SUPREME COURT OF QUEENSLAND
CITATION:
Kinsella & Anor v Gold Coast City Council (No 3) [2016] QSC 14
PARTIES:
HELEN BARBARA KINSELLA AND PETER LOUIS KINSELLA
(plaintiffs)
v
GOLD COAST CITY COUNCIL
(defendant)FILE NO:
5010 of 2013
DIVISION:
Trial
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court of Queensland
DELIVERED ON:
19 February 2016
DELIVERED AT:
Brisbane
HEARING DATE:
20 and 21 July 2015; plaintiffs’ further written submissions dated 29 July 2015; submissions in reply on behalf of LMS Energy Pty Ltd dated 6 August 2015; further submissions on behalf of Energex Limited dated 6 August 2015
JUDGE:
Burns J
ORDER:
The orders of the court are:
1. Pursuant to r 69 of the Uniform Civil Procedure Rules 1999 (Qld), that:
(a) LMS Energy Pty Ltd be included as the second defendant to this proceeding;
(b) Energex Limited be included as the third defendant to this proceeding;
2. Pursuant to r 377 of the Uniform Civil Procedure Rules 1999 (Qld), that leave be granted to the plaintiffs to file and serve the Amended Claim and Second Further Amended Statement of Claim in terms of the drafts forming, respectively, exhibit MTS1 to the affidavit of Michael Thomas Smith filed on 6 February 2015 and exhibit MTS3 to the affidavit of Michael Thomas Smith filed on 9 July 2015.
CATCHWORDS:
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – JOINDER OF CAUSES OF ACTION AND OF PARTIES – PARTIES – GENERALLY – where the defendant raised allegations of concurrent wrongdoing in its defence – where the plaintiff brought an application under s 69 of the Uniform Civil Procedures Rules 1999 (Qld) seeking to join the alleged concurrent wrongdoers to the proceeding – whether the plaintiffs have demonstrated an arguable case against the alleged concurrent wrongdoers – whether joinder is ‘necessary’ or ‘desirable, just and convenient’ to adjudicate effectually and completely on all matters in dispute in, or connected with the proceeding
Civil Liability Act 2003 (Qld) s 30, r 31, s 32, s 32A, s 32C
Uniform Civil Procedures Rules 1999 (Qld) r 69, r 75, r 377
Agar v Hyde [2000] HCA 41; (2000) 201 CLR 552
Batistatos v Roads and Traffic Authority of New South Wales [2006] HCA 27; (2006) 226 CLR 256
Brookfield Multiplex Ltd v Owners Corporation Strata Plan 61288 [2014] HCA 36; (2014) 254 CLR 185
Butler & Ors v State of Queensland [2013] QSC 354; [2014] 2 Qd R 423
Caltex Refineries (Qld) Pty Ltd v Stavar [2009] NSWCA 258; (2009) 75 NSWLR 649
Church of Scientology Inc v Woodward [1982] HCA 78; (1982) 154 CLR 25
General Steel Industries Inc v Commissioner for Railways (NSW) [1964] HCA 69; (1964) 112 CLR 125
Graham Barclay Oysters Pty Ltd v Ryan [2002] HCA 54; (2002) 211 CLR 540
HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd [2004] HCA 54; (2004) 217 CLR 640
Kestrel Coal Pty Ltd v Longwall Roof Supports Ltd & Ors [2003] QSC…
Keep reading for free
Create a free CaseChat account to read Kinsella v Gold Coast City Council (No 3) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] QSC 14
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were whether the plaintiff had demonstrated an arguable case against LMS and Energex and whether the joinder of these entities was necessary, desirable, just, and convenient to ensure that all matters in dispute, or connected with the proceeding, could be effectively and completely adjudicated. The court had to balance the plaintiff's right to join additional defendants against the principles of judicial economy and fairness to the defendants.
