Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes v Dunne

Link copied
Case Copied 43 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes v Dunne [2018] QCATA 112

PARTIES:

DWYER CORPORATION PTY LTD TRADING AS DWYER QUALITY HOMES
(applicant)

v

BRUCE DUNNE

(first respondent)

HEIDI DUNNE

(second respondent)

APPLICATION NOS:

APL278-17, APL027-18

ORIGINATING APPLICATION NO:

BDL105-16

MATTER TYPE:

Appeals

DELIVERED ON:

10 August 2018

HEARING DATE:

5 March 2018

HEARD AT:

Brisbane

DECISION OF:

Senior Member Brown
Member Olding

ORDERS:

In APL278-17:

1.   The application for leave to appeal is granted.

2.   The appeal is allowed.

3.   The decision of the Tribunal made on 2 August 2017 is set aside.

4.   In lieu, Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes must pay to Bruce Dunne and Heidi Dunne the sum of $66,537.18 within 28 days of the date of this decision.

5.   Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes must file in the Tribunal two (2) copies and give to Bruce Dunne and Heidi Dunne one (1) copy of any submissions on costs, by: 4:00pm on 24 August 2018.

6.   Bruce Dunne and Heidi Dunne must file in the Tribunal two (2) copies and give to Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes one (1) copy of any submissions in response, by: 4:00pm on 7 September 2018. 

7.   Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes must file in the Tribunal two (2) copies and give to Bruce Dunne and Heidi Dunne one (1) copy of any submissions in reply, by: 4:00pm on 21 September 2018.

8.   Unless a party requests an oral hearing by 4:00pm on 21 September 2018 costs in APL278-17 will be decided on the papers and without an oral hearing.

In APL027-18:

1.   Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes must file in the Tribunal two (2) copies and give to Bruce Dunne and Heidi Dunne one (1) copy of any further submissions including submissions on costs, by: 4:00pm on 24 August 2018.

2.   Bruce Dunne and Heidi Dunne must file in the Tribunal two (2) copies and give to Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes one (1) copy of any submissions in response, by: 4:00pm on 7 September 2018. 

3.   Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes must file in the Tribunal two (2) copies and give to Bruce Dunne and Heidi Dunne one (1) copy of any submissions in reply, by: 4:00pm on 21 September 2018.

4.   Unless a party requests an oral hearing by 4:00pm on 21 September 2018, the Application for leave to appeal or appeal, including the costs of the appeal, will be decided on the papers and without an oral hearing.

CATCHWORDS:

CONTRACTS – BUILDING ENGINEERING AND RELATED CONTRACTS – THE CONTRACT –GENERALLY – where contract provided for ‘full thirty year structural guarantee’ – where ‘guarantee’ construed as a structural warranty – whether failure of termite barrier covered by the structural warranty

Building Act 1975 (Qld), s 30(1)(f)
Building Code of Australia 2006, Vol 2, 1.1, O2.1(d), P2.1.1, 3.1
Domestic Building Contracts…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes v Dunne and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2018] QCATA 112
Decision Date

CaseChat Overview and Summary

Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes (DQH) appeals against a decision of the Queensland Civil and Administrative Tribunal (QCAT) that it was liable for termite damage to a house it constructed for the Dunnes, and the Tribunal’s order that DQH pay the Dunnes $66,537.18 for the damage. The Dunnes cross-appeal against the amount of the damages award. The appeals raise issues as to the meaning of a ‘full thirty year structural guarantee’ provided in the residential building contract, and whether the limitation period applicable to the Dunnes’ claim had expired. The Court considered the contract's clause 3.2, which states that the terms of the contract are set out in the contract and shall not be altered by reference to any prior representations, conditions, or agreements, written or verbal. The contract also included a special condition, stating that the house had a twenty-six week defects liability period and a full thirty-year structural guarantee. The Court held that the warranty contained in Special Condition 3 of the contract covered the failure of the termite barrier and the termite damage. The Court also found that the learned Member did not err in finding that DQH could be liable for damage caused by termites to the subject property at a time more than 6 years and 3 months after the date of practical completion. The Court set aside the decision of the Tribunal made on 2 August 2017, and ordered that Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes must pay to Bruce Dunne and Heidi Dunne the sum of $66,537.18 within 28 days of the date of this decision.

Orders

Orders of the court

In APL278-17:

1. The application for leave to appeal is granted.

2. The appeal is allowed.

3. The decision of the Tribunal made on 2 August 2017 is set aside.

4. In lieu, Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes must pay to Bruce Dunne and Heidi Dunne the sum of $66,537.18 within 28 days of the date of this decision.

5. Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes must file in the Tribunal two (2) copies and give to Bruce Dunne and Heidi Dunne one (1) copy of any submissions on costs, by: 4:00pm on 24 August 2018.

6. Bruce Dunne and Heidi Dunne must file in the Tribunal two (2) copies and give to Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes one (1) copy of any submissions in response, by: 4:00pm on 7 September 2018.

7. Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes must file in the Tribunal two (2) copies and give to Bruce Dunne and Heidi Dunne one (1) copy of any submissions in reply, by: 4:00pm on 21 September 2018.

8. Unless a party requests an oral hearing by 4:00pm on 21 September 2018 costs in APL278-17 will be decided on the papers and without an oral hearing.

In APL027-18:

1. Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes must file in the Tribunal two (2) copies and give to Bruce Dunne and Heidi Dunne one (1) copy of any further submissions including submissions on costs, by: 4:00pm on 24 August 2018.

2. Bruce Dunne and Heidi Dunne must file in the Tribunal two (2) copies and give to Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes one (1) copy of any submissions in response, by: 4:00pm on 7 September 2018.

