SUPREME COURT OF QUEENSLAND
CITATION:
Mitchell v Pacific Dawn P/L [2003] QCA 526
PARTIES:
BRUCE JOSEPH MITCHELL
(plaintiff/respondent)
vPACIFIC DAWN PTY LTD ACN 070 358 280
(defendant/appellant)FILE NO/S:
Appeal No 3844 of 2003
Appeal No 5854 of 2003
SC No 3872 of 2001DIVISION:
Court of Appeal
PROCEEDINGS:
General Civil Appeal
Appeal from interlocutory decisionORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
28 November 2003
DELIVERED AT:
Brisbane
HEARING DATE:
16 October 2003
JUDGES:
McPherson JA and Mackenzie and Wilson JJ
Separate reasons for judgment of each member of the Court,
each concurring as to the orders madeORDERS:
Order that the appeal numbered CA 3844 of 2003 be allowed and the respondent pay the appellant’s costs of and incidental to that appeal1.
Order that the determination or answers to the question designated 3 (b) in the order of the Supreme Court made on 4 April 2003 be set aside and that the question be determined by another judge of the Supreme Court2.
Order that the respondent be granted an indemnity certificate under s 15 of the Appeal Costs Fund Act 1973 in respect of that appeal3.
Order that the appeal numbered CA 5854 of 2003 be dismissed 4.
CATCHWORDS:
APPEAL AND NEW TRIAL – GENERAL PRINCIPLES – INTERFERENCE WITH JUDGE’S FINDINGS OF FACT – WHERE FINDINGS CLEARLY WRONG – GENERALLY – trial judge’s finding of fact wrong – findings of credibility based on wrong facts – whether issue properly tried
Appeal Costs Fund Act 1973 (Qld), s 15, s 16
Pettitt v Dunkley [1971] 1 NSWLR 376, followed
COUNSEL:
D B Fraser QC, with S R Lumb, for the appellant
J C Bell QC, with P J Bunning, for the respondentSOLICITORS:
Hogan & Company for the appellant
Gall Standfield & Smith for the respondent
McPHERSON JA: The respondent plaintiff Bruce Mitchell is a builder who on 2 September 1999 entered into a contract with the appellant defendant Pacific Dawn Pty Ltd for the construction of a commercial building on land it owned at Toowong. The contract incorporated standard printed provisions used for lump sum building contracts but provided for what was described as “a guaranteed upper limit cost of $2,650,000”. It was agreed that if at completion the construction cost did not exceed that limit, the plaintiff would receive an additional fee of 7.5% = $198,750 plus 107.5% of the cost of variations and extras for which the defendant was liable under the contract. The object was evidently to provide the plaintiff with an incentive to complete the work within the limits of the estimated cost. If completed for less, the parties were to share the reduction in costs below that sum. The construction agreement therefore had, as the learned judge remarked, characteristics of a lump sum and a cost plus contract.
The precise form or characterisation of the contract counts for little in the narrative of events that follows, although it may have influenced the attitudes of the parties as…
Continue reading Mitchell v Pacific Dawn Pty Ltd
Sign in free to access the full text
- AGLC
- Mitchell v Pacific Dawn Pty Ltd [2003] QCA 526
- Case
- [2003] QCA 526
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were whether the trial judge’s findings of fact were clearly erroneous and whether the credibility assessments were based on incorrect facts. The court also had to consider whether the issue of whether the incident occurred due to the respondent’s negligence had been properly tried and determined at the trial. The appellant argued that the trial judge had failed to properly assess the credibility of the witnesses and that the findings were based on incorrect assumptions about the evidence.
The court found that the trial judge’s findings were indeed clearly wrong, primarily due to incorrect factual assumptions underpinning the credibility assessments. The court held that these errors were significant enough to warrant setting aside the findings and ordering a new trial to determine the issues properly. The Full Court emphasised the importance of ensuring that the trial judge’s findings of fact are not only reasonable but also based on the correct facts. The court also noted that the issues at hand had not been properly tried and determined, necessitating a re-evaluation by another judge.
The court ordered that the appeal be allowed and that the original determination be set aside, with the question to be re-determined by another judge. Additionally, the court ordered that the respondent pay the appellant’s costs of the appeal and granted the respondent an indemnity certificate under the Appeal Costs Fund Act 1973. The court dismissed the second appeal as it was contingent on the outcome of the first appeal.
Orders
Orders of the court
Order that the appeal numbered CA 3844 of 2003 be allowed and the respondent pay the appellant’s costs of and incidental to that appeal1.
Order that the determination or answers to the question designated 3 (b) in the order of the Supreme Court made on 4 April 2003 be set aside and that the question be determined by another judge of the Supreme Court2.
Order that the respondent be granted an indemnity certificate under s 15 of the Appeal Costs Fund Act 1973 in respect of that appeal3.
Order that the appeal numbered CA 5854 of 2003 be dismissed 4.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.