CPB Contractors Pty Ltd v Transport for NSW

Link copied
Case Copied 22 min read

Supreme Court


New South Wales

Medium Neutral Citation: CPB Contractors Pty Ltd v Transport for NSW [2021] NSWSC 537
Hearing dates: 29 April 2021
Decision date: 14 May 2021
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

Proceedings stayed in respect of claims set out in pars 7 to 37 of Plaintiff’s Commercial List Statement

Catchwords:

CONTRACTS – Expert determination regarding contract to perform road widening works on Pacific Motorway – where expert determined issue adversely to plaintiff – where plaintiff commenced proceeding to reagitate that issue – whether plaintiff precluded by the terms of the contract from litigating that issue– whether an expert determination that no further compensation is payable is a determination that does not involve paying a sum of money

CONTRACTS – provision for expert determination – whether there was a deficiency or error in determination that disclosed expert did not make a determination in accordance with the contract

PRACTICE AND PROCEDURE – expert determination as to part of the claim the subject of the proceedings – whether proceedings commenced in the face of an expert determination should be stayed in part

Cases Cited:

Dance With Mr D Ltd v Dirty Dancing Investments Pty Ltd [2009] NSWSC 332

Electricity Generation Corp v Woodside Energy Ltd; Woodside Energy Ltd v Electricity Generation Corp (2014) 251 CLR 640; [2014] HCA 7

John Holland Pty Limited v Kellogg Brown & Root Pty Ltd [2015] NSWSC 451

Lahey Constructions Pty Ltd v State of New South Wales [2021] NSWCA 69

Lepcanfin Pty Ltd v Lepfin Pty Ltd [2020] NSWCA 155

Mount Bruce Mining Pty Limited v Wright Prospecting Pty Limited (2015) 256 CLR 104; [2015] HCA 37

Onslow Salt Pty Ltd v Buurabalayji Thalanyji Aboriginal Corp [2018] FCAFC 118

Shoalhaven City Council v Firedam Civil Engineering Pty Ltd (2011) 244 CLR 305; [2011] HCA 38

South Western Sydney Local Health District v Gould (2018) 97 NSWLR 513; [2018] NSWCA 69

Tal Life Ltd v Shuetrim; MetLife Insurance Ltd v Shuetrim (2016) 91 NSWLR 439; [2016] NSWCA 68

Zeke Services Pty Ltd atf Zeke Discretionary Trust v Traffic Technologies Ltd [2005] QSC 135

Texts Cited:

P Herzfeld and T Prince, Interpretation (Thomson Reuters, 2nd ed, 2020)

Category:Procedural rulings
Parties: CPB Contractors Pty Ltd (Plaintiff)
Transport for NSW (Defendant)
Representation:

Counsel:
P S Braham SC with C Roberts (Plaintiff)
T J Breakspear (Defendant)

Solicitors:
File Number(s): SC 2020/293681

Judgment

  1. By a contract dated 23 March 2017 (“the Contract”) made between Roads and Maritime Services (“RMS”) and the Plaintiff, CPB Contractors Pty Ltd (“CPB”), RMS engaged CPB to carry out work widening approximately 12.5km of the M1 Pacific Motorway from Tuggerah to Doyalson.

  2. The defendant, Transport for NSW (“Transport”) is the statutory successor to RMS. I will not refer further to RMS but will refer simply to Transport.

  3. In the course of carrying out the road widening work, CPB accumulated excess non contaminated spoil.

  4. Transport issued CPB with a series of Site Instructions to remove that…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CPB Contractors Pty Ltd v Transport for NSW and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] NSWSC 537
Decision Date

CaseChat Overview and Summary

CPB Contractors Pty Ltd sued Transport for New South Wales, seeking to re-litigate a determination made by an expert in relation to a contract for road widening works on the Pacific Motorway. The expert had determined that CPB Contractors were not entitled to any further compensation, a decision which CPB Contractors contested. The primary issue before the court was whether CPB Contractors were precluded by the terms of the contract from litigating the issue and whether the expert determination constituted a determination that did not involve paying a sum of money. The court also had to consider whether there was any deficiency or error in the expert's determination that suggested the expert did not make a determination in accordance with the contract. Furthermore, the court needed to decide whether proceedings commenced in the face of an expert determination should be stayed in part.

The court found that CPB Contractors were precluded by the terms of the contract from litigating the issue of further compensation, as the contract contained a clause preventing such re-litigation. The court held that the expert determination was not a determination that involved paying a sum of money, as it did not result in CPB Contractors being liable to pay any amount to Transport for New South Wales. The court also determined that there was no deficiency or error in the expert's determination that suggested the expert did not make a determination in accordance with the contract. Finally, the court concluded that proceedings commenced in the face of an expert determination should not be stayed in part, as the proceedings were not in relation to the same subject matter as the expert determination.

The orders of the court were that CPB Contractors' claim was to be dismissed in its entirety, and that Transport for New South Wales were entitled to their costs of the proceeding.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.