Gold City Developments Pty Ltd v Portpride Pty Ltd

Link copied
Case Copied 33 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CIVIL

CITATION:   GOLD CITY DEVELOPMENTS PTY LTD -v- PORTPRIDE PTY LTD [2010] WASC 148

CORAM:   MAZZA J

HEARD:   29 MARCH 2010

DELIVERED          :   18 JUNE 2010

FILE NO/S:   GDA 10 of 2009

MATTER                :Commercial Arbitration Act 1985 (WA)

and

An appeal against the interim award of Adrian Goold given 7 October 2009 in an arbitration

BETWEEN:   GOLD CITY DEVELOPMENTS PTY LTD

Appellant

AND

PORTPRIDE PTY LTD
First Respondent

ADRIAN GOOLD
Second Respondent

Catchwords:

Arbitration - Application for leave to appeal - Principles applicable to such applications - Whether arbitrator made manifest error in the construction of contracts - Turns on own facts

Legislation:

Commercial Arbitration Act 1985 (WA), s 38

Result:

Leave to appeal refused on all grounds

Category:    B

Representation:

Counsel:

Appellant:     Mr S D Pentony

First Respondent           :     Mr M F Holler

Second Respondent       :     No appearance

Solicitors:

Appellant:     Lavan Legal

First Respondent           :     Morgan Alteruthemeyer

Second Respondent       :     No appearance

Case(s) referred to in judgment(s):

Alghussein Establishment v Eton College [1991] 1 All ER 267

Alvaro v Temple [2009] WASC 205

Australian Broadcasting Commission v Australasian Performing Right Association Ltd [1973] HCA 36; (1973) 129 CLR 99

EDWF Holdings 1 Pty Ltd v EDWF Holdings 2 Pty Ltd [2010] WASCA 78

Michael Kellaway International Pty Ltd v Shark Bay Airport Pty Ltd (Unreported, WASCA, Library No 970604, 13 November 1997)

New Generation Enterprises Pty Ltd v Western Australian Planning Commission [2007] WASCA 89

Nouvelle Homes Pty Ltd v G & M Smargiassi [2008] WASC 127

Onesteel Manufacturing Pty Ltd v United KG Pty Ltd [2006] SASC 119; (2006) 94 SASR 376

Opat Decorating Service (Aust) Pty Ltd v Hansen Yuncken (SA) Pty Ltd (1994) 11 BCL 360

Pioneer Shipping Ltd v BTP Tioxide Ltd [1980] 1 QB 547

Promenade Investments Pty Ltd v New South Wales (1992) 26 NSWLR 203

Quadwest Developments Pty Ltd v Thi [2009] WASC 260

SMK Cabinets v Hili Modern Electrics Pty Ltd [1984] VR 391

Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd [2004] HCA 52; (2004) 219 CLR 165

Turner Corporation Ltd (in liq) v Co-ordinated Industries Pty Ltd (1994) 11 BCL 202

Turner Corporation Pty Ltd (Receiver & Manager Appointed) v Austotel Pty Ltd (1994) 13 BCL 378

Ukrainian Association of Western Australia in Perth (Inc) v Squire Constructions Pty Ltd [2004] WASC 4

West Boat Builders Pty Ltd v Cull Holdings Pty Ltd [1999] WASCA 72; (2000) 16 BCL 21

Zurich Bay Holdings Pty Ltd v Iluka Midwest Ltd [2009] WASC 237

  1. MAZZA J: The appellant (the proprietor) seeks leave to appeal and to appeal against an interim award made by the second respondent, a lay arbitrator (the arbitrator), under s 38(4) of the Commercial Arbitration Act 1985 (WA) (the Act).

  2. The application for leave to appeal and the appeal were heard together.  The arbitrator took no part in the proceedings.  He has notified the court that he will abide by its decision. 

Background

  1. The…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Gold City Developments Pty Ltd v Portpride Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2010] WASC 148
Decision Date

CaseChat Overview and Summary

Gold City Developments Pty Ltd, as the proprietor, sought leave to appeal against the decision of an arbitrator in their dispute with Portpride Pty Ltd, the builder. The dispute centred on the interpretation and application of certain clauses in the construction contract, particularly those related to the builder's responsibility for delays and the prevention principle. The Supreme Court of Western Australia was tasked with determining whether the arbitrator had made a manifest error in his construction of the contract.

The primary legal issue was whether clause 11 of the contract overcame the prevention principle, which typically prevents a party from benefiting from their own wrongdoing. The proprietor argued that clause 11, in its terms, excluded the operation of the prevention principle and that the arbitrator had erred in not interpreting it accordingly. The builder, on the other hand, contended that the arbitrator's interpretation of clause 11 was correct and not manifestly erroneous. They argued that clause 11(b) explicitly stated that the builder was not responsible for any delays caused by matters beyond their control, and that the failure to give notice could not override this defence.

The court held that the construction of clause 11 was legitimately open to the arbitrator and was, in the court's opinion, correct. The court found that the proprietor had not demonstrated that the arbitrator's conclusion on the construction of the contract was manifestly wrong. The court emphasised that while differing opinions on the proper construction of a clause might exist, it was not enough for the court to simply prefer a different interpretation. The court concluded that the arbitrator's interpretation of clause 11(b) was a clear and overriding statement that the builder was not responsible for delays caused by matters outside their control, and this interpretation was not manifestly erroneous.

The court dismissed the proprietor's application for leave to appeal, affirming the arbitrator's decision. The builder's interpretation of clause 11, which precluded any financial responsibility for delays beyond the builder's control, was upheld. The court found that the arbitrator's decision was not manifestly erroneous and that the builder was not liable for delays caused by the proprietor's own actions.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established

It was submitted that cl 11 overcame the principle of contractual construction, known as the prevention principle. This provides that a party to a contract will not be entitled to take advantage of its own wrong. The proprietor submitted that as in cases such as Turner Corporation Pty Ltd (Receiver & Manager Appointed) v Austotel Pty Ltd (1994) 13 BCL 378, Turner Corporation Ltd (in liq) v Co-ordinated Industries Pty Ltd (1994) 11 BCL 202 and Opat Decorating Service (Aust) Pty Ltd v Hansen Yuncken (SA) Pty Ltd (1994) 11 BCL 360, cl 11 in its terms excluded the operation of the prevention principle. The proprietor submitted that the arbitrator made a manifest error of law in failing to construe cl 11 in the way it now contends. The builder submitted that the arbitrator made no manifest error of law in his interpretation of cl 11. The builder submitted that the proprietor's construction of cl 11(b) and (c) did not take into account the words in cl 11(b) '[n]otwithstanding provisions to the contrary contained in this Contract the Builder shall not be responsible for any delays caused by any matter or thing over which the Builder shall have no control'. These words, it was submitted, are a clear and overriding statement in the contract to the effect that the builder was not responsible for anything over which it had no control. Accordingly, the failure to give notice could not thwart the builder's defence to the proprietor's claim for damages for delay. Counsel for the builder sought to distinguish the cases cited by the proprietor on the basis that the extension of time provisions in those cases were significantly different to those in the contract. He submitted that cl 11 did not overcome the prevention principle. The builder submitted that cl 11(c) could not be understood to require the builder to notify the proprietor of the proprietor's own delay. Further, even if it did, notice did not have to be given in writing. It cannot be overlooked that the proprietor must demonstrate that the conclusion reached by the arbitrator on the question of construction of the contract is manifestly wrong. Minds might differ on the construction of cl 11 but it is not enough that I might or would, on balance, have taken a different view on the proper construction of the clause: Zurich Bay Holdings Pty Ltd v Iluka Midwest Ltd [2009] WASC 237 [12]. In my opinion the arbitrator's construction was legitimately open to him. I would, however, go further. In my opinion it was correct. Either way, manifest error has not been demonstrated. The construction of cl 11(a) is not controversial in this case. Plainly it provides for when the works are to commence and be completed. The clause obliges the builder to 'proceed therewith with reasonable despatch and diligence and complete the Works'. With respect to cl 11(b) I accept the builder's submission that the words '[n]otwithstanding provisions to the contrary contained in this Contract the Builder shall not be responsible for any delays caused by any matter or thing over which the Builder shall have no control' are a clear and overriding statement which means that no other provisions in the contract, including cl 11(c), can have an effect which results in the builder having responsibility for any delaying event over which the builder had no control. I interpret the word 'responsible' as including any financial responsibility.