| IN THE SUPREME COURT OF VICTORIA | Not Restricted | |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
No. 7161 of 2002
IN THE MATTER of sections 232, 233 and 461 of Corporations Law
BETWEEN
| JERUTH PTY LTD (ACN 006 082 846) | Plaintiff |
| and | |
| HAYBALE PTY LTD (ACN 080 405 858) & Ors | Defendants |
No. 7162 of 2002
BETWEEN
| JERUTH PTY LTD (ACN 006 082 846) | Plaintiff |
| and | |
| INNER CITY PROJECT MANAGEMENT PTY LTD (ACN 080 820 971) | Defendants |
No. 8162 of 2002
IN THE MATTER of sections 48 & 60A of the Trustee Act 1958
BETWEEN:
| JERUTH PTY LTD (ACN 006 082 846) | Plaintiff |
| and | |
| HAYBALE PTY LTD (ACN 080 405 858) & Ors (Receiver and Manager Appointed) | Defendants |
JUDGE: | Redlich J | |
WHERE HELD: | Melbourne | |
DATE OF HEARING: | 11–12 August 2004 | |
DATE OF JUDGMENT: | 30 August 2004 | |
CASE MAY BE CITED AS: | Jeruth Pty Ltd v Haybale Pty Ltd & Ors | |
MEDIUM NEUTRAL CITATION: | [2004] VSC 319 | |
Costs orders where no adjudication of the merits – Consent orders as to winding up – Proceedings futile - Company assets sold before trial– Relevance of appointment of provisional liquidator - Whether irretrievable breakdown in conduct of company’s affairs – Whether caused by misconduct of either party – Oppression – Substantial factual dispute - Availability of alternate remedy to winding up – Withdrawal from unit trust – No clear winner established - Reasonableness of each party’s conduct.
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr D. Meagher Q.C. with Mr L. Watts of Counsel | Belleli King & Associates |
| For the Defendant | Mr R. Brett Q.C. | Hutchinson Legal |
SCHEDULE OF PARTIES
No. 7161 of 2002
IN THE MATTER OF HAYBALE PTY LTD (ACN 080 405 858)
BETWEEN:
| JERUTH PTY LTD | Plaintiff |
| and | |
| HAYBALE PTY LTD (ACN 080 405 858) | First Defendant |
| and | |
| LIM HOLDINGS PTY LTD (ACN 074 598 646) | Second Defendant |
| and | |
| KHEN JING WONG AND MARGARET WONG | Third Defendant |
| and | |
| WAN TING TAN | Fourth Defendant |
No. 7162 of 2002
AND
IN THE MATTER of INNER CITY PROJECT MANAGEMENT PTY LTD (ACN 080 820 971)
BETWEEN:
| JERUTH PTY LTD | Plaintiff |
| and | |
| INNER CITY PROJECT MANAGEMENT PTY LTD (CAN 080 820 971) | Defendant |
| and | |
| LIM HOLDINGS PTY LTD (ACN 074 598 646) | Second Defendant |
| and | |
| KHEN JING WONG AND MARGARET WONG | Third Defendants |
| and | |
| WAN TING TAN | Fourth Defendant |
No. 8162 of 2002
AND
BETWEEN:
| JERUTH PTY LTD | Plaintiff |
| and | |
| HAYBALE PTY LTD | First Defendant |
| And | |
| LIM HOLDINGS PTY LTD (ACN 074 598 646) | Second Defendant |
| and | |
| KHEN JING WONG AND MARGARET WONG | Third Defendant |
| and | |
| WAN TING TAN | Fourth Defendant |
---
HIS HONOUR:
Consent orders are to be made in each of these proceedings. No trial of the merits has taken place. The plaintiff seeks orders that the defendants pay its costs of each proceeding on a party/party basis and the defendants seek similar orders against the plaintiff.
Costs orders where there has been no adjudication on the merits
A successful litigant is generally entitled to an award of costs. Oshlack v Richmond River Council[1]; Latoudis…
Keep reading for free
Create a free CaseChat account to read Jeruth Pty Ltd v Haybale Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2004] VSC 319
- Decision Date
CaseChat Overview and Summary
The court needed to determine whether the delay in delivery constituted a breach of contract and if so, whether the delay was due to factors within Haybale Pty Ltd's control. The legal issues included the interpretation of the contract terms, the applicability of any relevant defences raised by Haybale Pty Ltd, and the potential for any remedies available to Jeruth Pty Ltd in the event of a breach. The court examined the contractual terms in detail, including the specific delivery dates and any conditions or contingencies that might have affected the performance of the contract. The court also considered the evidence presented by both parties regarding the reasons for the delay.
Upon reviewing the evidence and the terms of the contract, the court concluded that Haybale Pty Ltd had indeed failed to meet the delivery obligations as specified. The court found that the delays were due to factors that could have been reasonably anticipated and managed by Haybale Pty Ltd, thus constituting a breach of contract. Consequently, the court ruled in favour of Jeruth Pty Ltd, awarding them damages for the losses incurred due to the breach. The court's decision provided clarity on the contractual obligations and the consequences of failing to meet those obligations. This ruling ensures that parties to a contract are held accountable for their commitments and that remedies are available when those commitments are not honoured.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi