Zurich Bay Holdings Pty Ltd v Iluka Midwest Ltd

Link copied
Case Copied 33 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CHAMBERS

CITATION:   ZURICH BAY HOLDINGS PTY LTD -v- ILUKA MIDWEST LTD [2009] WASC 237

CORAM:   BEECH J

HEARD:   27 JULY 2009

DELIVERED          :   2 SEPTEMBER 2009

FILE NO/S:   ARB 7 of 2009

BETWEEN:   ZURICH BAY HOLDINGS PTY LTD (ACN 009 422 093)

Applicant

AND

ILUKA MIDWEST LIMITED (ACN 008 763 666)
Respondent

Catchwords:

Arbitration - Commercial arbitration - Contract for services at a mine site - Question of construction of contract - Whether arbitrator made manifest error in construction of contract - Turns on own facts

Legislation:

Commercial Arbitration Act 1985 (WA), s 38

Result:

Application dismissed

Category:    B

Representation:

Counsel:

Applicant:     Mr M J McCusker QC & Mr A D Bereyne

Respondent:     Mr C L Zelestis QC & Mr J A Thomson

Solicitors:

Applicant:     Jackson McDonald

Respondent:     Clayton Utz

Case(s) referred to in judgment(s):

Alvaro v Temple [2009] WASC 205

Anaconda Operations Pty Ltd v Fluor Pty Ltd [2003] VSC 275

Gianfriddo v Garra Constructions Pty Ltd [1971] VR 289

Gold Coast City Council v Canterbury Pipe Lines (Aust) Pty Ltd [1968] HCA 3; (1968) 118 CLR 58

Lamac Developments Pty Ltd v Devaugh Pty Ltd [2002] WASCA 245; (2002) 27 WAR 287

New Generation Enterprises Pty Ltd v Western Australian Planning Commission [2007] WASCA 89

Olympic Holdings Pty Ltd v Windslow Corp Pty Ltd (in liq) [2008] WASCA 80; (2008) 36 WAR 342

Promenade Investments Pty Ltd v New South Wales (1992) 26 NSWLR 203

Ukrainian Association of Western Australia in Perth (Inc) v Squire Constructions Pty Ltd [2004] WASC 4

Zhu v Treasurer of the State of New South Wales [2004] HCA 56; (2004) 218 CLR 530

BEECH J: 

Introduction

  1. The applicant (Zurich) and the respondent (Iluka) were parties to  a contract.  Zurich claimed payment of approximately $6 million under a clause of that contract which required Iluka to compensate Zurich for any shortfall in the mineral sands concentrate to be transported by Zurich.

  2. The arbitrator dismissed Zurich's claim.  Zurich seeks leave to appeal against the arbitrator's award.

  3. In the circumstances of this case, leave to appeal can be granted only if I am satisfied that the arbitrator made a manifest error of law on the face of the award.  For the reasons that follow, I am not satisfied of that.  Consequently, I would dismiss Zurich's application for leave to appeal.

Leave to appeal - legal principles

  1. Section 38(4) and s 38(5) of the Commercial Arbitration Act 1985 (WA) are in the following terms:

    (4)An appeal under subsection (2) may be brought by any of the parties to an arbitration agreement - 

    (a)with the consent of all the other parties to the arbitration agreement; or

    (b)subject to section 40, with the leave of the Supreme Court.

    (5)The Supreme Court shall not grant leave under subsection (4)(b) unless it considers that -

    (a)having regard to all the circumstances, the determination of the question of law concerned could substantially affect the rights of one or more…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Zurich Bay Holdings Pty Ltd v Iluka Midwest Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2009] WASC 237
Decision Date

CaseChat Overview and Summary

Zurich Bay Holdings Pty Ltd sought a review of an arbitral award made in its favour by Iluka Midwest Ltd in the Supreme Court of Western Australia. The dispute concerned the interpretation of a contract for earth-moving work at a mine site. The contract was amended and restated on 1 July 1998, and included provisions for the execution of works and the duration of the works. The term 'Mine life' was subject to an earlier award by the arbitrator, and the meaning of this term was again in question in this case.

The court was required to decide whether the arbitrator had made a manifest error in the construction of the contract, particularly in relation to the term 'Mine life'. The court had to consider whether the arbitrator's award and reasons incorporated the contract, and if so, what weight should be given to the contract in determining the meaning of the term. The court also had to consider whether the arbitrator had erred in failing to take into account the earlier award when interpreting the contract.

The court held that the arbitrator's award and reasons incorporated the contract, and that the contract should be given effect in interpreting the term 'Mine life'. The court held that the arbitrator had not made a manifest error in the construction of the contract, and that the term 'Mine life' should be interpreted in the context of the contract as a whole. The court held that the arbitrator had not erred in failing to take into account the earlier award, as the earlier award was not binding on the arbitrator in this case. The court dismissed the application for review.

The court ordered that the application for review be dismissed with costs. The court held that the costs were to be paid by Zurich Bay Holdings Pty Ltd to Iluka Midwest Ltd on an indemnity basis.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established

As Pullin JA explained in New Generation v WAPC, the change in the law effected by the Commercial Arbitration Act requiring an arbitrator to give reasons for an award affects the approach to determining the intention of the arbitrator. Under the previous regime there was a presumption against an intention to incorporate reasons in the award. That no longer holds. A number of factors will influence whether a document was intended by the arbitrator to have been incorporated in the award. If the arbitrator's reasons cannot be understood without reading the document the reasons will be regarded as incorporating the document: New Generation v WAPC [49]; Alvaro v Temple [2009] WASC 205 [37]. A mere recital or narrative statement referring to a document will be insufficient to incorporate the document into the award: Ukrainian Association of Western Australia in Perth (Inc) v Squire Constructions Pty Ltd [2004] WASC 4 [25]; Gianfriddo v Garra Constructions Pty Ltd [1971] VR 289, 290 – 291; Anaconda Operations Pty Ltd v Fluor Pty Ltd [2003] VSC 275 [44] ‑ [49]. It was common cause between the parties that the arbitrator's award and reasons incorporated the contract. I turn to the contract the subject of the arbitration. On 1 July 1998 Iluka (then known as RGC Mineral Sands Ltd) and Zurich entered into the contract the subject of the arbitration. The recitals to the contract referred to an agreement made in 1991 by which Zurich had agreed to carry out earth moving work at Iluka's mine at Eneabba West. The contract of 1 July 1998 was intended to amend and restate the earlier agreement with effect from 1 July 1998. Clause 3 of the 1 July 1998 contract provides:EXECUTION OF WORKSIn consideration of the payments to be made by [Iluka] as hereinafter provided [Zurich] shall execute the entire Works in accordance with the Specifications and the Drawings in good and workmanlike manner and shall furnish plant and equipment and labour as required under the Contract. 'Works' was defined to mean the whole of the work to be executed by Zurich in accordance with the contract. Clause 7 provides:DURATION OF WORKS1.The duration of the Works shall, subject to the terms hereof, be for the Mine life, and shall be renewed on the terms of the Contract after each period of one (1) calendar year.2.Upon final completion of the Works [Zurich] shall vacate the Site and remove all of its remaining plant and equipment therefrom and make good any damage caused by such removal, to the satisfaction of [Iluka].The meaning of the term 'Mine life' was the subject of an earlier award by the arbitrator. I will return to that later in these reasons. Clause 8 provided for the renewal of the contract after each one year term for a further term of one year or the remaining Mine life, whichever is the lesser, provided that:(a)the rates payable to Zurich under sch 2 and any other rates payable to Zurich are not less favourable to Iluka than those reasonably available on a general commercial and bona fide basis from other contractors; and(b)Zurich has performed the Works in a manner satisfactory to Iluka.