Supreme Court
New South Wales
Medium Neutral Citation: CPB Contractors Pty Ltd v Transport for NSW [2021] NSWSC 537 Hearing dates: 29 April 2021 Decision date: 14 May 2021 Jurisdiction: Equity - Technology and Construction List Before: Stevenson J Decision: Proceedings stayed in respect of claims set out in pars 7 to 37 of Plaintiff’s Commercial List Statement
Catchwords: CONTRACTS – Expert determination regarding contract to perform road widening works on Pacific Motorway – where expert determined issue adversely to plaintiff – where plaintiff commenced proceeding to reagitate that issue – whether plaintiff precluded by the terms of the contract from litigating that issue– whether an expert determination that no further compensation is payable is a determination that does not involve paying a sum of money
CONTRACTS – provision for expert determination – whether there was a deficiency or error in determination that disclosed expert did not make a determination in accordance with the contract
PRACTICE AND PROCEDURE – expert determination as to part of the claim the subject of the proceedings – whether proceedings commenced in the face of an expert determination should be stayed in part
Cases Cited: Dance With Mr D Ltd v Dirty Dancing Investments Pty Ltd [2009] NSWSC 332
Electricity Generation Corp v Woodside Energy Ltd; Woodside Energy Ltd v Electricity Generation Corp (2014) 251 CLR 640; [2014] HCA 7
John Holland Pty Limited v Kellogg Brown & Root Pty Ltd [2015] NSWSC 451
Lahey Constructions Pty Ltd v State of New South Wales [2021] NSWCA 69
Lepcanfin Pty Ltd v Lepfin Pty Ltd [2020] NSWCA 155
Mount Bruce Mining Pty Limited v Wright Prospecting Pty Limited (2015) 256 CLR 104; [2015] HCA 37
Onslow Salt Pty Ltd v Buurabalayji Thalanyji Aboriginal Corp [2018] FCAFC 118
Shoalhaven City Council v Firedam Civil Engineering Pty Ltd (2011) 244 CLR 305; [2011] HCA 38
South Western Sydney Local Health District v Gould (2018) 97 NSWLR 513; [2018] NSWCA 69
Tal Life Ltd v Shuetrim; MetLife Insurance Ltd v Shuetrim (2016) 91 NSWLR 439; [2016] NSWCA 68
Zeke Services Pty Ltd atf Zeke Discretionary Trust v Traffic Technologies Ltd [2005] QSC 135
Texts Cited: P Herzfeld and T Prince, Interpretation (Thomson Reuters, 2nd ed, 2020)
Category: Procedural rulings Parties: CPB Contractors Pty Ltd (Plaintiff)
Transport for NSW (Defendant)Representation: Counsel:
Solicitors:
P S Braham SC with C Roberts (Plaintiff)
T J Breakspear (Defendant)
File Number(s): SC 2020/293681
Judgment
-
By a contract dated 23 March 2017 (“the Contract”) made between Roads and Maritime Services (“RMS”) and the Plaintiff, CPB Contractors Pty Ltd (“CPB”), RMS engaged CPB to carry out work widening approximately 12.5km of the M1 Pacific Motorway from Tuggerah to Doyalson.
-
The defendant, Transport for NSW (“Transport”) is the statutory successor to RMS. I will not refer further to RMS but will refer simply to Transport.
-
In the course of carrying out the road widening work, CPB accumulated excess non contaminated spoil.
-
Transport issued CPB with a series of Site Instructions to remove that…
Keep reading for free
Create a free CaseChat account to read CPB Contractors Pty Ltd v Transport for NSW and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] NSWSC 537
- Decision Date
CaseChat Overview and Summary
The court found that CPB Contractors were precluded by the terms of the contract from litigating the issue of further compensation, as the contract contained a clause preventing such re-litigation. The court held that the expert determination was not a determination that involved paying a sum of money, as it did not result in CPB Contractors being liable to pay any amount to Transport for New South Wales. The court also determined that there was no deficiency or error in the expert's determination that suggested the expert did not make a determination in accordance with the contract. Finally, the court concluded that proceedings commenced in the face of an expert determination should not be stayed in part, as the proceedings were not in relation to the same subject matter as the expert determination.
The orders of the court were that CPB Contractors' claim was to be dismissed in its entirety, and that Transport for New South Wales were entitled to their costs of the proceeding.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.