FEDERAL COURT OF AUSTRALIA
Hadgkiss v Aldin (No 2) [2007] FCA 2069
INDUSTRIAL LAW – breaches of s 38 Building and Construction Industry Improvement Act 2005 (Cth) by unlawful industrial action – breaches of order made under s 127 (pre-reform) Workplace Relations Act 1996 (Cth) by unlawful industrial action – penalties suspended in part – whether declarations should be made by reference to deemed admissions.
Building and Construction Industry Improvement Act 2005 (Cth), s 38
Workplace Relations Act 1996 (Cth), s 127Australian Competition and Consumer Commission v Dataline.Net.Au Pty Ltd [2007] FCAFC 146 discussed
Australian Competition and Consumer Commission v Dataline.Net.Au Pty Ltd (2006) 236 ALR 665 applied
Bank of Kuwait and the Middle East v The Ship MV “Mawashi Al Gasseem” (No 2) [2007] FCA 815 applied
British American Tobacco Australasia Limited v The Person Identified by the Australian Customs Service as “Gory Sabar” [2007] FCA 1417 referred to
Hadgkiss v Aldin [2007] FCA 2068 referred to
Macquarie Bank Ltd v Seagle (2005) 146 FCR 400 cited
Wu v Avin Operations Pty Ltd [2006] FCA 36 citedNIGEL HADGKISS v GORDON WILLIAM ALDIN
WAD 185 OF 2006GILMOUR J
20 DECEMBER 2007
PERTH
IN THE FEDERAL COURT OF AUSTRALIA
WESTERN AUSTRALIA DISTRICT REGISTRY
WAD 185 OF 2006
BETWEEN:
NIGEL HADGKISS
ApplicantAND:
GORDON WILLIAM ALDIN
Respondent
JUDGE:
GILMOUR J
DATE OF ORDER:
20 DECEMBER 2007
WHERE MADE:
PERTH
UPON THE ADMISSIONS WHICH THE 2nd, 3rd, 83rd AND 92nd RESPONDENTS ARE DEEMED TO HAVE MADE CONSEQUENT UPON THEIR NON-COMPLIANCE WITH ORDERS OF THE COURT IT IS DECLARED THAT:
1.Between 24 February 2006 and 3 March 2006 (the Period), the 2nd, 3rd, 83rd and 92nd respondents contravened s 38 of the Building and Construction Industry Improvement Act 2005 (Cth) by engaging in unlawful industrial action (being failure to attend for building work) on 24, 25, 27, 28 February 2006, 1, 2 and 3 March 2006, in relation to the construction of the New Metro Rail City Project – Package F section of the Perth to Mandurah railway project.
2.During the Period, the 2nd and 3rd respondents breached clause 4 of the order made on 6 December 2005 under s 127 of the Workplace Relations Act 1996 (Cth) by Commissioner Gregor of the Australian Industrial Relations Commission (the s 127 order) which required them to immediately stop, and not engage in or threaten to engage in industrial action, when on the 24, 25, 27, 28 February 2006, 1, 2 and 3 March 2006 they engaged in industrial action during the construction of the New Metro Rail City Project – Package F section of the Perth to Mandurah railway project.
AND THE COURT FURTHER ORDERS THAT:
3.Subject to Order 4, a penalty in the amount of $9000 be imposed on each of the 2nd, 3rd, 85th and 95th respondents for contravening s 38 of the Building and Construction Industry Improvement Act 2005
Keep reading for free
Create a free CaseChat account to read Hadgkiss v Aldin (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2007] FCA 2069
- Decision Date
CaseChat Overview and Summary
The central legal issues revolved around whether the respondents were indeed in default for failing to file a defence and whether the court had the discretion to enter judgment against them without providing further notice of the hearing, particularly since two of the respondents had not received personal notification of the hearing. The court also had to consider the principles surrounding the waiver of rights by defaulters and the implications of such waivers in proceedings under Order 35A of the Federal Court Rules.
In delivering the judgment, the court acknowledged the general reluctance to permit a party to obtain orders without proper notice. However, it found that the respondents, having been served with the originating process and subsequently defaulting in their obligations, had effectively waived their rights to be notified of the hearing. The court relied on the principle that defaulters who do not take required steps after service of the originating process consent to judgment based on the facts alleged in the statement of claim. This principle was reinforced by the decision in British American Tobacco Australasia Limited v The Person Identified by the Australian Customs Service as “Gory Sabar” where similar circumstances were encountered.
Based on the findings and legal considerations, the court granted the orders sought by the applicant, including declarations, pecuniary penalties, and costs against the respondents. The court concluded that it was just to enter judgment in default against the respondents who had failed to file a defence or appear before the court, despite not having personally notified them of the hearing.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: GILMOUR J
Full text does not contain this section.