| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL COURT
TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST
S ECI 2017 000009
| MINESCO PTY LTD (AS TRUSTEE FOR THE TARCISCO CREMASCO UNIT TRUST) (ABN 63 609 431 256) | Plaintiff |
| v | |
| ANDERSON SUNVAST HONG KONG LTD | First Defendant |
| And | |
| THOMAS JONES | Second Defendant |
---
JUDGE: | VICKERY J |
WHERE HELD: | MELBOURNE |
DATE OF HEARING: | 2 MAY 2017 |
DATE OF JUDGMENT: | 2 JUNE 2017 |
CASE MAY BE CITED AS: | MINESCO PTY LTD v ANDERSON SUNVAST HONG KONG LTD |
MEDIUM NEUTRAL CITATION: | [2017] VSC 299 |
---
ADMINISTRATIVE LAW — Judicial review — Delay in commencing proceeding — Extension of time — Supreme Court (General Civil Procedure) Rules 2015 (Vic) — O 56 — r 56.02(3).
ADMINISTRATIVE LAW — Building and Construction Industry Security of Payment Act 2002 (Vic) — Natural justice — Whether lack of appearance of procedural fairness in adjudication process amounts to breach of natural justice.
BUILDING AND CONSTRUCTION —Claim for relief in the nature of certiorari quashing an adjudication determination — Whether adjudicator denied respondent natural justice — The Hickory principle (Hickory Developments Pty Ltd v Schiavello (Vic) Pty Ltd & Anor (2009) 26 VR 112, 143 [142] considered — Building and Construction Industry Security of Payment Act 2002 (Vic) s 21.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr M H Whitten QC with Ms H J E Nash | Ganci Huggett Lawyers |
| For the First Defendant | Mr R Andrew | Giannakopoulos Solicitors |
HIS HONOUR:
Introduction
This proceeding concerns an application for judicial review of an adjudication determination made under the Building and Construction Industry Security of Payment Act 2002 (Vic) (‘the Act’).
The Plaintiff, Minesco Pty Ltd (‘Minesco’), is a company specialising in the supply of windows and material cladding for large-scale construction projects.
Minesco was contracted to supply façade works for the construction of the Monash Children’s Hospital in Clayton, Victoria (the ‘Project’).
In March 2015, Minesco entered into a design and fabrication subcontract with the First Defendant, Anderson Sunvast Hong Kong Ltd (‘Anderson’), for the manufacture, supply and delivery of curtain wall units from China for the Project, for the sum of $1,824,936.00.
On 2 August 2016, Anderson served a final payment claim on Minesco for the sum of $238,976.05 in respect of its works. The claim was endorsed as a final payment claim and was expressed to be a payment claim ‘made under the Building and Construction Industry Security of Payment Act (2002)’ in accordance with s 14(2)(e) of the Act.
On 9 August 2016, Minesco served a payment schedule under s 15 of the Act, in which the schedule amount was determined as ‘NIL’ on the basis of an alleged previous agreement between the parties, the upshot of which was alleged to be that Anderson owed Minesco $80,876, which was due and payable.
On 23 August 2016, Anderson submitted an Adjudication Application pursuant to s 18 of the Act to an authorised nominating authority, Adjudicate Today Pty Ltd (the ‘Nominating Authority’).
On 29 August 2016, the…
Continue reading Minesco Pty Ltd v Anderson Sunvast Hong Kong Ltd
Sign in free to access the full text
- AGLC
- Minesco Pty Ltd v Anderson Sunvast Hong Kong Ltd [2017] VSC 299
- Case
- [2017] VSC 299
- Decision Date
CaseChat Overview and Summary
The court needed to determine whether the adjudicator's process breached the principles of natural justice under the Building and Construction Industry Security of Payment Act 2002 (Vic). Specifically, it had to consider whether the lack of procedural fairness rendered the adjudication invalid. The court also examined the Hickory principle, drawing from the case of Hickory Developments Pty Ltd v Schiavello (Vic) Pty Ltd & Anor, which established criteria for assessing procedural fairness in adjudication processes.
The Supreme Court found that the adjudicator had indeed denied Minesco natural justice by not allowing them an opportunity to respond to critical evidence presented by the other party. The court concluded that this procedural lapse amounted to a significant breach of natural justice. Consequently, the court quashed the adjudication determination, aligning with the principle established in Hickory Developments. The court held that such a denial of procedural fairness could invalidate an adjudication determination.
The final order of the court was to quash the adjudication determination, thereby providing Minesco with the relief it sought. The court's decision underscored the importance of procedural fairness in adjudication processes, reinforcing the need for adjudicators to adhere to natural justice principles.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.