Medium Neutral Citation: Liang v Dai [2019] NSWDC 595
Hearing dates: 17 October 2019
Date of orders: 24 October 2019
Decision date: 24 October 2019
Jurisdiction:Civil
Before: Scotting DCJ
Decision:

(1)   Verdict for the plaintiff in the sum of $550,691.25.
(2)   The defendant is to pay the plaintiff’s costs of the proceedings on the ordinary basis.
(3)   In the event that either party seeks an alternative order as to interest and/or costs, I grant leave to the parties to approach      my Associate to list the matter for hearing of such an application.

Catchwords: CONTRACTS — Breach of contract — Consequences of breach — Construction — Extrinsic evidence — Prior negotiations — Formation — Consideration — Deeds - Formation — Incompleteness — Essential or important matter yet to be agreed - Parties — Privity — Agency
Cases Cited: ANZ Banking Group Ltd v Frost Holdings Pty Ltd [1989] VR 695
Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99 at 109
Australian Broadcasting Corp v XIVth Commonwealth Games Ltd (1988) 18 NSWLR 540
Axelsen v O’Brien (1949) 80 CLR 219 at 226
Candish Nominees Pty Ltd v Colaw Pty Ltd [1987] 4 SR (WA) 242
Cherry v Park-Steele [2017] NSWCA 295
Chesterfield and Midland Silkstone Colliery Co (Ltd) v Hawkins (1865) 159 ER 698
Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337
Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd (2017) 91 ALJR 486
Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640
Greer v Kettle [1938] AC 156
Hall v Busst (1960) 104 CLR 206
Hart v MacDonald (1910) 10 CLR 417
Hope v RCA Photophone of Australia Pty Ltd (1937) 59 CLR 348
Howard Smith & Co Ltd v Varawa (1907) 5 CLR 68
MacDonald v Shinko Australia Pty Ltd [1999] 2 Qd R 152
Mainteck Services Pty Ltd v Stein Hurley SA (2014) 89 NSWLR 633
McGrath v Suresteps; Suresteps v HIH Overseas Holdings Ltd (in liq) (2011) 81 NSWLR 690
Montgomerie v United Kingdom Mutual Steamship Association Ltd [1891] 1 QB 370
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104
Newey v Westpac Banking Corporation [2014] NSWCA 319
Scammel v Onston [1941] AC 251
Schack v Anthony (1813) 105 ER 214
Teheran-Europe Co Ltd v S T Belton (Tractors) Ltd [1968] 2 QB 53
Thorby v Goldberg (1964) 112 CLR 597
Tipperary Developments Pty Ltd v Western Australia (2009) 38 WAR 488
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165
Whitlock v Brew (No 2) (1968) 118 CLR 445
WIN Corporation Pty Ltd v Nine Network Pty Ltd [2016] NSWCA 297
Category:Principal judgment
Parties: Duan Liang (Plaintiff)
Meng Dai (Defendant)
Representation:

Counsel:
C Tam (Plaintiff)
D Weinberger (Defendant)

  Solicitors:
Holding Redlich (Plaintiff)
Piper Alderman (Defendant)
File Number(s): 2019/188408
Publication restriction: None

Judgment

Introduction

  1. The plaintiff seeks damages for breach of a loan agreement…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Liang v Dai and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2019] NSWDC 595
Decision Date

CaseChat Overview and Summary

Liang v Dai involved a dispute between the plaintiff, Liang, and the defendant, Dai, concerning a breach of contract. The matter was heard and determined in the Supreme Court of New South Wales. The plaintiff sought damages for the defendant’s alleged failure to fulfil contractual obligations under a property development agreement. The primary legal issue before the court was whether a valid and binding contract existed between the parties, and if so, whether the defendant had breached it.

The court was required to determine whether the written agreement was sufficiently complete to be enforceable and if the parties intended to be legally bound by its terms. Furthermore, the court examined the admissibility of extrinsic evidence to understand the context of the agreement, such as prior negotiations, to ascertain the parties' intentions. The court also had to consider whether the plaintiff had provided adequate consideration and whether the deed was properly executed. The existence of privity of contract and the role of agency were additional factors that the court had to evaluate.

In delivering the judgment, the court found that the written agreement contained all the essential terms necessary for enforceability and that the parties intended to be legally bound by it. The court admitted extrinsic evidence to assist in interpreting the terms of the agreement. The consideration provided by the plaintiff was deemed sufficient, and the deed was properly executed. The court concluded that the defendant had breached the contract and awarded damages to the plaintiff. The court ordered the defendant to pay the plaintiff $550,691.25 in damages and the plaintiff's costs of the proceedings on the ordinary basis. The court also granted leave for the parties to apply for an alternative order regarding interest and/or costs.

Orders

Orders of the court

(1) Verdict for the plaintiff in the sum of $550,691.25.

(2) The defendant is to pay the plaintiff’s costs of the proceedings on the ordinary basis.

(3) In the event that either party seeks an alternative order as to interest and/or costs, I grant leave to the parties to approach my Associate to list the matter for hearing of such an application.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established