SUPREME COURT OF SOUTH AUSTRALIA
(Civil)
EWING INTERNATIONAL LP v AUSBULK LTD (No 2)
[2009] SASC 381
Judgment of The Honourable Justice Layton
9 December 2009
CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES
CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - OFFER AND ACCEPTANCE - MATTERS NOT GIVING RISE TO BINDING CONTRACT - VAGUENESS AND UNCERTAINTY
EQUITY - EQUITABLE REMEDIES - SPECIFIC PERFORMANCE
Claimant (Ausbulk) seeks orders requiring Respondent (Ewing) to procure performance guarantees – Ewing entered into two contracts with Ausbulk for construction work relating to grain silos – clause 5 of the contracts required Ewing to provide security for performance – Ewing provided bank guarantees as security – dispute arose regarding the performance of the contract in 2007 – each party alleged termination for breach and sought damages – dispute referred to arbitration – performance guarantees due to expire in February 2008 – Ausbulk sought to call on the guarantees – Ewing sought injunctions in Supreme Court – injunctions granted on 8 February 2008 conditional upon Ewing extending existing guarantees – precise form of orders to await hearing the parties – parties negotiated on the basis of Ewing providing guarantees that would not be limited in time – on 18 February 2008 Ewing advised Ausbulk that its bank refused to issue guarantees not limited in time – parties then negotiated on the basis of Ewing providing guarantees limited in time but with mechanism for rollover – Ausbulk alleges contract entered into by parties on 20 February 2008 – alleged contract included obligation of Ewing to provide rollover guarantees with a mechanism which enabled Ausbulk to call on guarantees in final month before expiry – consent orders entered on 26 February 2008.
Contractual issues: whether correspondence and attached draft orders evidenced a contract dated 20 February 2008 – whether contract placed obligation on Ewing to roll over guarantees until determination of arbitration – whether express or implied terms – whether legal representatives had actual or ostensible authority to enter into contract on behalf of parties – whether adequate consideration – whether intention to create legal relations – whether contract void for uncertainty – whether order for specific performance of that contractual obligation appropriate when performance of obligation is contingent on bank agreeing to provide guarantees – relevance of impecuniosity of Ewing – whether order for specific performance would be futile – whether permissible to make order requiring Ewing to do “all that is reasonably necessary” to achieve rollover obligation.
Held: contract formed at 20 February 2008 – contract not void for uncertainty – order for specific performance appropriate – order for specific performance should not be refused on the grounds of futility merely because Ewing is impecunious and the contractual obligation is contingent on approval by bank – appropriate to order that Ewing do “all that is reasonably necessary” to achieve rollover obligation.
EQUITY - GENERAL PRINCIPLES - MISTAKE - EFFECT ON CONTRACTS - MISTAKE AS TO NATURE OR CONTENTS OF DOCUMENT
Alternative claim in common mistake – whether orders provide for obligation…
Keep reading for free
Create a free CaseChat account to read Ewing International LP v Ausbulk Ltd (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] SASC 381
- Decision Date
CaseChat Overview and Summary
The court held that a contract was formed on 20 February 2008, and it was not void for uncertainty. An order for specific performance was appropriate, even if the performance of the obligation was contingent on the bank agreeing to provide guarantees. It was appropriate to order Ewing to do "all that is reasonably necessary" to achieve the rollover obligation. The court found that the parties intended to include an express requirement on Ewing to roll over the guarantees in the consent orders. Ewing was estopped from denying that the orders required the rollover of the guarantees, as the parties had proceeded on the underlying assumption that Ewing was required to roll over the guarantees. Ausbulk relied on the representation to its detriment, and Ewing was estopped from denying its obligation to roll over the guarantees.
