| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMON LAW DIVISION
JUDICIAL REVIEW AND APPEALS LIST
S ECI 2020 02305
| JOLIN NOMINEES PTY LTD (ACN 005 114 170) | Applicant |
| v | |
| DANIEL INVESTMENTS (AUST) PTY LTD (ACN 090 946 446) | Respondent |
---
JUDGE: | Daly As J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 27 May 2021 |
DATE OF JUDGMENT: | 27 October 2021 |
CASE MAY BE CITED AS: | Jolin Nominees Pty Ltd v Daniel Investments (Aust) Pty Ltd |
MEDIUM NEUTRAL CITATION: | [2021] VSC 705 |
---
JUDICIAL REVIEW AND APPEALS – Application for leave to appeal from VCAT under s 148 of the Victorian Civil and Administrative Tribunal Act 1998 (Vic) – Principles of statutory construction – Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355, referred to – Whether Senior Member erred in applying the test pursuant to s 38(6)(b) of the Domestic Building Contracts Act 1995 (Vic) – Mann v Paterson [2019] HCA 32, referred to – Pratley Constructions v Racine [2004] VCAT 2035, referred to – Whether Senior Member took into account irrelevant considerations or failed to take into account relevant considerations – Minister for Aboriginal Affairs v Peko-Wallsend Ltd (1986) 162 CLR 24, referred to – Construction of contract – Whether builder entitled to extension of time – Whether builder alternatively entitled to extension of time under s 39 of the Domestic Building Contracts Act 1995 (Vic) – Whether Senior Member provided adequate reasons – Leave to appeal granted in part – Appeal dismissed.
---
APPEARANCES: | Counsel | Solicitors |
| For the Applicant | Mr T Margetts QC with Mr J A Ribbands | Defteros Lawyers |
| For the Respondent | Ms C M Harris QC with Mr B G Mason | Collins House Legal |
HER HONOUR:
Introduction and background
This proceeding is an application for leave to appeal against a decision of a Senior Member of the Victorian Civil Administrative Tribunal (‘VCAT’) to award the respondent damages in the sum of $328,767.23, being the final payment and the cost of variations pursuant to a building contract for the construction of six townhouses in Coburg. The appeal raises important questions regarding the consequences of a builder’s failure to comply with the notification requirements of the standard form major domestic building contract (‘HIA contract’) and the Domestic Building Contracts Act 1995 (Vic) (‘DBCA’) concerning variations, along with the proper construction and application of the provisions of the HIA contract and the DBCA concerning extension of time claims by builders.
The applicant, Jolin Nominees Pty Ltd (‘owner’) is a property developer. Mr Muratti, its director, is himself an experienced builder. The respondent, Daniel Investments (Aust) Pty Ltd (‘builder’) is a builder. Its director, Mr Daniel, is a qualified civil engineer and registered building practitioner.
The owner acquired the site in 2014, at which time there was a single storey house on the site. In or about April 2014, the owner invited the builder to tender for the demolition of the house and the construction of the townhouses (‘works’). The owner…
Keep reading for free
Create a free CaseChat account to read Jolin Nominees Pty Ltd v Daniel Investments (Aust) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] VSC 705
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included whether VCAT had erred in its interpretation of sections 38(6)(b) and 39 of the Act, and if so, whether such error warranted the grant of leave to appeal. Additionally, the court had to determine whether VCAT had taken into account relevant considerations and whether the reasons provided were adequate. The applicant contended that VCAT had misapplied the statutory test, particularly in the context of Pratley Constructions v Racine and Mann v Paterson. The respondent argued that the tribunal’s interpretation and application of the statute were correct and that adequate reasons were provided.
The court examined the principles of statutory construction, referencing Project Blue Sky Inc v Australian Broadcasting Authority. It found that VCAT had indeed erred in its application of section 38(6)(b), as it had not appropriately considered the statutory criteria. However, the court determined that the error did not necessitate the grant of leave to appeal because the outcome of the dispute would likely remain unchanged. The court also concluded that VCAT had provided sufficient reasons, albeit with some deficiencies, which did not justify a departure from the general rule against overturning VCAT decisions without substantial error.
The court granted leave to appeal in part, focusing on the interpretation and application of section 38(6)(b). However, it dismissed the appeal, holding that the error did not affect the overall outcome. The court also noted that while VCAT’s reasons could have been more detailed, they were adequate for the purposes of judicial review. Consequently, the original decision of VCAT was upheld.