FEDERAL COURT OF AUSTRALIA
Minister for the Environment & Heritage v Greentree (No 2) [2004] FCA 741
ENVIRONMENT – Convention on Wetlands of International Importance (‘Ramsar Convention’) – clearing of designated wetland – whether purported designation by the Commonwealth of a wetland pursuant to Art 2 of the Ramsar Convention was effective for the purposes of s 17(1) of the Environment Protection and Biodiversity Conservation Act 1999 (Cth) (‘EPBC Act’) – whether clearing of land was specifically authorised under State law – whether clearing of land had a ‘significant impact on the ecological character of a declared Ramsar wetland’ within s 16(1) of the EPBC Act
Constitution s51(xxix)
Environment Protection and Biodiversity Conservation Act 1999 (Cth) ss 3, 16, 17, 17B, 43A, 52, 138, 326, 327, 333, 334, 335, 409, 475, 481, 482, 484, 519, 523, 524, 528
Crimes Act 1914 (Cth) s 4AA
Administrative Decisions (Judicial Review) Act 1977 (Cth) s 3Environmental Planning and Assessment Act 1979 (NSW) ss 4, 5, 14, 24, 26, 54, 55, 57, 62, 66, 67, 68, 69, 70, 76, 76A
Noxious Weeds Act 1993 (NSW) ss 7, 8, 9, 12
Native Vegetation Conservation Act 1997 (NSW) ss 4, 6, 7, 14, 21, 22
Local Government Act 1993 (NSW) s 4
Soil Conservation Act 1938 (NSW) s21ABConvention on Wetlands of International Importance especially as Waterfowl, done at Ramsar, Iran on 2 February 1971
Convention for the Protection of the World Cultural and Natural HeritageVienna Convention on the Law of Treaties
Richardson v Forestry Commission (1988) 164 CLR 261 cited
Queensland v Commonwealth (1989) 167 CLR 232 cited
Australian Heritage Commission v Mount Isa Mines (1997) 187 CLR 297 cited
Corporation of the City of Enfield v Development Assessment Commission (2000) 199 CLR 135 cited
Energy Resources of Aust Ltd v Commission of Taxation [2003] ATC 4024 cited
Evans v Friemann (1981) 35 ALR 428 cited
Seventh Mingcourt Pty Ltd v Lawrence (1996) 64 FCR 367 cited
Plaintiff S157/2002 v Commonwealth (2003) 211 CLR 476 cited
Commissioner of Taxation v Sara Lee Household & Body Care (Australia) Pty Ltd (2000) 201 CLR 520 cited
Applicant A v Minister for Immigration and Ethnic Affairs (1997) 190 CLR 225 cited
Mercantile Mutual Life Insurance Co Ltd v Australian Securities Commission (1993) 40 FCR 409 followed
Booth v Bosworth (2001) 114 FCR 39 followed
National Parks and Conservation Association v Babbitt 241 F3d 722 (9th Cir. 2001) citedTesco Supermarkets Ltd v Nattrass [1972] AC 153 cited
Hamilton v Whitehead (1988) 166 CLR 121 cited
Meridian Global Funds Management Asia Ltd v Securities Commission [1995] 2 AC 500 cited
Australian Competition and Consumer Commission v Australian Safeway Stores Pty Ltd (2003) 198 ALR 657 citedMINISTER FOR THE ENVIRONMENT AND HERITAGE v RONALD GREENTREE & ORS
N 914 of 2003SACKVILLE J
SYDNEY
11 JUNE 2004
IN THE FEDERAL COURT OF AUSTRALIA
NEW SOUTH WALES DISTRICT REGISTRY
N 914 OF 2003
BETWEEN:
MINISTER FOR THE ENVIRONMENT AND HERITAGE
APPLICANTAND:
RONALD GREENTREE
FIRST…
Keep reading for free
Create a free CaseChat account to read Minister for the Environment & Heritage v Greentree (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2004] FCA 741
- Decision Date
CaseChat Overview and Summary
The court had to decide several key legal issues. First, it needed to determine if there was sufficient evidence to conclude that Mr. Greentree and Auen had engaged in activities that significantly impacted the ecological character of the Windella Ramsar site, thus contravening s 16(1) of the EPBC Act. Second, the court considered whether the Minister had established grounds for injunctive relief under s 475(2) of the EPBC Act against the named respondents. Additionally, the court had to address whether the relief should include remediation orders as per s 475(3) of the EPBC Act. Finally, the court examined the claims against the other respondents, deciding if any grounds existed for granting relief against them.
The court concluded that Mr. Greentree and Auen had indeed contravened s 16(1) of the EPBC Act by taking actions that had a significant impact on the ecological character of the Windella Ramsar site. Therefore, they were liable for civil penalties under ss 16 and 481 of the EPBC Act. The court also found that the Minister had established a basis for injunctive relief against Ms. Greentree and Auen, subject to discretionary considerations. However, there was insufficient evidence to warrant injunctive relief against the other respondents, and their claims were dismissed. Consequently, the court directed the Minister to file and serve specific documents within 14 days, including short minutes of order, written submissions, and evidence on penalty and costs. The respondents were also required to file and serve their own documents within another 14 days.
