CITATION: Laing O'Rourke v Transport Infrastructure [2007] NSWSC 723 HEARING DATE(S): 27th,28th June & 6th July 2007
JUDGMENT DATE :
17 July 2007JUDGMENT OF: Hammerschlag J DECISION: Summons dismissed CATCHWORDS: CONTRACT - Dispute resolution provision requiring party to negotiate in good faith - uncertainty - severance of uncertain provisions - construction of contracts - requirement to construe so as to allow harmonious operation LEGISLATION CITED: Commercial Arbitration Act 1984 NSW CASES CITED: Laws Holdings Pty Limited v Short (1972) 46 ALJR 563
Elizabeth Bay Developments Pty Limited v Boral Building Services Pty Limited (1995) 36 NSWLR 709
Walford v Miles [1992] 2 AC 128
Booker Industries Pty Limited v Wilson Parking (Queensland) Pty Limited (1982) 149 CLR 600
Coal Cliff Collieries Pty Limited v Sijehama Pty Limited (1991) 24 NSWLR 1
Aiton Australia Pty Limited v Transfield Pty Limited (1999) 153 FLR 236
Whitlock v Brew (No 2) [1967] VR 803
Whitlock v Brew (No 2) (1968) 118 CLR 445
Griffith University v Tang (2005) 221 CLR 99
State of New South Wales & Ors v Banabelle Electrical Pty Limited & Ors (2002) 54 NSWLR 503
Hooper Baillie Associated Limited v Natcon Group Pty Limited (1992) 28 NSWLR 194
Meehan v Jones (1982) 149 CLR 571
Trawl Industries of Australia Pty Limited v Effem Foods Pty Limited t/a “Uncle Bens of Australia” (1992) 27 NSWLR 326
IBM Australia Limited v National Distribution Services Limited (1991) 22 NSWLR 466
Francis Travel Marketing Pty Limited v Virgin Atlantic Airways Limited (1996) 39 NSWLR 160
Wilkie v Gordian Runoff Limited (2005) 221 CLR 522
Project Blue Sky Inc. v Australian Broadcasting Authority (1998) 194 CLR 355
Legal & General Life of Australia Ltd v A Hudson Pty Ltd (1985) 1 NSWLR 314
Dobbs v National Bank of Australasia Limited (1935) 53 CLR 643
Ex parte Young In Re Kitchin [1881] 17 Ch.D 668PARTIES: Laing O'Rourke (BMC) Pty Ltd
Transport Infrastructure Development Corporation
CRI Chatswood Pty Ltd
Laurie James (submitting appearance)FILE NUMBER(S): SC 55043/2007 COUNSEL: G Inatey SC with A Nicholls (Plaintiff)
A Meagher SC with G Rich (1st Defendant)
B Oslington QC with L V Gyles (2nd Defendant)SOLICITORS: Colin Biggers & Paisley (Plaintiffs)
Clayton Utz (First Defendant)
Blake Dawson Waldron (2nd Defendant)
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY & CONSTRUCTION LIST
HAMMERSCHLAG J
17 JULY 2007
55043/2007 LAING O'ROURKE (BMC) PTY LTD v TRANSPORT INFRASTRUCTURE DEVELOPMENT CORPORATION
JUDGMENT
BACKGROUND TO AND NATURE OF THIS DISPUTE
1 HIS HONOUR: There is presently being developed at
Chatswood on the North Shore Railway Line from Sydney to Hornsby, a new transport interchange with related retail, car park and other facilities.
2 On 24 June 2005 the first defendant (“TIDC”) a corporation constituted by s 18A of the Transport Administration Act 1988 (NSW), the second defendant (“CRI”) and two guarantor companies associated with CRI made a deed known as the Chatswood Transport Interchange or CTI Development Deed (“the Development Deed”) which sets out the…
Keep reading for free
Create a free CaseChat account to read Laing O'Rourke v Transport Infrastructure and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2007] NSWSC 723
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the dispute resolution provision, which required the parties to negotiate in good faith, was uncertain and therefore unenforceable. If the provision was found to be uncertain, the court had to consider whether it could be severed from the rest of the contract, allowing the remaining provisions to stand. Additionally, the court needed to interpret the contract as a whole to ensure its harmonious operation.
The court found that the dispute resolution provision was uncertain as it did not define what was meant by "negotiate in good faith." However, the court held that the uncertainty could be severed from the rest of the contract, allowing the other provisions to remain in effect. The court emphasised the importance of construing contracts in a way that allows for the harmonious operation of all its provisions. The court ordered that the parties must negotiate in good faith, but did not define what that meant, leaving it to the parties to determine in the context of their specific dispute. The court's decision ensured that the contract could continue to operate effectively, while also acknowledging the uncertainty in the dispute resolution provision.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.