Skinner v FTP Contracting Pty Ltd & Anor (No 2) [2020] QCATA 12
PARTIES: MATTHEW SKINNER (appellant)
v
FTP CONTRACTING PTY LTD
and
MATTHEW COATES(respondents)
APPLICATION NO/S:
APL119-19
ORIGINATING APPLICATION NO/S:
MCDO 50102/19 (Southport)
MATTER TYPE:
Appeals
DELIVERED ON:
23 January 2020
HEARING DATE:
8 November 2019
HEARD AT:
Brisbane
DECISION OF:
Member Gordon
ORDERS: 1. The decision made on 24 April 2019 in application MCDO 50102/19 (Southport) is corrected pursuant to section 135 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) as follows:
‘1. Matthew Coates to be added as a second applicant.
2. Matthew Skinner to pay Matthew Coates $4877.23 within 21 days.’
2. Leave to appeal is granted.
3. On a rehearing under section 147 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) the decision made on 24 April 2019 in application MCDO 50102/19 (Southport) is set aside, and the application is dismissed for lack of jurisdiction.
CATCHWORDS: APPEAL AND NEW TRIAL – APPEAL – GENERAL PRINCIPLES – INTERFERENCE WITH JUDGE’S FINDINGS OF FACT – OTHER MATTERS – where the panel found that a contract existed for work which did not require a licence – where an appeal was brought against those findings – where in an appeal hearing it appeared that the panel’s findings were probably incorrect – whether leave to appeal should be given resulting in a rehearing
ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – restrictions on the minor civil disputes jurisdiction of the tribunal – whether the tribunal has jurisdiction to deal with a minor civil disputes on a quantum meruit – whether the claim is a building dispute and if so whether the pre-action QBCC conciliation has taken place – whether the tribunal has jurisdiction to deal with a building dispute as a minor civil dispute if it is a claim to recover a debt or a liquidated demand of money
CONTRACT – GENERAL CONTRACTUAL PRINCIPLES – FORMATION OF CONTRACTUAL RELATIONS – MATTERS NOT GIVING RISE TO BINDING CONTRACT – vagueness and uncertainty – agreements not intended to create legal relations – where work done at house but no written contract, no agreed remuneration, and other uncertainties – where parties had reasons other than an ordinary commercial transaction for the work to be done – whether a contract was entered into
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 135, s 142, s 146, s 147
Queensland Building and Construction Commission Act 1991 (Qld), s 42, s 77
Queensland Building and Construction Commission Regulation 2003 (Qld), s 5, s 2, Schedule 1AA
Ericson v Queensland Building Services Authority [2013] QCA 391
APPEARANCES & REPRESENTATION:
Appellant:
G D Robson, principal of North Law Solicitors
Respondent:
Self-represented
REASONS FOR DECISION
This application started life as one brought in the minor civil disputes jurisdiction of the tribunal by FTP Contracting…
Keep reading for free
Create a free CaseChat account to read Skinner v FTP Contracting Pty Ltd & Anor (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QCATA 12
- Decision Date
CaseChat Overview and Summary
The central legal issues in the appeal were whether QCAT had jurisdiction to hear the case as a minor civil dispute under the Queensland Civil and Administrative Tribunal Act 2009 (Qld) and whether a binding contract existed between the parties. The appeal also examined whether the claim was a building dispute and if the pre-action QBCC conciliation had taken place, which are jurisdictional prerequisites for such disputes. Additionally, the appeal considered whether QCAT had the authority to hear a building dispute as a minor civil dispute if the claim was to recover a debt or a liquidated sum of money.
The appeal panel found that the original QCAT decision contained errors of law and fact, particularly regarding the existence of a binding contract. The panel concluded that the work done did not result from a binding contract due to the absence of written agreement, agreed remuneration, and other uncertainties. The panel also determined that QCAT lacked jurisdiction to hear the matter as a minor civil dispute since the claim was essentially a building dispute without the required pre-action QBCC conciliation. Consequently, the appeal was allowed, and the original decision was set aside.
The final orders included correcting the original decision to add Matthew Coates as a second applicant, requiring Matthew Skinner to pay Matthew Coates $4877.23 within 21 days, granting leave to appeal, and setting aside the original decision for lack of jurisdiction on rehearing.
Orders
Orders of the court
1. The decision made on 24 April 2019 in application MCDO 50102/19 (Southport) is corrected pursuant to section 135 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) as follows:
‘1. Matthew Coates to be added as a second applicant.
2. Matthew Skinner to pay Matthew Coates $4877.23 within 21 days.’
2. Leave to appeal is granted.
3. On a rehearing under section 147 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) the decision made on 24 April 2019 in application MCDO 50102/19 (Southport) is set aside, and the application is dismissed for lack of jurisdiction.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.