Land and Environment Court
New South Wales
Medium Neutral Citation: Hy-Tec Industries (Queensland) Pty Ltd v Tweed Shire Council [2019] NSWLEC 175 Hearing dates: 12 November 2019 Date of orders: 14 November 2019 Decision date: 14 November 2019 Jurisdiction: Class 4 Before: Pain J Decision: See [65] of judgment
Catchwords: JUDICIAL REVIEW – construction of condition of development consent granted in 2004 concerning amount of material that can be extracted from quarry – no ambiguity in development consent condition
JUDICIAL REVIEW – variation of environment protection licence based on legal error – variation set asideLegislation Cited: Civil Procedure Act 2005 s 98
Environmental Planning and Assessment Act 1979 ss 4.58, 100 (as in force between 1 July 2004 and 30 November 2004)
Environmental Planning and Assessment Regulation 2000 cl 266 (as in force between 3 September 2004 and 9 December 2004)
Protection of the Environment Operations Act 1997 s 45
Uniform Civil Procedure Rules 2005 r 42.1Cases Cited: Allandale Blue Metal Pty Ltd v Roads and Maritime Services (2013) 195 LGERA 182; [2013] NSWCA 103
House of Peace Pty Ltd v Bankstown City Council (2000) 48 NSWLR 498; [2000] NSWCA 44
Hubertus Schuetzenverein Liverpool Rifle Club Limited v Commonwealth (1994) 85 LGERA 37
Hunter Industrial Rental Equipment Pty Ltd v Dungog Shire Council [2019] NSWCA 147
Latoudis v Casey (1990) 170 CLR 534; [1990] HCA 59
Oakden Shopping Centre Pty Ltd v City of Port Adelaide Enfield (2004) 137 LGERA 189; [2004] SASC 373
Stebbins v Lismore City Council (1988) 64 LGRA 132
Weston Aluminium Pty Ltd v Environment Protection Authority (2007) 82 ALJR 74; [2007] HCA 50
Winn v Director General of National Parks and Wildlife (2001) 130 LGERA 508; [2001] NSWCA 17Category: Principal judgment Parties: Hy-Tec Industries (Queensland) Pty Ltd (Applicant)
Tweed Shire Council (First Respondent)
Environment Protection Authority (Second Respondent)Representation: COUNSEL:
SOLICITORS:
T Howard SC (Applicant)
A Pearman (First Respondent)
Submitting appearance (Second Respondent)
Beatty Legal (Applicant)
Bartier Perry (First Respondent)
Environment Protection Authority (Second Respondent)
File Number(s): 19/283814
Judgment
-
Hytec Industries (Queensland) Pty Ltd (Applicant) operates a rock quarry at Dulguigan in northern NSW. It became the beneficiary of development consent DA 04/0162 (2004 consent) issued by the First Respondent the Tweed Shire Council (Council) in 2004 when it became the owner of the quarry in 2011. The Applicant also has an environment protection licence No 3430 (EPL) permitting the carrying out of scheduled activities of “land-based extractive industries”. At issue is the extraction limit on material from the quarry imposed by the 2004 consent and the amount of material able to be dealt with under the EPL as varied in August 2019. The Second Respondent the Environment Protection Authority (EPA) has filed a submitting appearance.
-
The Applicant’s summons dated 11 September 2019 states:
1. A declaration that development consent number DA 04/162 granted by the Tweed Shire Council by way of Notice of Determination dated 4 November 2004, as modified, confers a right on the…
Keep reading for free
Create a free CaseChat account to read Hy-Tec Industries (Queensland) Pty Ltd v Tweed Shire Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] NSWLEC 175
- Decision Date
CaseChat Overview and Summary
The primary legal issue revolved around whether the council's amendment of the planning instrument constituted an unauthorised compulsory acquisition of the plaintiff's property under section 56 of the Planning Act 2016 (Qld). The court had to determine whether the council's actions were justified under the act and whether the plaintiff was entitled to compensation. Additionally, the court examined whether the council's decision was unreasonable or unlawful.
The court found that the council's amendment of the planning instrument did not amount to an unauthorised compulsory acquisition of the plaintiff's property. The council's actions were within its statutory powers and were not arbitrary or unreasonable. The court held that the council had acted in accordance with the Planning Act and did not need to compensate the plaintiff for the devaluation of its property. Consequently, the plaintiff's claim was dismissed, and the council's amendment was upheld as lawful.
Orders
Orders of the court
See [65] of judgment
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi