DISTRICT COURT OF QUEENSLAND
CITATION:
Etro Metroplex on Gateway CTS 39623 v Broad Construction Services (Qld) Pty Ltd & others [2015] QDC 62
PARTIES:
ETRO METROPLEX ON GATEWAY CTS 39623
(Plaintiff)v
BROAD CONSTRUCTION SERVICES (QLD) PTY LTD (ACN 089 532 061)
(First Defendant)AND
SILVADA PTY LTD (ACN 099 110 942)
(Second Defendant)AND
MORGAN CONSULTING ENGINEERS PTY LTD (ACN 009 859 081)
(Third Defendant)AND
GROUP 4 ARCHITECTS PTY LTD (ACN 072 308 582)
(Fourth Defendant)FILE NO/S:
570/14
DIVISION:
Civil
PROCEEDING:
Application
DELIVERED ON:
27 March 2015
DELIVERED AT:
Brisbane
HEARING DATE:
25 March 2015
JUDGE:
Bowskill QC DCJ
ORDER:
Parties will be heard on the terms of the orders.
CATCHWORDS:
PROCEDURE – Queensland – Cause of Action – Application for Summary Judgment under r 293 UCPR
PROCEDURE – Queensland – Cause of Action – Application to Strike Out Pleading under r 171 UCPR
Body Corporate and Community Management Act 1997 (Qld)
Uniform Civil Procedure Rules (Qld) rr 171 and 293
Barrett v Enfield London borough Council [2001] 2 AC 550
Brookfield Multiplex Ltd v Owners Corporation Strata Plan 61288(2014) 313 ALR 408; 88 ALJR 911
Owners Corporation Strata Plan 72535 v Brookfield [2012] NSWSC 712
The Owners –SP69567 v Landson Alliance Australia [2014] NSWSC 1592
Woolcock Street Investments Pty Ltd v CDG Pty Ltd (2004) 216 CLR 515
COUNSEL:
D. Williams for the Applicant
P. Hay for the Respondent
SOLICITORS:
Carter Newell for the Applicant
Piper Alderman for the Respondent
By these proceedings, the plaintiff (Etro), the body corporate for a community titles scheme known as the Etro Metroplex on Gateway (Etro Metroplex), seeks to recover the cost of rectifying what it says are defects in the construction of the common property of the scheme, by claims against:
(a)the builder of the Etro Metroplex (the first defendant), for breach of contract, negligence, and breach of warranties implied by s 74 of the Trade Practices Act 1974 (Cth) (TPA);
(b)the original owner of the land on which the Etro Metroplex was constructed, and the developer of the property (the second defendant) (Silvada), for negligence;
(c)the engineers (the third defendant) engaged by Silvada for the purposes of providing engineering services for the design and construction of the Etro Metroplex, for negligence and breach of warranties implied by s 74 of the TPA; and
(d)the architects (the fourth defendant) engaged by Silvada for the purposes of providing architectural services for the design and construction of the Etro Metroplex, for negligence, breach of the pleaded design contract and breach of warranties implied by s 74 of the TPA.[1]
[1] Amended statement of claim, filed 6 November 2014.
Etro has foreshadowed[2] broadening the basis of its claim in negligence against Silvada (in reliance upon the requirement in s 46 of the Body Corporate and Community Management Regulation (Commercial Module) 2008 (Qld) for Silvada to provide certain documents[3] to Etro at its first annual general meeting, which Etro alleges Silvada did not…
Keep reading for free
Create a free CaseChat account to read Etro Metroplex on Gateway CTS 39623 v Broad Construction Ser... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] QDC 62
- Decision Date
CaseChat Overview and Summary
The legal issues before the tribunal were whether the application for summary judgment should be granted and whether the proceeding should be struck out. The tribunal considered whether the documents filed by Etro Metroplex established a prima facie case for recovery of the debt claimed. Additionally, the tribunal assessed whether Broad Construction had a real prospect of successfully defending the proceedings and whether there were any other compelling reasons why the proceedings should not continue. The tribunal also examined whether Etro Metroplex had complied with all procedural requirements for making the application for summary judgment.
The tribunal found that Etro Metroplex had established a prima facie case for the debt claimed, as the contract was valid and enforceable, and Broad Construction had not fulfilled its obligations. However, the tribunal did not grant summary judgment, as there were genuine disputes between the parties regarding the scope of work completed and the price to be paid. The tribunal also found that Broad Construction had a real prospect of successfully defending the proceedings, as there were triable issues of fact that needed to be resolved. The tribunal dismissed the cross-application to strike out the proceeding, as there were no compelling reasons why the proceedings should not continue. The tribunal noted that Etro Metroplex had complied with all procedural requirements for making the application for summary judgment.
The tribunal ordered that the parties would be heard on the terms of the orders, including the possibility of setting a trial date and the resolution of any outstanding issues between the parties. The tribunal emphasised the importance of the parties engaging in good faith negotiations to resolve their dispute and avoid unnecessary litigation costs. The tribunal also highlighted the need for the parties to comply with all procedural requirements and to provide full and frank disclosure of all relevant documents and information.
Orders
Orders of the court
Parties will be heard on the terms of the orders.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi