[2014] TASFC 10
COURT: SUPREME COURT OF TASMANIA (FULL COURT)
CITATION: Kronenberg v Bridge [2014] TASFC 10
PARTIES: KRONENBERG, David Gerald
KRONENBERG, Robyn Joy
v
BRIDGE, Stephen
FILE NO: 1045/2013
JUDGMENT
APPEALED FROM: Kronenberg v Bridge [2013] TASSC 57
DELIVERED ON: 20 October 2014
DELIVERED AT: Hobart
HEARING DATES: 11, 12 March 2014
JUDGMENT OF: Blow CJ, Porter and Pearce JJ
CATCHWORDS:
Contracts – Building, engineering and related contracts – The contract – Generally – Formation of contract – Standard form of fixed price contract endorsed "as a cost plus contract" – Whether contract made.
Scammell (G) & Nephew Ltd v Ouston [1941] AC 251; York Air Conditioning and Refrigeration (A/sia) Pty Ltd v Commonwealth (1949) 80 CLR 11; Upper Hunter County District Council v Australian Chilling and Freezing Co Ltd (1968) 118 CLR 429; Meehan v Jones (1982) 149 CLR 571, referred to.
Aust Dig Contracts [250]
Contracts – Building, engineering and related contracts – The contract – Construction of particular contracts and implied conditions – Determination of cost – Standard form of fixed price contract endorsed "as a cost plus contract" – Estimated price specified – Whether estimated price promissory or representational.
Hospital Products Ltd v United States Surgical Corporation (1984) 156 CLR 41, referred to.
Aust Dig Contracts [257]
Trade and Commerce – Trade Practices Act 1974 (Cth) and related legislation – Enforcement and remedies – Actions for damages – Assessment or availability of damages – What loss or damage recoverable – Lost commercial opportunity – Misleading representation as to cost of future building works – Loss of opportunity to enter into more advantageous contract.
Fair Trading Act 1990 (Tas), s37.
Doepel & Associates Architects Pty Ltd v Hodgkinson [2008] WASCA 262; Dominelli Ford (Hurstville) Pty Ltd v Carmot Auto Spares Pty Ltd (1992) 38 FCR 471; Doolan v Renkon Pty Ltd (2011) 21 Tas R 156, referred to.
Aust Dig Trade and Commerce [1138]
REPRESENTATION:
Counsel:
Appellants: S B McElwaine SC
Respondent: M E O'Farrell SC
Solicitors:
Appellants: Shaun McElwaine + Associates
Respondent: Toomey Maning & Co
Judgment Number: [2014] TASFC 10
Number of paragraphs: 144
Serial No 10/2014
File No 1045/2013
DAVID GERALD KRONENBERG and ROBYN JOY KRONENBERG
v STEPHEN BRIDGE
REASONS FOR JUDGMENT FULL COURT
BLOW CJ
PORTER J
PEARCE J
20 October 2014
Order of the Court
Further hearing of appeal adjourned.
Serial No 10/2014
File No 1045/2013
DAVID GERALD KRONENBERG and ROBYN JOY KRONENBERG
v STEPHEN BRIDGE
REASONS FOR JUDGMENT FULL COURT
BLOW CJ
20 October 2014
The appellants, David and Robyn Kronenberg, own some land at Eaglehawk Neck. The respondent, Stephen Bridge, is a builder. On 2 January 2007 the appellants entered into an arrangement with the respondent for him to build a house on their land. The respondent worked on the construction of the house from January 2007 until October 2008, but did not complete it. During that period the appellants made payments to the…
Keep reading for free
Create a free CaseChat account to read Kronenberg v Bridge and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2014] TASFC 10
- Decision Date
CaseChat Overview and Summary
The court was required to determine the legal effect of the conflicting terms within the contract document. Specifically, it had to consider whether the endorsement "as a cost plus contract" fundamentally altered the nature of the standard form fixed price contract, thereby preventing the formation of a binding agreement, or if a contract could still be found to exist despite the apparent contradiction.
The court's reasoning focused on the principles of contract formation, particularly the requirement for a clear and unequivocal agreement on essential terms. The judges considered whether the parties had reached a consensus *ad idem* given the contradictory nature of the contract's terms. The court noted that the endorsement created an ambiguity that cast doubt on the parties' intention to be bound by either a fixed price or a cost plus arrangement.
The further hearing of the appeal was adjourned.
Orders
Orders of the court
Further hearing of appeal adjourned.