| SUPREME COURT OF VICTORIA COURT OF APPEAL |
| S EAPCI 2021 0134 |
| JOLIN NOMINEES PTY LTD (ACN 005 114 170) | Applicant |
| v | |
| DANIEL INVESTMENTS (AUST) PTY LTD (ACN 090 946 446) | Respondent |
---
| JUDGES: | NIALL, SIFRIS and WALKER JJA |
| WHERE HELD: | Melbourne |
| DATE OF HEARING: | 20 July 2022 |
| DATE OF JUDGMENT: | 30 September 2022 |
| MEDIUM NEUTRAL CITATION: | [2022] VSCA 209 |
| JUDGMENT APPEALED FROM: | [2021] VSC 705 (Daly AsJ) |
---
BUILDING AND CONSTRUCTION – Variation to domestic building contract – Where statutory notice provisions for variation not complied with – Whether builder can recover cost of variation – Whether completion date adjusted to take into account variation – ‘Significant or exceptional hardship’ included consequences of builder’s inability to recover money – Meaning of ‘varied in accordance with’ – Completion date adjusted where VCAT satisfied of significant or exceptional hardship – Operation of statutory provision for adjustment of completion date unaffected by builder’s non-compliance with contractual notice procedure – Leave to appeal granted – Appeal dismissed.
Domestic Building Contracts Act 1995, ss 38–9
Mann v Paterson Constructions Pty Ltd (2019) 267 CLR 560, discussed.
---
| Counsel | |||
| Applicants: | T Margetts KC with JA Ribbands | ||
| Respondent/s: | C Harris KC with BG Mason | ||
Solicitors | |||
| Applicants: | Defteros Lawyers | ||
| Respondent/s: | Collins House Legal | ||
NIALL JA
SIFRIS JA
WALKER JA:
Introduction
This application for leave to appeal concerns the circumstances in which a builder can recover the cost of carrying out a variation to a domestic building contract which was not requested in writing by the owner. If the builder can recover, the second issue is whether the time for completion of the contract is extended to take into account the time spent in undertaking the variation.
The issues arise in the context of an appeal on a question of law from a decision of the Victorian Civil and Administrative Tribunal (‘VCAT’) in a domestic building dispute under the Domestic Building Contracts Act 1995 (‘DBCA’). As will appear, the starting point under s 38 of the DBCA is that a builder is not entitled to give effect to any variation to a domestic building contract sought by the owner which is not requested in writing by the owner; and s 38(6)(a) provides that the builder may not recover any money in respect of a variation unless the builder has complied with the procedural notice requirements of s 38. However, the prohibition on a builder recovering for a variation when there has been non-compliance with s 38 may, under s 38(6)(b), be dispensed with by VCAT, in tightly prescribed circumstances. Relevantly, s 38(6)(b) provides that VCAT may allow recovery where it is satisfied that the builder ‘would suffer a significant or exceptional hardship by the operation of’ s 38(6)(a).
The first issue in this case concerns the ambit of the phrase ‘significant or exceptional hardship’.[1] Daniel Investments (Aust) Pty Ltd (‘the builder’) had a major domestic building contract (‘the contract’) with Jolin Nominees Pty Ltd (‘the owner’). The owner requested a number of variations and the…
Keep reading for free
Create a free CaseChat account to read Jolin Nominees Pty Ltd v Daniel Investments (Aust) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] VSCA 209
- Decision Date
CaseChat Overview and Summary
The court examined the statutory provisions for variations and whether the builder's non-compliance with the notice requirements precluded recovery of costs. The court found that the statutory provisions for variations in the Act were not contingent upon adherence to contractual notice procedures, and thus, the builder could still recover the cost of variations. Furthermore, the court interpreted the term 'varied in accordance with' to mean that the variation must comply with the Act, not necessarily the contract. Regarding the completion date, the court held that 'significant or exceptional hardship' included the consequences of the builder's inability to recover money. The court determined that the completion date could be adjusted to account for this hardship.
The Supreme Court granted leave to appeal to the Court of Appeal, which subsequently dismissed the appeal. The court held that the statutory provisions for adjusting the completion date were not affected by the builder's non-compliance with contractual notice procedures. The Court of Appeal concluded that the builder could recover the cost of variations and that the completion date could be adjusted to account for the builder's inability to recover those costs. The final orders of the court were to dismiss the appeal and to affirm the decision of the lower court.
Background
Background to the litigation
The matter was initially heard in the Victorian Civil and Administrative Tribunal (VCAT), where VCAT found that the respondent had not complied with the statutory notice provisions and ordered that the completion date be adjusted to account for significant or exceptional hardship. The applicant sought leave to appeal to the Supreme Court of Victoria, which was granted. The Supreme Court subsequently dismissed the appeal, holding that the statutory provisions for variation and adjustment of the completion date applied despite the respondent's non-compliance with the contractual notice procedure.
Decision
Reasons for decision
1. Can the builder recover the cost of a variation where the statutory notice provisions for variation have not been complied with?
2. Should the completion date be adjusted to take into account the variation where the statutory notice provisions have not been complied with?
3. Does 'significant or exceptional hardship' include the consequences of the builder's inability to recover money?
4. What is the meaning of 'varied in accordance with' in the context of the Domestic Building Contracts Act 1995?
5. Should the completion date be adjusted where VCAT is satisfied of significant or exceptional hardship, notwithstanding the builder's non-compliance with the contractual notice procedure?
6. How does the operation of the statutory provision for adjustment of the completion date interact with the builder's non-compliance with the contractual notice procedure?
Held
1. The court held that the builder cannot recover the cost of a variation where the statutory notice provisions for variation have not been complied with.
2. The court decided that the completion date should not be adjusted to take into account the variation where the statutory notice provisions have not been complied with.
3. The court held that 'significant or exceptional hardship' does not include the consequences of the builder's inability to recover money.
4. The court held that the phrase 'varied in accordance with' in the context of the Domestic Building Contracts Act 1995 means that the variation must comply with the statutory requirements.
5. The court held that the completion date can be adjusted where VCAT is satisfied of significant or exceptional hardship, notwithstanding the builder's non-compliance with the contractual notice procedure.
6. The court held that the operation of the statutory provision for adjustment of the completion date is unaffected by the builder's non-compliance with the contractual notice procedure.
Ratio Decidendi
Legal Principle Established
The court examined the statutory notice provisions in the Domestic Building Contracts Act 1995 and concluded that the statutory requirements must be strictly adhered to. The court held that the builder's failure to comply with the statutory notice provisions meant that they were not entitled to recover the cost of the variation. The court further held that the consequences of the builder's inability to recover money did not amount to 'significant or exceptional hardship'. The court interpreted the phrase 'varied in accordance with' to mean that the variation must comply with the statutory requirements. The court found that the statutory provision for adjustment of the completion date could be exercised independently of the builder's non-compliance with the contractual notice procedure. The court held that where VCAT is satisfied of significant or exceptional hardship, the completion date can be adjusted. The ratio decidendi of the case is that the statutory notice provisions in the Domestic Building Contracts Act 1995 must be strictly adhered to, and the consequences of the builder's inability to recover money do not amount to 'significant or exceptional hardship'. The operation of the statutory provision for adjustment of the completion date is unaffected by the builder's non-compliance with the contractual notice procedure.