Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: Kelly v Southern Pacific Builders Pty Ltd [2025] NSWCATCD 7 Hearing dates: 27 September 2024 (last submissions on 2 December 2024) Date of orders: 11 February 2025 Decision date: 11 February 2025 Jurisdiction: Consumer and Commercial Division Before: G Blake AM SC, Principal Member Decision: (1) The respondent is to carry out the rectification works in accordance with the Schedule on condition that the applicants provide access to the dwelling as provided in the Schedule.
(2) If the respondent fails to carry out the rectification works in accordance with the Schedule, leave is granted to the applicants to renew the proceedings.
(3) The respondent is to pay the costs of the applicants of the proceedings on the ordinary basis.
(4) If any party wishes to make an application to vary order (3) above, the applicant (the costs applicant) is to file and serve a costs application, including submissions limited to three pages and any evidence in support, by 25 February 2025.
(5) The respondent to the costs application is to file and serve any submissions limited to three pages and any evidence in response by 11 March 2025.
(6) The costs applicant is to file any submissions limited to two pages in reply by 18 March 2025.
(7) The parties are to indicate in their submissions whether they consent to an order dispensing with an oral hearing of the costs application, and if they do not consent, submissions of no more than one page as to why an oral hearing should be conducted rather than the application being determined on the papers. If a hearing is not dispensed with, the parties will be advised of a date for the hearing of the application.
Catchwords: BUILDING AND CONSTRUCTION — Home Building Act 1989 (NSW) — Building dispute – where the builder breached express and implied warranties – work order made against the builder
Legislation Cited: Civil and Administrative Tribunal Act 2013 (NSW), ss 28, 29, 60, Sch 4, cll 3, 8
Civil and Administrative Tribunal Rules 2014 (NSW), r 38
Evidence Act 1995 (NSW), s 79
Fair Trading Act 1987 (NSW), ss 79R, 79T, 79U, 79V
Home Building Act 1989 (NSW), ss 3B, 18B, 18E, 48A, 48K, 48O, Sch 1, cll 1, 2, 3
Trade Practices Act 1974 (Cth) s 74 (repealed)
Cases Cited: Blacktown City Council v Hocking [2008] NSWCA 144; (2008) Aust Torts Reports 81-956
Catapult Constructions Pty Ltd v Denison [2018] NSWCATAP 158
Deacon v National Strategic Constructions Pty Ltd; National Strategic Constructions Pty Ltd v Deacon [2017] NSWCATAP 185
Forster v Hunter New England Area Health Service (2010) 77 NSWLR 495; [2010] NSWCA 106
Goode v Angland (2017) 96 NSWLR 503; [2017] NSWCA 311
Hancock v East Coast Timber Products Pty Ltd (2011) 80 NSWLR 43; [2011] NSWCA 11
Indico Holdings Pty Ltd v TNT Australia Ply Ltd (1990) 41 NSWLR 281
Makita (Australia) Pty Ltd v Sprowles (2001) 52 NSWLR 705; [2001]…
Keep reading for free
Create a free CaseChat account to read Kelly v Southern Pacific Builders Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2025] NSWCATCD 7
- Decision Date
CaseChat Overview and Summary
The tribunal found that Southern Pacific Builders had indeed breached the terms of the contract by failing to carry out the rectification works as agreed. The tribunal considered the evidence presented and concluded that the respondent's work did not meet the required standards. Given the clear breach of contract, the tribunal ordered that the respondent must complete the rectification works as outlined in the Schedule attached to the order. Additionally, the tribunal granted the applicants leave to renew the proceedings if the respondent failed to comply with the order. The tribunal also directed that the respondent pay the applicants' costs of the proceedings on the ordinary basis. The tribunal further detailed the procedure for any party seeking to vary the costs order, including submission deadlines and the potential for an oral hearing.
The orders made by the tribunal were clear and comprehensive, addressing both the immediate rectification works and the financial implications of the respondent's breaches. The tribunal provided a structured process for handling any future costs applications, ensuring that the applicants could seek further relief if necessary. This case underscores the importance of adhering to contractual obligations and the remedies available under the Home Building Act when such obligations are not met.
Orders
Orders of the court
(1) The respondent is to carry out the rectification works in accordance with the Schedule on condition that the applicants provide access to the dwelling as provided in the Schedule.
(2) If the respondent fails to carry out the rectification works in accordance with the Schedule, leave is granted to the applicants to renew the proceedings.
(3) The respondent is to pay the costs of the applicants of the proceedings on the ordinary basis.
(4) If any party wishes to make an application to vary order (3) above, the applicant (the costs applicant) is to file and serve a costs application, including submissions limited to three pages and any evidence in support, by 25 February 2025.
(5) The respondent to the costs application is to file and serve any submissions limited to three pages and any evidence in response by 11 March 2025.
(6) The costs applicant is to file any submissions limited to two pages in reply by 18 March 2025.
(7) The parties are to indicate in their submissions whether they consent to an order dispensing with an oral hearing of the costs application, and if they do not consent, submissions of no more than one page as to why an oral hearing should be conducted rather than the application being determined on the papers. If a hearing is not dispensed with, the parties will be advised of a date for the hearing of the application.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi