Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes v Dunne

Link copied
Case Copied 17 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes v Dunne [2018] QCATA 193

PARTIES:

DWYER CORPORATION PTY LTD TRADING AS DWYER QUALITY HOMES
(applicant)

v

BRUCE DUNNE

(first respondent)

HEIDI DUNNE

(second respondent)

APPLICATION NOS:

APL278-17, APL027-18

ORIGINATING APPLICATION NO:

BDL105-16

MATTER TYPE:

Appeals

DELIVERED ON:

19 December 2018

HEARING DATE:

On the papers

HEARD AT:

Brisbane

DECISION OF:

Senior Member Brown

Member Olding

ORDERS:

In APL278-17

1.   No order as to costs.

In APL027-18

1.   Leave to appeal refused.

CATCHWORDS:

PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – COSTS – GENERAL MATTERS – POWER TO AWARD GENERALLY – STATUTORY BASIS GENERALLY – where appellant successful on appeal against primary decision – where success on limited grounds and to limited extent – whether appellant should be entitled to recover costs of appeal – where appropriate for there to be no order as to costs – where appeal against costs order – where leave to appeal costs order required – whether error by tribunal – whether substantial injustice to appellant as a result of error – whether discretion of tribunal to order costs miscarried

Queensland Building and Construction Commission Act 1991 (Qld), s 77(3)(h)
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 100, s 102(1), s 102(3), s 106, s 142(3)(a)(iii), s 147, s 147(3)(a), s 147(3)(b)

Cachia v Grech [2009] NSWCA 232
Foots v Southern Cross Mine Management Pty Ltd (2007) 234 CLR 52
Glenwood Properties Pty Ltd v Delmoss Pty Ltd [1986] 2 Qd R 388
Haulage Pty Ltd v Fruehauf Australia Pty Ltd [1989] 2 Qd R 577
House v The King (1936) 55 CLR 499

John Urquhart t/as Hart Renovations v Partington & Anor [206] QCA 199
Latoudis v Casey (1990) 170 CLR 72
Lyons v Dreamstarter Pty Ltd [2011] QCATA 142

Oshlack v Richmond River Council (1998) 193 CLR 72
Queensland All Codes Racing Industry Board v Abbott (No. 2) [2016] QCATA 49
QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd R 41
Richards v The Sandy Cape Deep Sea Fishing Club Inc [2003] QCA 72
Salam & Anor v Henley Properties (QLD) Pty Ltd [2016] QCATA 98

REPRESENTATION:

Applicant:

Garland Waddington, Solicitors

Respondent:

Gadens Lawyers

APPEARANCES:

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).

REASONS FOR DECISION

Background

  1. Dwyer Corporation Pty Ltd trading as Dwyer Quality Homes (‘DQH’) constructed a home for the Dunnes. The Dunnes filed an application for a domestic building dispute in the tribunal claiming that DQH had failed to properly install a termite barrier (proceeding BDL105-16). The Dunnes were successful in BDL105-16 and DQH was ordered to pay to the Dunnes $71,217.72 (the primary decision).[1] 

  2. The tribunal subsequently ordered DQH to pay the Dunnes’ costs in BDL105-16 in the amount of $12,794.70 (the costs decision).[2]

    [2]Dunne v Dwyer Quality Homes (No. 2) [2017] QCAT…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes v Dunne and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2018] QCATA 193
Decision Date

CaseChat Overview and Summary

The Dunnes filed an application for domestic building disputes against Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes (DQH) for termite damage to a house they purchased from DQH. The Dunnes were successful at first instance and substantially successful in the appeal, the tribunal and the Appeal Tribunal finding that the termite damage was covered by the contractual warranty. The Dunnes sought their costs of the proceedings below, and the tribunal found that they were entitled to their costs. DQH appealed the tribunal’s decision to award costs to the Dunnes. The primary issue before the court was whether DQH should be entitled to recover costs of the appeal, and if so, whether the tribunal’s discretion to order costs miscarried. The court found that the Appeal Tribunal had the power to award costs under s 77(3)(h) of the Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act). The tribunal’s discretion to order costs under this section is a broad general one, which must be exercised judicially, not upon irrelevant or extraneous considerations but upon facts connected with or leading up to the litigation. The court found that the tribunal did not miscarry its discretion in ordering costs to the Dunnes. The court also found that the Dunnes were substantially successful in opposing the appeal and that DQH should therefore pay their costs of the appeal. However, the court found that it was appropriate for there to be no order as to costs because the Dunnes were not substantially successful in the appeal. The court also found that the Appeal Tribunal did not err in law in refusing leave to appeal the costs order. The court held that the Appeal Tribunal’s decision not to grant leave to appeal was not an error of law, and that there was no substantial injustice to DQH as a result of this decision.

Orders

Orders of the court

In APL278-17

1. No order as to costs.

In APL027-18

1. Leave to appeal refused.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

For determination are:(a)The costs in APL278-17;(b)The application for leave to appeal and appeal in APL028-18. The decisions in BDL105-16 and APL278-17 DQH entered a contract to build a house for the Dunnes, with construction being completed around December 2007. The contract included a special condition that the house had a full thirty year structural guarantee. Termites subsequently damaged the house. The Dunnes filed an application for domestic building disputes. They were successful at first instance and substantially successful in the appeal, the tribunal and the Appeal Tribunal finding that the termite damage was covered by the contractual warranty. The Dunnes were awarded damages at first instance of $71,217.12. On appeal the damages payable by DQH were reduced to $66,537.18. The Dunnes sought their costs of the proceedings below. Both parties were self-represented. The tribunal found that the Dunnes were entitled to their costs.[3] The costs allowed related to expert witness fees of $12,452.00 and the filing fees on the application.[3]Ibid. Costs in QCAT – the statutory framework An appeal against a costs order may only be made if the leave of the appeal tribunal is first obtained.[4] The relevant principles for determining whether leave should be granted are well established: is there a reasonably arguable case of error in the primary decision?;[5] is there a reasonable prospect that the applicant will obtain substantive relief?;[6] is leave necessary to correct a substantial injustice to the applicant caused by some error?;[7] is there a question of general importance upon which further argument, and a decision of the appellate court or Tribunal, would be to the public advantage?[8][4]QCAT Act, s 142(3)(a)(iii).[5] QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd R 41. [6] Cachia v Grech [2009] NSWCA 232, [13].[7]Ibid. [8]Glenwood Properties Pty Ltd v Delmoss Pty Ltd [1986] 2 Qd R 388, 389; McIver Bulk Liquid Haulage Pty Ltd v Fruehauf Australia Pty Ltd [1989] 2 Qd R 577, 578, 580. The starting point in any consideration of costs in the tribunal is that, other than as provided under the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act) or an enabling Act, each party should bear their own costs.[9] [9]QCAT Act, s 100. The relevant enabling Act in these appeals and in BDL105-16 is the Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act). By s 77(3)(h) of the QBCC Act, the tribunal may award costs. The power to award costs under this section applies in appeal tribunal proceedings.[10][10]See Olindaridge Pty Ltd & Wagner v Tracey [2015] QCATA 175 followed in Pivovarova v Michelsen [2016] QCATA 45. See also Wharton v Duffy Constructions (QLD) Pty Ltd [2016] QCATA 12 followed in Lee Manson t/as Manson Homes v Brett & Anor [2018] QCATA 109. The discretion to order costs under s 77(3)(h) is a broad general one, which must be exercised judicially, not upon irrelevant or extraneous considerations but upon facts connected with or leading up to the litigation.[11][11]Lyons v Dreamstarter Pty Ltd [2011] QCATA 142.

Ratio Decidendi

Legal principle established

The Dunnes say that DQH was substantially unsuccessful in the appeal, that they were substantially successful in opposing the appeal and that DQH should therefore pay their costs of the appeal. The Dunnes say the costs should be assessed on the District Court scale. Consideration APL027-18 As we have observed, the relevant enabling Act governing proceeding BDL105-16 is the QBCC Act. The tribunal may, by s 77(3)(h) of the QBCC Act, award costs. The submission by DQH that costs in the proceeding below are governed by s 100 of the QCAT Act is not correct. Section 147 of the QCAT Act constrains the powers of the Appeal Tribunal to decide an appeal on a question of fact or a question of mixed law and fact. The Appeal Tribunal may confirm or amend the decision under appeal[13] or set aside the decision and substitute its own decision.[14] As we observed in the primary decision:[29] We now proceed to decide the appeal by way of rehearing. It was held in Harrison & Anor v Meehan, and confirmed on appeal by the Court of Appeal, that: [20] . . . Appeals by way of rehearing involve a new determination of the rights and liabilities of the parties, rather than a mere correction of errors in the determination of the Tribunal below. [21] An appeal by way of rehearing under s 147 of the QCAT Act is not a rehearing de novo. The Appeal Tribunal must make its own determination on the material before the Tribunal below (supplemented, if necessary, by additional evidence if permitted under s 147(2)) with due respect for the findings of fact of the primary Tribunal, and due to consideration of the advantages enjoyed by it. [30] In Harrison, the appeal tribunal, in comments that on appeal were also specifically endorsed by the Court of Appeal, went on to say that in rehearing the matter: … we have adopted the learned member’s primary findings of fact other than where those findings have been challenged in these appeals or where there is some doubt as to the findings made. (footnotes omitted)[15][13]QCAT Act, s 147(3)(a).[14]Ibid, s 147(3)(b).[15]Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes v Dunne [2018] QCATA 112. We also held in the primary decision:[31] In this appeal the Member’s findings that the termite barrier was breached; that the breach was caused by failure of the termite barrier; and that the breach caused the damage are not challenged. Consistent with the approach endorsed by the Court of Appeal, we adopt the Member’s findings on these matters. One of the grounds of appeal relied upon is that the Member erred in assessing the home owners’ entitlement to damages. We will address this ground of appeal in rehearing the matter.[32] The issues raised in the grounds of appeal relate primarily to the construction and application of the Contract. In deciding the appeal by way of rehearing the matter, the decision of the learned member at first instance was set aside and in lieu a different decision made. DQH says that the consequence of this is that there is no basis for the learned member’s decision on costs to stand.