The final orders required the Minister to file and serve short minutes of order consistent with the reasons for judgment, along with supporting written submissions, additional evidence, submissions on penalty, and submissions on costs. Similarly, the respondents had to file and serve their own short minutes of order, written submissions, additional evidence, submissions on penalty, and submissions on costs. These orders aimed to facilitate further proceedings regarding the civil penalties, injunctive relief, and remediation orders against the respondents.
Orders
Orders of the court
1. Within 14 days the Minister file and serve:
(a) short minutes of order consistent with these Reasons for Judgment, specifying the orders that should be made against Mr Greentree and Auen (other than the civil penalties that should be imposed) and providing for dismissal of the proceedings against the other respondents;
(b) written submissions in support of the short minutes of order;
(c) additional evidence (if any) on which the Minister intends to rely in support of the short minutes of order;
(d) any evidence on which the Minister intends to rely on the question of penalty;
(e) written submissions on penalty; and
(f) written submissions on costs.
2. Within a further 14 days the respondents file and serve:
(a) short minutes of order, consistent with these Reasons for Judgment, to the extent that the respondents dispute the short minutes of order filed and served by the Minister;
(b) written submissions in support of the respondents’ short minutes of order;
(c) additional evidence (if any) on which the respondents intend to rely in support of the respondents’ short minutes of order;
(d) any evidence on which Mr Greentree and Auen intend to rely on the question of penalty;
(e) written submissions on behalf of Mr Greentree and Auen on penalty; and
(f) written submissions on costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: SACKVILLE J
The 6th Meeting approved a ‘Strategic Plan 1997-2002’ (Resolution VI.14). The Strategic Plan specified a number of ‘General Objectives’. General Objective 5 was ‘to ensure the conservation of all sites concluded in the [List]’. Under this heading, the Strategic Plan stated a number of ‘Operational Objectives’. Operational Objective 5.3 was as follows:‘Operational Objective 5.3:To obtain regularly updated information on wetlands of international importance, in accordance with the approved standard format.Action 5.3.1 Ensure that the maps and descriptions of Ramsar sites submitted to the Ramsar Database by the Contracting Parties at the time of designation are complete, in the approved standard format of the Information Sheet on Ramsar Wetlands, and provide sufficient detail to be used for management planning and monitoring of ecological character. [CPs, Bureau, Wetlands International]Action 5.3.2 Ensure that missing or incomplete data sheets and/or maps of listed sites are submitted as a matter of priority and in the shortest possible time, as a means to enhance the relevance and use of the Ramsar Database. [CPs]Action 5.3.3 Ensure that data sheets on Ramsar Sites are regularly updated, at least for every second meting of the COP, so that they can be used for reviewing the achievements of the Convention, for future strategic planning, for promotional purposes, and for site, regional and thematic analysis (Resolution VI.13). [CPs, STRP, Bureau, Wetlands International]’A note to the General Objectives states that the body or bodies responsible for carrying out each Action is indicated in square brackets. ‘Bureau’ means the Ramsar Convention Bureau, ‘STRP’ means the Scientific and Technical Review Panel, while ‘Wetlands International’ is an ‘international partner Organisation’. The initials ‘CPs’ are not explained but presumably refer to ‘Contracting Parties’. As recorded in a document entitled ‘Measures Taken for Improving Data on Ramsar Sites’ (29 June 1997), the Ramsar Convention’s STRP and Bureau examined the Information Sheet on Ramsar Wetlands (‘RIS’) originally approved by Recommendation 4.7. The outcome was as follows:‘The text of the RIS has not been changed, but a new presentation has been adopted with the aim of making it easier to use. The presentation of the Guidelines which accompany the RIS has also been reviewed and improved.’ The amended RIS retained item 7 (Geographical ordinates) but renumbered it as item 4. The note to the new item 4 was in substance the same as the note to the previous item 7. Item 32 (Outline map of site) was renumbered item 10. The note to item 10 was revised from its previous form to read as follows:‘Outline map of site: The most detailed and up-to-date map of the wetland available should be appended to the Information Sheet. Indicate whether or not a map accompanies the Information Sheet by ticking the appropriate yes or no box.The “ideal” Ramsar site will clearly show the boundaries of the Ramsar site, scale, latitude, longitude and compass bearing, administrative boundaries (e.g., province, district, etc.), and display topographical information, the distribution of the main wetland habitat types and notable hydrological features. It will also show major landmarks (towns, roads, etc.). Indications of land use activities are especially useful.…The optimum scale for a map depends on the actual area of the site depicted. Generally the map should have a 1:25,000 or 1:50,000 scale for areas up to 10,000 ha; 1:100,000 scale for large areas up to 100,000 ha; 1:250,000 for areas exceeding 100,000 ha. In simplest terms, the site should be depicted in some detail…’ (Emphasis in original.)