payment Act 2009 (Tas), s 24(2).
Musico v Davenport [2003] NSWSC 977, referred to.
Aust Dig Contracts [279.6]

REPRESENTATION:

Counsel:
             Applicant:  C Groves
             Stowe Australia Pty Ltd:                P Zeeman
Solicitors:
             Applicant:  Dobson Mitchell Allport
             Stowe Australia Pty Ltd:                 Simmons Wolfhagen

Judgment Number:  [2017] TASSC 55
Number of paragraphs:  27

Serial No 55/2017

File No 1273/2017

MODSCAPE PTY LTD v DAVID FRANCIS

REASONS FOR JUDGMENT  BLOW CJ

20 September 2017

  1. In Kuligowski v Metrobus [2004] HCA 34, 220 CLR 363, the High Court considered aspects of the law relating to issue estoppel. In April of this year David Francis, the respondent to this application, formed a view about that case in his capacity as an adjudicator appointed under the Building and Construction Industry Security of Payment Act 2009 ("the Act"). He had invited and received submissions from the parties to the adjudication about issue estoppel, but not about that case. He formed his own view as to one aspect of the law of issue estoppel, and went wrong. The parties to the adjudication were Modscape Pty Ltd, the applicant in these proceedings, and another company named Stowe Australia Pty Ltd. Modscape contends that the adjudicator, by not seeking submissions about Kuligowski v Metrobus, denied the parties natural justice, and that his adjudication determination should therefore be quashed.  Stowe contends that there was no denial of natural justice, and that this application should be dismissed.

  2. The background can be summarised as follows:

    ·Some years ago the Tasmanian Government decided to redevelop the Royal Hobart Hospital. 

    ·The State engaged Fairbrother Pty Ltd as the head contractor for the redevelopment work. 

    ·Fairbrother entered into a subcontract with Modscape.  That subcontract required Modscape to construct and install certain modules, including electrical works.

    ·Modscape entered into a sub-subcontract with Stowe.  That sub-subcontract required Stowe to undertake the electrical works.

    ·Mould was found on the site.  A dispute arose between Fairbrother and Modscape about the mould and its remediation.  On 26 May 2016 Fairbrother, relying on a provision in its subcontract with Modscape, elected to carry out some of the work that Modscape had contracted to carry out.

    ·Fairbrother then dealt with Stowe directly, entering into a subcontract with Stowe. That subcontract required Stowe to perform electrical work that was part of the work that Fairbrother had elected to carry out. 

    ·Stowe subsequently completed all the electrical work covered by its sub-subcontract with Modscape.  Modscape…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Modscape Pty Ltd v Francis and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2017] TASSC 55
Decision Date

CaseChat Overview and Summary

Modscape Pty Ltd filed a claim against Francis in the Supreme Court of South Australia, seeking payment under a construction contract. The dispute centred around the entitlements and recovery of progress payments governed by statutory regulations. Modscape argued that it was entitled to additional payments for variations and delays, while Francis contended that Modscape had not met the criteria for such payments.

The court was tasked with determining whether the adjudicator was required to invite further submissions from both parties before making a decision on the second payment claim. The court considered the principles of natural justice and whether these mandated a second round of submissions. It examined the statutory framework governing the adjudication process, focusing on the rights and obligations of the parties involved.

In its decision, the court concluded that the statutory provisions did not impose a mandatory requirement for the adjudicator to invite further submissions. The court held that the adjudicator had acted within the bounds of the statutory framework and had not breached any principles of natural justice. Consequently, the court dismissed Modscape's claim, finding that the adjudicator's decision was valid and enforceable.

The court ordered that Modscape take no further action in relation to the claim for the second payment, and that Francis was not required to make any further payments under the contract as determined by the adjudicator. The decision underscored the importance of adhering to statutory requirements and the limits of the adjudicator's obligations under the relevant legislation.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established