The court found that the plaintiff's allegations against LMS and Energex were sufficiently substantiated to warrant their inclusion as defendants. The plaintiff had alleged that LMS had been responsible for designing and implementing a landfill gas extraction system and that Energex had contracted with LMS to operate and maintain this system. The court also noted that the loss alleged by the plaintiff was not contingent but had occurred in or about September 2009, as evidenced by expert valuation. Therefore, the court concluded that the joinder of LMS and Energex was necessary and desirable to ensure complete and effectual adjudication of the matter.
Accordingly, the court made the following orders: LMS Energy Pty Ltd and Energex Limited were to be included as defendants in the proceeding. The plaintiff was granted leave to file and serve an amended claim and a second further amended statement of claim. The court also indicated that it would hear the parties on the issue of costs, with a preliminary view that the costs of and incidental to this application should be borne by each party in the proceeding.
Orders
Orders of the court
The orders of the court are:
1. Pursuant to r 69 of the Uniform Civil Procedure Rules 1999 (Qld), that:
(a) LMS Energy Pty Ltd be included as the second defendant to this proceeding;
(b) Energex Limited be included as the third defendant to this proceeding;
2. Pursuant to r 377 of the Uniform Civil Procedure Rules 1999 (Qld), that leave be granted to the plaintiffs to file and serve the Amended Claim and Second Further Amended Statement of Claim in terms of the drafts forming, respectively, exhibit MTS1 to the affidavit of Michael Thomas Smith filed on 6 February 2015 and exhibit MTS3 to the affidavit of Michael Thomas Smith filed on 9 July 2015.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
It only remains to be said that, in assessing whether LMS or Energex should be joined as defendants, the focus must necessarily be on the causes of action proposed on behalf of the named plaintiffs as opposed to the represented parties. Consideration Before turning to the specific arguments advanced on behalf of LMS and Energex, it is useful to commence with a brief summary of the case advanced against each under the proposed pleading. The proposed cases against LMS and Energex By the proposed pleading, the case against LMS is put in this way. From late 1998, the Council had “a series of dealings” with LMS for the purpose of obtaining advice “as to how the risks posed by [the landfill facility] could be addressed by closure and as to the implementation of an appropriate [landfill gas] collection and extraction system”. In early 1999, LMS was commissioned by the Council to evaluate the facility’s compliance with an environmental authority issued under the provisions of the Environmental Protection Act 1994 (Qld). From no later than August 1999, that authority required the Council to, amongst other things, develop and implement a landfill gas monitoring program to ensure that the facility complied with certain release standards for landfill gas. In the event that methane gas levels exceeded those standards, the Council was required by the authority to “take all necessary steps to ensure protection of human health” and to “install a collection system for landfill gas … to minimise the likelihood of any subsurface migration of landfill gas … [and to] prevent or minimise any uncontrolled emission of landfill gas”. During the first half of 1999, LMS provided written reports to the Council that contained advice and recommendations as to the steps necessary to manage landfill gas at the facility and, by around June of that year, the Council and LMS were aware that there was a significant lateral migration of landfill gas occurring on at least the Western batter of the facility. Subsequently, LMS designed a landfill gas extraction system for the facility. Then, on 4 October 2001, LMS entered into two written agreements with Energex under which LMS agreed to install the system and to operate, maintain and monitor it. By the provisions of one of the agreements,[23] LMS agreed to “provide all things and take all measures necessary to protect people, property and the environment”,[24] to “prevent, as is reasonable in the circumstances, nuisance and unreasonable noise and disturbance”[25] and comply with the terms of the environmental authority.[26] It is then alleged that from 2002 to April 2009, LMS was “directly responsible for the installation, maintenance, operation and monitoring of” the system designed by it and had “the power to install, maintain, operate and monitor” the system “so as to prevent existing and future owner of lots” in the residential estate from “suffering loss and damage in the form of diminution in the value of their land by the migration of landfill gas” from the facility.[23] The Operation and Management Agreement.[24] Clause 3.2(a).[25] Clause 3.2(b).[26] Clause 3.2(f).