3. Dwyer Corporation Pty Ltd t/as Dwyer Quality Homes must file in the Tribunal two (2) copies and give to Bruce Dunne and Heidi Dunne one (1) copy of any submissions in reply, by: 4:00pm on 21 September 2018.

4. Unless a party requests an oral hearing by 4:00pm on 21 September 2018, the Application for leave to appeal or appeal, including the costs of the appeal, will be decided on the papers and without an oral hearing.

Background

Background to the litigation

DQH also seeks leave to appeal an associated costs decision (‘the second appeal’), but only if successful in the first appeal. The appeals are to be heard and decided together. Background DQH constructed a house for the Dunnes pursuant to a residential building contract (the Contract) entered into on 26 February 2007, with construction being completed around December 2007. The house suffered termite damage, the most significant damage becoming evident in 2014. The Contract was in the form of the Master Builders Queensland Residential Building Contract RBC May 2005 and incorporated the RBC May 2005 General Conditions. The General Conditions included clause 3.2, as follows:3.2 Contract complete in itselfThe parties acknowledge that the terms of this Contract are set out in the Contract and shall not be altered, varied, suspended, deleted, or affected by reference to any prior representations, conditions or agreement, whether written or verbal. ‘Contract’ in turn is defined in clause 1 of the General Conditions as:Contract – means these general conditions, the Schedule, the Plans, the Specifications, and any other documents annexed to, or incorporated by reference in, the Contract. Under clause 2(a) of the General Conditions:(a) headings and explanatory notes contained in this Contract do not form part of and cannot be used in its interpretation. The General Conditions also adopted[1] the statutory warranties under Part 4 of the now-repealed Domestic Building Contracts Act 2000 (Qld), but by the time the Dunnes commenced proceedings against DQH, the time limit of 6 years and 6 months for commencing proceedings for breach of the statutory warranties had expired. This meant that proceedings could not be brought pursuant to the statute or the condition adopting the statutory warranties.[1]Clause 10.1. However, the Contract also included a special condition (Special Condition 3) in these terms:3. House has a twenty six week defects liability period and a full thirty year structural guarantee. Additionally, the Dunnes were given what the Member described as a ‘separate “guarantee” flyer described variously as a 30 year “structural guarantee” and a 30 year “structure guarantee”’ (the Flyer), which provided in part:3. This guarantee covers only structural integrity of the footing slab design, and structural construction work by Dwyer Corporation Pty Ltd in the dwelling, but does not include timber shrinkage or movement, surface or shrinkage cracks in brickwork, concrete slabs, gyprock, cement, plaster or timber, movement, cracking or lifting of ceramic tiles, or any other matter whatsoever which in the opinion of Dwyer Corporation Pty Ltd is non-structural. The Flyer was not signed on behalf of DQH, nor annexed to or referred to in the Contract. DQH’s practice was to provide it at the handover. The expressions ‘structural guarantee’, ‘structural construction work’ and ‘non-structural’ are not defined in the Flyer or in the Contract.

Evidence

Evidence before the court

Decision

Reasons for decision

Accordingly, even if the warranty was to be construed as conditioned upon reasonable monitoring and maintenance by the Dunnes, the damage is attributable to shortcomings in the installation of the termite barrier by DQH and not to lack of monitoring or maintenance. Conclusion on meaning of ‘full thirty year structural guarantee’ Having regard to these matters, we consider that installation of a termite barrier, when such a barrier is required for protection of the integrity of a building, falls within a ‘full thirty year structural guarantee’. This view is consistent with the reference to a ‘full’ structural warranty in the composite expression found in Special Condition 3. It is also broadly consistent with the BCA requirements, although we would reach the same conclusion without reference to those requirements. A narrower construction would mean that a builder who committed to a ‘full thirty year structural guarantee’ would not be liable for a shortcoming in construction of a residence that leads directly to serious damage to its structural elements. Accordingly, we consider that the warranty contained in Special Condition 3 of the contract covered the failure of the barrier and the termite damage.Application of limitation period One of the grounds of appeal raised by DQH is that the learned Member erred in finding that DQH could be liable for damage caused by termites to the subject property at a time more than 6 years and 3 months after the date of practical completion. In rehearing the matter, it is appropriate that we consider what the parties said about time limits in respect of the claim by the Dunnes. At the outset, we observe that as there are no pleadings in the Tribunal; the issues for determination and the relevant questions of fact and law which the Tribunal is required to decide are identified in the application, the response and the parties’ statements of evidence. The Dunnes’ Application for domestic building disputes[33] does not specifically refer to, nor seek to rely upon, Special Condition 3 of the contract. The Dunnes refer to ‘4 known termite protective barrier breaches within the warranty period’. It is not readily apparent whether this is a reference to the period within which application was required to be made to the Queensland Building and Construction Commission for a direction to rectify defective or incomplete work or a reference to the period within which a claim for a breach of statutory warranty was required to be made.[34] [33]Application for domestic building disputes filed 29 April 2016.[34]Queensland Building and Construction Commission Act 1991 (Qld), s 72A(4); Domestic Building Contracts Act 2000 (Qld), s 51(1). In its response, DQH asserts that the ‘construction is well out of builders warrantee (sic) period’.[35] DQH says in its response:DQHs warrantee (sic) period is a generous one. As the house is well out of the 6 year 3 month major defect period and any major defect must be contained to any remedial work undertaken by DQH within the last 6 years and 3 months. [35]Response filed 1 June 2016.

Ratio Decidendi

Legal principle established