Ccig (Australia) Pty Ltd v Amicus Hospitality Group Pty Ltd

Link copied
Case Copied 28 min read

SUPREME COURT OF QUEENSLAND

CITATION:

CCIG (Australia) Pty Ltd v Amicus Hospitality Group Pty Ltd [2019] QSC 232

PARTIES:

CCIG (AUSTRALIA) PTY LTD
ACN 602 873 905

(applicant)

v
AMICUS HOSPITALITY GROUP PTY LTD
ACN 622 349 017

(respondent)

FILE NO:

BS8627 of 2019

DIVISION:

Trial Division

PROCEEDING:

Originating application

DELIVERED ON:

18 September 2019

DELIVERED AT:

Brisbane

HEARING DATE:

11 September 2019

JUDGE:

Mullins J

ORDER:

1.   A declaration that upon the proper construction of the  Contract between the applicant and the respondent dated 29 November 2017 (Contract), in particular clauses 5.2, 5.3, 5.8, 42.8 and Annexure Part A of the General Conditions of the Contract, the respondent is obliged to provide to the applicant security in the form of an unconditional bank guarantee in the sum of $1,295,000.00 in the applicant’s favour from 1 August 2019 as security for the due and proper performance of the Contract by the respondent until 14 days after the issue of a Final Certificate pursuant to clause 42.8 of the Contract.

2.   The respondent specifically perform its obligations under clause 5 of the General Conditions of the Contract by providing to the applicant security in the form of an unconditional bank guarantee in the sum of $1,295,000.00 in the applicant’s favour from 1 August 2019 as security for the due and proper performance of the Contract by the respondent until 14 days after the issue of a Final Certificate pursuant to clause 42.8 of the Contract.

3. The respondent must pay the applicant’s costs of the proceeding.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – SECURITY AND RETENTION FUNDS – where the contract incorporated the Australian Standard General Conditions of Contract (AS2124-1992) as amended by Annexure Part B to the general conditions – where clauses 5.2 and 5.3 of the general conditions required the contractor to provide two unconditional bank guarantees each for 2.5% of the contract sum – where the bank guarantees that were provided each had an expiry date – where the second guarantee expired after the date of practical completion but before the date on which the principal is bound to release any security then held by the principal – whether the principal is entitled to demand the contractor provide a bank guarantee to replace the expired bank guarantee – whether the principal had impliedly approved the form of the bank guarantees with expiry dates

Ewing International LP v Ausbulk Ltd (No 2) [2009] SASC 381, cited
Larking v Great Western (Nepean) Gravel Ltd (in liq) (1940) 64 CLR 221; [1940] HCA 37, considered

Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104; [2015] HCA 37, considered
PHHH Investments No 2 Pty Ltd v United Commercial Projects Pty Ltd (No 2) [2018] VSC 92, distinguished

COUNSEL:

P J Dunning QC and L M Campbell for the applicant

M H Hindman QC and S J Gibson for…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ccig (Australia) Pty Ltd v Amicus Hospitality Group Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] QSC 232
Decision Date

CaseChat Overview and Summary

The case of Ccig (Australia) Pty Ltd v Amicus Hospitality Group Pty Ltd, decided by the Supreme Court of Queensland, concerns a dispute between the contractor, Ccig (Australia) Pty Ltd, and the principal, Amicus Hospitality Group Pty Ltd, regarding the provision of bank guarantees as part of a building contract. The contract in question incorporated the Australian Standard General Conditions of Contract (AS2124-1992) and specified that the contractor must provide two unconditional bank guarantees for 2.5% of the contract sum. The bank guarantees provided by the contractor had an expiry date, and one of these guarantees expired after practical completion of the project but before the date on which the principal was required to release any security. The principal sought a declaration and an order for specific performance, asserting that the contractor must provide a new bank guarantee to replace the expired one. The principal also claimed that the form of the bank guarantees, which included expiry dates, had been impliedly approved.

The legal issues that the court was required to address included whether the principal was entitled to demand the replacement of the expired bank guarantee, and whether the principal had impliedly approved the form of the bank guarantees that included expiry dates. The court had to interpret the relevant clauses of the contract, including clauses 5.2, 5.3, 5.8, 42.8, and Annexure Part A of the General Conditions of the Contract, to determine the rights and obligations of the parties under the contract. The court also had to consider the implications of the expiry date on the bank guarantees and whether this affected the validity of the principal's claims.

The court held that the principal was entitled to demand the replacement of the expired bank guarantee. The court found that the contract required the contractor to provide unconditional bank guarantees until 14 days after the issue of a Final Certificate, and the expiry date did not affect the validity of the principal's demand. The court also found that the principal had not impliedly approved the form of the bank guarantees that included expiry dates, as the contract did not specify that the bank guarantees could have expiry dates. The court concluded that the principal was entitled to a declaration and an order for specific performance, and that the contractor must provide a new bank guarantee in the sum of $1,295,000.00 from 1 August 2019 as security for the due and proper performance of the contract until 14 days after the issue of a Final Certificate. The court also ordered the contractor to pay the principal's costs of the proceeding.

In summary, the court held that the principal was entitled to demand the replacement of the expired bank guarantee, and that the form of the bank guarantees with expiry dates had not been impliedly approved. The court granted the principal a declaration and an order for specific performance, and ordered the contractor to pay the principal's costs of the proceeding.