The court also held that clause 5 of the Construction Contracts required Ewing to roll over the guarantees in the case of arbitration, and both clause 5 and the arbitration clause survived the termination of the contract. However, the obligation to provide security was now governed by the 20 February 2008 contract. Ausbulk failed to call legal representatives involved in the negotiation of the consent orders as witnesses, while Ewing failed to call legal representatives or employees involved in the negotiation of the consent orders as witnesses. The court found that the Jones v Dunkel (1959) 101 CLR 298 inference was not appropriate in the circumstances.
The court ordered that Ewing must do all that is reasonably necessary to enable it to provide security in accordance with clause 5.2 of the general conditions of contract AS 2124-1992 (General Conditions) forming part of the contract OHB/02/011-003 (the Silos Contract) and OHB/02/011-007 (the Capital Structural Package Contract). Liberty to apply was granted should Ewing be unable to procure security in accordance with the orders within 21 days.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
In draft minutes of order (3) the Recital was expressed as follows:[26]A.Upon noting that the Plaintiff and the First Defendant have agreed to extend the dispute the subject of this arbitration before Mr S Walsh QC to incorporate all of the matters the subject of this action (as defined by the affidavit of Mr Michael Heard sworn 18 December 2007) insofar as this action relates to the [Silo contract] (without making any agreement concerning arbitration of matters the subject of the action insofar as it relates to the Structural Package 2 job number “OHB/02/011‑007” and work number “EWO1419193).[26] TB 94. Paragraph 3 was expressed as follows:[27]3.That the injunctions expressed in Orders 1 and 2:3.1 be conditional upon Ewing extending the Bank Guarantees in the terms of the pro forma guarantees annexed hereto and marked A and B respectively;3.2 cease to have any effect on 15 February 2008 at 5.00pm in the event such extensions of the Bank Guarantees have not been put in place and provided to the defendants’ solicitors by that time;3.3 subject thereto, such injunctions remain in place until further order of the Court(Emphasis added.)[27] TB 94. Draft minutes of order (4)[28] expressed the Recital in the same terms as draft minutes of order (3). Paragraph 3 was expressed as follows:3.That the injunctions expressed in Orders 1 and 2:3.1 be conditional upon Ewing extending the Bank Guarantees in the terms of the Bank Guarantees annexed hereto and marked A and B respectively;3.2 subject thereto, such injunctions remain in place until further order of the Court(Emphasis added.)[28] TB 97. Both of these two versions still retained the condition in paragraph 3.1 that Ewing extend the Bank Guarantees in the terms of the annexed guarantees and that they remain in place until further order, but draft minutes of order (3) additionally required that Bank Guarantees be put in place by 15 February 2008. Mr Jenner responded to Mr Blue at 9.41pm on 13 February 2008, saying:[29]I spoke to the client tonight and it seems that in a general sense the bank will be happy if there is an order of the Court and/or (he wasn’t sure) a written acknowledgement by ABB. So needing a Court order makes it something of a “chicken and egg” situation.He will speak to the client first thing (NZ time) in the morning about the matter.One way forward may be a short Deed acknowledged in the order and directing ASB to replace two sets of guarantees with two new ones in agreed terms.We have tweaked the wording a little to give ASB some certainty.14 February 2008 correspondence [29] TB 109. On 14 February 2008, four emails were exchanged between the parties in the lead up to a hearing before me on that date. First, an email was sent from Mr Jenner to Mr Blue at 12:43pm attaching minutes of order in which paragraph 3 is expressed in the same form as draft minutes of order (4), which made no mention of the requirement for Bank Guarantees to be in place by 15 February 2008. The Recitals had been varied to read:[30]A.Upon noting the intimation from counsel for both parties that the determination of the arbitration before Mr S Walsh QC should avoid the need for a trial of the matters in the within action.B.Upon noting that the Plaintiff has procured/will procure the provision of replacement Bank Guarantees in the terms annexed hereto marked A and B.C.The payments referred to in order 4 below are payments made “on account” pending a determination as to whether the defendants are entitled to access on the bank guarantees.[30] TB 145.