QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Kroll v Kovac [2024] QCAT 143
PARTIES:
NEIL KROLL (applicant)
v
ZVONIMIR KOVAC (respondent)
APPLICATION NO/S:
BDL179-22
MATTER TYPE:
Building matters
DELIVERED ON:
10 April 2024
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Member D Brown
ORDERS:
The Tribunal directs Zvonimir Kovac pay Neil Kroll the sum of $3,654 by 4:00 pm on 10 June 2024.
CATCHWORDS
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF PAINTING WORK – REMEDIES FOR BREACH OF CONTRACT – IMPLIED TERMS AND WARANTIES – DAMAGES – where there was no formal contract in writing signed by the parties – where work is defective – where the owner was entitled to recover for damage caused by the building contractor for defective work
Queensland Building and Construction Commission Act 1991 (Qld)
Queensland Civil and Administrative Tribunal Act 2009 (Qld)
Atkinson and Anor v Van Uden [2020] QCAT 259
Cameron v Guise [2019] QCAT 220
Ghama v Crew & Anor [2020] QCAT 149
Skinner v FTP Contracting Pty Ltd & Anor (No 2) [2020] QCATA 12
APPEARANCES & REPRESENTATION:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act2009 (Qld)
REASONS FOR DECISION
Background
The respondent, Mr Kovac, carried out painting of the front facing section of the applicant, Mr Kroll’s house. The email quote indicates it was to paint the roof tiles, fretwork, gutters/facer, eves, post, handrails, a screen door and the letter box for the applicant homeowner, Mr Kroll. The contract price as per an email dated 22 April 2020 was $1,850.00, requested to be paid in cash with a $1,000 deposit and $850 on completion.
Mr Kroll discussed the work with Mr Kovac before agreeing to him undertaking the work and believed him to be a professional painter as per his business card. Mr Kroll states Mr Kovac told him he had painted roofs previously and would prep the roof and apply a primer and special membrane paint, and guaranteed it would last 10-15 years, commenting it would probably last 20 years.[1]
[1]Applicant’s written statement dated 3 November 2022.
Work was completed on or around 27 May 2020 and Mr Kroll paid the $1,850 in full.
As is unfortunately not uncommon, the parties adopted a somewhat relaxed approach to the formation of the agreement for the performance of the building work. No written contract was entered into by the parties and the contract is limited to Mr Kovac’s email quote for the work on 22 April 2020 and oral conversations.
Mr Kroll’s claim against Mr Kovac is for defective work as he asserts the paint started to peel in large pieces after 6 months and he first contacted Mr Kovac by phone in January 2021. At that time Mr Kovac indicated he would repaint the roof, but never attended to rectify the work.
There is evidence provided by the applicant that he contacted the respondent Mr…
Continue reading Kroll v Kovac
Sign in free to access the full text
- AGLC
- Kroll v Kovac [2024] QCAT 143
- Case
- [2024] QCAT 143
- Decision Date
CaseChat Overview and Summary
The Tribunal found that although there was no formal written contract, the parties' conduct and communications established an implied agreement for the painting work. The Tribunal relied on the principle that oral agreements can be just as binding as written ones if the circumstances demonstrate an intention to create legal relations. The Tribunal held that Kovac breached the contract by failing to perform the work to the required standard, as evidenced by the poor quality of the painting which necessitated further work to rectify. The measure of damages was assessed based on the additional costs incurred by Kroll to have the work redone properly. The Tribunal concluded that the amount claimed by Kroll was reasonable and proportionate to the defective work performed by Kovac.
Accordingly, the Tribunal ruled in favour of Kroll and ordered Kovac to compensate Kroll for the defective work. Specifically, the Tribunal directed Kovac to pay Kroll the sum of $3,654 by 4:00 pm on 10 June 2024. The Tribunal considered this amount to be a fair reflection of the costs incurred by Kroll to rectify the substandard work performed by Kovac. This decision underscores the enforceability of oral contracts in appropriate circumstances and the obligation of contractors to perform their work to a satisfactory standard.
Orders
Orders of the court
The Tribunal directs Zvonimir Kovac pay Neil Kroll the sum of $3,654 by 4:00 pm on 10 June 2024.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.