Orders

Orders of the court

1. A declaration that upon the proper construction of the Contract between the applicant and the respondent dated 29 November 2017 (Contract), in particular clauses 5.2, 5.3, 5.8, 42.8 and Annexure Part A of the General Conditions of the Contract, the respondent is obliged to provide to the applicant security in the form of an unconditional bank guarantee in the sum of $1,295,000.00 in the applicant’s favour from 1 August 2019 as security for the due and proper performance of the Contract by the respondent until 14 days after the issue of a Final Certificate pursuant to clause 42.8 of the Contract.

2. The respondent specifically perform its obligations under clause 5 of the General Conditions of the Contract by providing to the applicant security in the form of an unconditional bank guarantee in the sum of $1,295,000.00 in the applicant’s favour from 1 August 2019 as security for the due and proper performance of the Contract by the respondent until 14 days after the issue of a Final Certificate pursuant to clause 42.8 of the Contract.

3. The respondent must pay the applicant’s costs of the proceeding.

Background

Background to the litigation

Ccig (Australia) Pty Ltd (the applicant) entered into a contract with Amicus Hospitality Group Pty Ltd (the respondent) for the construction of a hotel. The contract incorporated the Australian Standard General Conditions of Contract (AS2124-1992) as amended by Annexure Part B. Clauses 5.2 and 5.3 of the general conditions required the contractor to provide two unconditional bank guarantees each for 2.5% of the contract sum. The contract sum was $51,800,000. The respondent provided two bank guarantees, each for $1,295,000. Both bank guarantees had specified expiry dates. The second guarantee expired after the date of practical completion but before the date on which the principal was bound to release any security then held by the principal. The applicant claimed that the respondent was obliged to provide a bank guarantee to replace the expired bank guarantee and sought a declaration and specific performance of this obligation. The respondent argued that the principal had impliedly approved the form of the bank guarantees with expiry dates, and therefore the applicant could not demand a replacement guarantee.

The matter came before the Supreme Court of New South Wales. The applicant filed an originating application seeking a declaration and specific performance in relation to the bank guarantee. The respondent filed a defence and cross-claim. The case was heard by the Supreme Court, which delivered its judgment in favour of the applicant, granting the declaration and specific performance and ordering the respondent to pay the applicant's costs of the proceeding.

Decision

Reasons for decision

Issues
1. Whether upon the proper construction of the Contract between the applicant and the respondent dated 29 November 2017, the respondent is obliged to provide to the applicant security in the form of an unconditional bank guarantee in the sum of $1,295,000.00 in the applicant’s favour from 1 August 2019 as security for the due and proper performance of the Contract by the respondent until 14 days after the issue of a Final Certificate pursuant to clause 42.8 of the Contract.
2. Whether the principal had impliedly approved the form of the bank guarantees with expiry dates.

Held
1. The court held that upon the proper construction of the Contract between the applicant and the respondent dated 29 November 2017, the respondent is obliged to provide to the applicant security in the form of an unconditional bank guarantee in the sum of $1,295,000.00 in the applicant’s favour from 1 August 2019 as security for the due and proper performance of the Contract by the respondent until 14 days after the issue of a Final Certificate pursuant to clause 42.8 of the Contract.
2. The court held that the principal had not impliedly approved the form of the bank guarantees with expiry dates.

Ratio Decidendi

Legal Principle Established

The court began by examining the contract in question, which incorporated the Australian Standard General Conditions of Contract (AS2124-1992) as amended by Annexure Part B to the general conditions. The contract specified that the contractor was to provide two unconditional bank guarantees each for 2.5% of the contract sum. The bank guarantees provided by the respondent had expiry dates, with the second guarantee expiring after practical completion but before the principal was bound to release any security. The court was tasked with determining whether the principal was entitled to demand a new bank guarantee to replace the expired one and whether the principal had impliedly approved the form of the bank guarantees with expiry dates.

In relation to the first issue, the court considered clauses 5.2 and 5.3 of the general conditions, which required the contractor to provide two unconditional bank guarantees each for 2.5% of the contract sum. The court also examined clauses 5.8, 42.8, and Annexure Part A of the General Conditions of the Contract. The court concluded that the respondent was indeed obliged to provide the specified security in the form of an unconditional bank guarantee from 1 August 2019 until 14 days after the issue of a Final Certificate. This conclusion was based on the clear language of the contract and the requirement for the guarantees to be unconditional and to cover the period specified in the contract.

In relation to the second issue, the court considered whether the principal had impliedly approved the form of the bank guarantees with expiry dates. The court noted that the contract did not explicitly address the issue of expiry dates on the bank guarantees. However, the court held that the principal had not impliedly approved the form of the bank guarantees with expiry dates. This was because there was no evidence that the principal had accepted or acted in a manner that would imply such approval. The court emphasised that any variation to the terms of the contract must be explicitly agreed upon by both parties.

In summary, the court's reasoning was grounded in the strict construction of the contract terms, and it found that the respondent must provide the specified security in the form of an unconditional bank guarantee from 1 August 2019 until 14 days after the issue of a Final Certificate. Additionally, the court determined that the principal had not impliedly approved the form of the bank guarantees with expiry dates. The ratio decidendi of this case is that a contractor must provide security as explicitly required by the contract terms, and implied approval of variations to the contract terms cannot be established without clear evidence of acceptance or conduct by the other party.