JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CIVIL
CITATION: GOLD CITY DEVELOPMENTS PTY LTD -v- PORTPRIDE PTY LTD [2010] WASC 148
CORAM: MAZZA J
HEARD: 29 MARCH 2010
DELIVERED : 18 JUNE 2010
FILE NO/S: GDA 10 of 2009
MATTER :Commercial Arbitration Act 1985 (WA)
and
An appeal against the interim award of Adrian Goold given 7 October 2009 in an arbitration
BETWEEN: GOLD CITY DEVELOPMENTS PTY LTD
Appellant
AND
PORTPRIDE PTY LTD
First RespondentADRIAN GOOLD
Second Respondent
Catchwords:
Arbitration - Application for leave to appeal - Principles applicable to such applications - Whether arbitrator made manifest error in the construction of contracts - Turns on own facts
Legislation:
Commercial Arbitration Act 1985 (WA), s 38
Result:
Leave to appeal refused on all grounds
Category: B
Representation:
Counsel:
Appellant: Mr S D Pentony
First Respondent : Mr M F Holler
Second Respondent : No appearance
Solicitors:
Appellant: Lavan Legal
First Respondent : Morgan Alteruthemeyer
Second Respondent : No appearance
Case(s) referred to in judgment(s):
Alghussein Establishment v Eton College [1991] 1 All ER 267
Alvaro v Temple [2009] WASC 205
Australian Broadcasting Commission v Australasian Performing Right Association Ltd [1973] HCA 36; (1973) 129 CLR 99
EDWF Holdings 1 Pty Ltd v EDWF Holdings 2 Pty Ltd [2010] WASCA 78
Michael Kellaway International Pty Ltd v Shark Bay Airport Pty Ltd (Unreported, WASCA, Library No 970604, 13 November 1997)
New Generation Enterprises Pty Ltd v Western Australian Planning Commission [2007] WASCA 89
Nouvelle Homes Pty Ltd v G & M Smargiassi [2008] WASC 127
Onesteel Manufacturing Pty Ltd v United KG Pty Ltd [2006] SASC 119; (2006) 94 SASR 376
Opat Decorating Service (Aust) Pty Ltd v Hansen Yuncken (SA) Pty Ltd (1994) 11 BCL 360
Pioneer Shipping Ltd v BTP Tioxide Ltd [1980] 1 QB 547
Promenade Investments Pty Ltd v New South Wales (1992) 26 NSWLR 203
Quadwest Developments Pty Ltd v Thi [2009] WASC 260
SMK Cabinets v Hili Modern Electrics Pty Ltd [1984] VR 391
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd [2004] HCA 52; (2004) 219 CLR 165
Turner Corporation Ltd (in liq) v Co-ordinated Industries Pty Ltd (1994) 11 BCL 202
Turner Corporation Pty Ltd (Receiver & Manager Appointed) v Austotel Pty Ltd (1994) 13 BCL 378
Ukrainian Association of Western Australia in Perth (Inc) v Squire Constructions Pty Ltd [2004] WASC 4
West Boat Builders Pty Ltd v Cull Holdings Pty Ltd [1999] WASCA 72; (2000) 16 BCL 21
Zurich Bay Holdings Pty Ltd v Iluka Midwest Ltd [2009] WASC 237
MAZZA J: The appellant (the proprietor) seeks leave to appeal and to appeal against an interim award made by the second respondent, a lay arbitrator (the arbitrator), under s 38(4) of the Commercial Arbitration Act 1985 (WA) (the Act).
The application for leave to appeal and the appeal were heard together. The arbitrator took no part in the proceedings. He has notified the court that he will abide by its decision.
Background
The…
Keep reading for free
Create a free CaseChat account to read Gold City Developments Pty Ltd v Portpride Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2010] WASC 148
- Decision Date
CaseChat Overview and Summary
The primary legal issue was whether clause 11 of the contract overcame the prevention principle, which typically prevents a party from benefiting from their own wrongdoing. The proprietor argued that clause 11, in its terms, excluded the operation of the prevention principle and that the arbitrator had erred in not interpreting it accordingly. The builder, on the other hand, contended that the arbitrator's interpretation of clause 11 was correct and not manifestly erroneous. They argued that clause 11(b) explicitly stated that the builder was not responsible for any delays caused by matters beyond their control, and that the failure to give notice could not override this defence.
The court held that the construction of clause 11 was legitimately open to the arbitrator and was, in the court's opinion, correct. The court found that the proprietor had not demonstrated that the arbitrator's conclusion on the construction of the contract was manifestly wrong. The court emphasised that while differing opinions on the proper construction of a clause might exist, it was not enough for the court to simply prefer a different interpretation. The court concluded that the arbitrator's interpretation of clause 11(b) was a clear and overriding statement that the builder was not responsible for delays caused by matters outside their control, and this interpretation was not manifestly erroneous.
The court dismissed the proprietor's application for leave to appeal, affirming the arbitrator's decision. The builder's interpretation of clause 11, which precluded any financial responsibility for delays beyond the builder's control, was upheld. The court found that the arbitrator's decision was not manifestly erroneous and that the builder was not liable for delays caused by the proprietor's own actions.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
It was submitted that cl 11 overcame the principle of contractual construction, known as the prevention principle. This provides that a party to a contract will not be entitled to take advantage of its own wrong. The proprietor submitted that as in cases such as Turner Corporation Pty Ltd (Receiver & Manager Appointed) v Austotel Pty Ltd (1994) 13 BCL 378, Turner Corporation Ltd (in liq) v Co-ordinated Industries Pty Ltd (1994) 11 BCL 202 and Opat Decorating Service (Aust) Pty Ltd v Hansen Yuncken (SA) Pty Ltd (1994) 11 BCL 360, cl 11 in its terms excluded the operation of the prevention principle. The proprietor submitted that the arbitrator made a manifest error of law in failing to construe cl 11 in the way it now contends. The builder submitted that the arbitrator made no manifest error of law in his interpretation of cl 11. The builder submitted that the proprietor's construction of cl 11(b) and (c) did not take into account the words in cl 11(b) '[n]otwithstanding provisions to the contrary contained in this Contract the Builder shall not be responsible for any delays caused by any matter or thing over which the Builder shall have no control'. These words, it was submitted, are a clear and overriding statement in the contract to the effect that the builder was not responsible for anything over which it had no control. Accordingly, the failure to give notice could not thwart the builder's defence to the proprietor's claim for damages for delay. Counsel for the builder sought to distinguish the cases cited by the proprietor on the basis that the extension of time provisions in those cases were significantly different to those in the contract. He submitted that cl 11 did not overcome the prevention principle. The builder submitted that cl 11(c) could not be understood to require the builder to notify the proprietor of the proprietor's own delay. Further, even if it did, notice did not have to be given in writing. It cannot be overlooked that the proprietor must demonstrate that the conclusion reached by the arbitrator on the question of construction of the contract is manifestly wrong. Minds might differ on the construction of cl 11 but it is not enough that I might or would, on balance, have taken a different view on the proper construction of the clause: Zurich Bay Holdings Pty Ltd v Iluka Midwest Ltd [2009] WASC 237 [12]. In my opinion the arbitrator's construction was legitimately open to him. I would, however, go further. In my opinion it was correct. Either way, manifest error has not been demonstrated. The construction of cl 11(a) is not controversial in this case. Plainly it provides for when the works are to commence and be completed. The clause obliges the builder to 'proceed therewith with reasonable despatch and diligence and complete the Works'. With respect to cl 11(b) I accept the builder's submission that the words '[n]otwithstanding provisions to the contrary contained in this Contract the Builder shall not be responsible for any delays caused by any matter or thing over which the Builder shall have no control' are a clear and overriding statement which means that no other provisions in the contract, including cl 11(c), can have an effect which results in the builder having responsibility for any delaying event over which the builder had no control. I interpret the word 'responsible' as including any financial responsibility.