Project Company No 2 Pty Ltd v Cushway Blackford and Associates Pty Ltd

Link copied
Case Copied 20 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Project Company No 2 Pty Ltd v Cushway Blackford & Associates Pty Ltd & Anor [2011] QCA 102

PARTIES:

PROJECT COMPANY NO 2 PTY LTD
ACN 051 834 309
(appellant)
v
CUSHWAY BLACKFORD & ASSOCIATES PTY LTD
ACN 010 522 988
(first respondent)
ACN 066 045 645 PTY LIMITED
ACN 066 045 645
(second respondent)

FILE NO/S:

Appeal No 13097 of 2010
SC No 5192 of 2006
SC No 7296 of 2007

DIVISION:

Court of Appeal

PROCEEDING:

General Civil Appeal

ORIGINATING COURT:

Supreme Court at Brisbane

DELIVERED ON:

17 May 2011

DELIVERED AT:

Brisbane

HEARING DATE:

8 April 2011

JUDGES:

Muir and White JJA and Peter Lyons J
Separate reasons for judgment of each member of the Court, each concurring as to the orders made

ORDERS:

The appeal be allowed with costs.1.   

Project Company No 1 Pty Ltd (ACN 107 480 375) be added as a plaintiff in the proceedings.2.   

The plaintiffs have leave to make consequential amendments to the claim within seven days of today’s date.3.   

The plaintiffs make such amendments to the statement of claim last filed in the proceedings as they may be advised within fourteen days of today’s date.4.   

CATCHWORDS:

PROCEDURE – SUPREME COURT PROCEDURE – QUEENSLAND – PROCEDURE UNDER RULES OF COURT – PARTIES – JOINDER AND ADDITION OF PARTIES – where the appellant entered into a contract for the construction of an abattoir and associated facilities – where the respondents were engaged as subcontractors for the construction of the abattoir and associated facilities – where there was a fire in the main switchboard of the abattoir – where the appellant brought claims in negligence and breach of contract against the respondents – where the appellant’s parent company suffered the loss claimed in the proceeding – whether the primary judge erred in dismissing the appellant’s applications for leave to join its parent company as a party to the proceeding and to amend the claim and statement of claim to effect the proposed joinder

TORTS – NEGLIGENCE – ESSENTIALS OF ACTION FOR NEGLIGENCE – DUTY OF CARE – WHERE ECONOMIC OR FINANCIAL LOSS – where the appellant’s parent company suffered loss through the interruption of its business as a result of a failure in the switchboard of an abattoir – where the parent company was not a party to the relevant contract – whether a designer or builder of a commercial premises owes a duty of care to persons with whom they have no contractual relationship – whether the primary judge erred

Uniform Civil Procedure Rules 1999 (Qld), r 69(1)(b), r 377

Barrett v Enfield London Borough Council [2001] 2 AC 550, considered
Bryan v Maloney (1995) 182 CLR 609; [1995] HCA 17, distinguished
Caltex Oil (Australia) Pty Ltd v Dredge Willemstad (1976) 136 CLR 529; [1976] HCA 65, considered
Fangrove Pty Ltd v Tod Group Holdings Pty Ltd [1999] 2 Qd R 236; [1998] QCA 404, distinguished
Woolcock Street Investments…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Project Company No 2 Pty Ltd v Cushway Blackford and Associa... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2011] QCA 102
Decision Date

CaseChat Overview and Summary

Project Company No 2 Pty Ltd (the appellant) sought to join its parent company, Project Company No 1 Pty Ltd (the proposed joiner), as a party to proceedings against Cushway Blackford and Associates Pty Ltd (the respondents), who were subcontractors engaged in the construction of an abattoir. The appellant claimed that the respondents’ negligence and breach of contract caused a fire in the main switchboard, leading to financial loss for the parent company due to business interruption. The Supreme Court of Queensland dismissed the appellant’s applications to join the parent company and amend the statement of claim. The appellant appealed to the court, arguing that the primary judge erred in dismissing these applications.

The primary legal issue before the court was whether the primary judge was correct in dismissing the appellant's applications for leave to join the parent company as a party to the proceeding and to amend the claim and statement of claim accordingly. A secondary issue was whether the parent company, which had no contractual relationship with the respondents, could claim for economic loss resulting from the fire in the abattoir’s switchboard. The court needed to determine if a designer or builder of a commercial premises owes a duty of care to persons with whom they have no contractual relationship.

The court found that the primary judge erred in dismissing the appellant’s applications. The court held that the parent company could be joined as a party to the proceeding because it suffered the economic loss claimed in the proceeding. The court also held that the parent company could claim for economic loss, as a designer or builder of a commercial premises may owe a duty of care to persons with whom they have no contractual relationship if the loss was reasonably foreseeable. The court concluded that the primary judge failed to consider the parent company’s potential claim for economic loss and whether it could be joined as a party to the proceeding. The appeal was allowed, and the parent company was added as a plaintiff in the proceedings. The plaintiffs were granted leave to make consequential amendments to the claim and statement of claim within specified timeframes.

Orders

Orders of the court

The appeal be allowed with costs.1.

Project Company No 1 Pty Ltd (ACN 107 480 375) be added as a plaintiff in the proceedings.2.

The plaintiffs have leave to make consequential amendments to the claim within seven days of today’s date.3.

The plaintiffs make such amendments to the statement of claim last filed in the proceedings as they may be advised within fourteen days of today’s date.4.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established