SUPREME COURT OF QUEENSLAND
CITATION:
Dawnlite Pty Ltd v Riverwalk Realty Pty Ltd & Ors [2013] QSC 243
PARTIES:
DAWNLITE PTY LTD (ACN 010 647 677)
(plaintiff)
v
RIVERWALK REALTY PTY LIMITED (ACN 002 606 000)
(1st defendant)AND
ELDSURE PTY LTD (ACN 071 335 861)
(2nd defendant)AND
SAMEL HOLDINGS PTY LTD (ACN 114 423 755)
(3rd defendant)AND
INTEGRATED ASSET MANAGEMENT (QUEENSLAND) PTY LTD (ACN 117 065 264)
(4th defendant)AND
BROADBEACH RENTAL MANAGEMENT PTY LTD (ACN 075 025 900)
(5th defendant)AND
NRGC MERMAID BEACH PTY LTD (ACN 122 398 396)
(6th defendant)AND
NRGC COMMERCIAL PTY LTD (ACN 122 398 396)
(7th defendant)AND
NRGC REAL ESTATE GROUP PTY LTD (ACN 122 593 177)
(8th defendant)AND
TREVOR IAN MILLS
(9th defendant)AND
GLENN DAVID MILLS
(10th defendant)AND
WANTANA PTY LTD (ACN 001 653 612)
(11th defendant)AND
LYNNE ROBYN YALDWYN
(12th defendant)AND
PHILIP JOHN L NICOLSON
(13th defendant)AND
DAVID WILLIAM SOMMERVILLE
(14th defendant)AND
ADAM JEREMY GAITER
(15th defendant)AND
CHRISTOPHER JAMES HOLT
(16th defendant)AND
TOHL PTY LTD (ACN 106 015 221)
(17th defendant)AND
DAVID MILLS
(18th defendant)AND
JARED KARL HODGE
(19th defendant)AND
KIMBA EQUITY INVESTMENTS PTY LTD (ACN 101 847 198)
(20th defendant)AND
MATTHEW GERARD STEINHOUR
(21st defendant)FILE NO:
BS 8735 of 2009
DIVISION:
Trial Division
PROCEEDING:
Trial
DELIVERED ON:
12 September 2013
DELIVERED AT:
Brisbane
HEARING DATES:
25- 28 February, 1, 4, 6 March 2013
Supplementary written submissions 7, 11 March 2013
JUDGE:
Justice Margaret Wilson
ORDER:
1. Claim dismissed.
2. Leave to the parties to make written submissions as to costs – the defendants’ submissions to be provided by 4pm on 17 September 2013 and the plaintiff’s submissions to be provided by 4pm on 19 September 2013.
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – FORMATION OF CONTRACTUAL RELATIONS – where the plaintiff alleged that two oral agreements were made between it and the defendants – where the plaintiff alleged that the first agreement was for the plaintiff to provide $650,000 to be used to acquire two real estate businesses – where these businesses would in turn be consolidated with four existing real estate businesses owned or controlled by the defendants – where the plaintiff alleged that it would have an equity interest in the expanded group business reflecting the amount of its initial contribution – where the plaintiff alleged that under the first agreement, it would be paid the value of its initial contribution at the latest by 60 days after it gave notice of its requirement that that occur – where the plaintiff alleged that the second agreement was for the redemption and repayment of its investment by 30 June 2009 – where the defendants alleged that the first agreement was for the plaintiff to purchase two real estate businesses, with the mere possibility of merging with the four existing real…
Keep reading for free
Create a free CaseChat account to read Dawnlite Pty Ltd v Riverwalk Realty Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] QSC 243
- Decision Date
CaseChat Overview and Summary
The court found that the plaintiff had not proved the agreements were made in the terms alleged. The court held that the 9th defendant did not have express, implied, or ostensible authority to enter the agreement on behalf of the defendants, nor had the defendants ratified the agreement. The court further held that the plaintiff had not proved that the defendants made representations that amounted to an estoppel. The court dismissed the claim and ordered that the parties could make written submissions as to costs. The defendants' submissions were to be provided by 4pm on 17 September 2013 and the plaintiff's submissions by 4pm on 19 September 2013.
Orders
Orders of the court
1. Claim dismissed.
2. Leave to the parties to make written submissions as to costs – the defendants’ submissions to be provided by 4pm on 17 September 2013 and the plaintiff’s submissions to be provided by 4pm on 19 September 2013.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.