FEDERAL COURT OF AUSTRALIA
Onslow Salt Pty Ltd v Buurabalayji Thalanyji Aboriginal Corporation [2018] FCAFC 118
Appeal from: Buurabalayji Thalanyji Aboriginal Corporation v Onslow Salt Pty Ltd [2017] FCA 1240 File number(s): WAD 546 of 2017 Judge(s): BESANKO, BARKER AND COLVIN JJ Date of judgment: 18 July 2018 Date of publication of reasons: 2 August 2018 Catchwords:
PRACTICE AND PROCEDURE – where dispute resolution clause provided for independent advisory opinion to be obtained before commencing court proceedings – where proceedings commenced without joining in agreed process for advisory opinion – decision by primary judge to refuse stay of proceedings – appeal from refusal – whether non‑binding nature of dispute resolution process relevant to discretion – whether trial judge formed view that dispute resolution clause did not apply to particular dispute – no error by primary judge in exercise of discretion – appeal dismissed
Legislation: Commercial Arbitration Act 2010 (Cth)
Native Title Act 1993 (Cth)
Cases cited: Badgin Nominees Pty Ltd v Oneida Ltd [1998] VSC 188
BHPB Freight Pty Ltd v Cosco Oceania Chartering Pty Ltd [2008] FCA 551
Buurabalayji Thalanyji Aboriginal Corporation v Onslow Salt Pty Ltd [2017] FCA 1240
Computershare Ltd v Perpetual Registrars [2000] VSC 233
Dance With Mr D Ltd v Dirty Dancing Investments Pty Ltd [2009] NSWSC 332
Hancock Prospecting Pty Ltd v Rinehart [2017] FCAFC 170
Hooper Bailie Associated Ltd v Natcon Group Pty Ltd (1992) 28 NSWLR 194
House v The King [1936] HCA 40; (1936) 55 CLR 499
Huddart Parker Ltd v The Ship Mill Hill [1950] HCA 43; (1950) 81 CLR 502
Mineral Resources Ltd v Pilbara Minerals Ltd [2016] WASC 338
Raskin v Mediterranean Olives Estate Ltd [2017] VSC 94
Recyclers of Australia Pty Ltd v Hettinga Equipment Inc [2000] FCA 547; (2000) 100 FCR 420
Savcor Pty Ltd v State of New South Wales [2001] NSWSC 596; (2001) 52 NSWLR 587
Straits Exploration (Australia) Pty Ltd v Murchison United NL [2005] WASCA 241; (2005) 31 WAR 187
Zeke Services Pty Ltd v Traffic Technologies Ltd [2005] QSC 135; [2005] 2 Qd R 563
Date of hearing: 18 July 2018 Registry: Western Australia Division: General Division National Practice Area: Native Title Category: Catchwords Number of paragraphs: 44 Counsel for the Applicant: Mr SK Dharmananda SC with Mr JL Southalan Solicitor for the Applicant: Gilbert + Tobin Counsel for the First Respondent: Mr ML Bennett Solicitor for the First Respondent: Bennett + Co Counsel for the Second Respondent: The Second Respondent filed a submitting notice, save as to costs Table of Corrections 3 August 2018 Amendment to counsel for the applicant's name, from 'Mr J Southerland', to correctly read 'Mr JL Southalan'. ORDERS
WAD 546 of 2017 BETWEEN: ONSLOW SALT PTY LTD (ACN 050 159 558)
Applicant
AND: BUURABALAYJI THALANYJI ABORIGINAL CORPORATION (RNTBC)
First Respondent
THE STATE OF WESTERN AUSTRALIA
Second Respondent
JUDGES:
BESANKO, BARKER AND COLVIN JJ
DATE OF ORDER:
18 JULY 2018
THE COURT ORDERS THAT:
1.The appeal be dismissed.
2.The appellant pay…
Keep reading for free
Create a free CaseChat account to read Onslow Salt Pty Ltd v Buurabalayji Thalanyji Aboriginal Corp... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] FCAFC 118
- Decision Date
CaseChat Overview and Summary
The appeal raised two main issues for the court. The first was whether the non-binding nature of the dispute resolution process was relevant to the exercise of the court's discretion to stay the proceedings. The second was whether the primary judge had erred in deciding that the dispute resolution clause did not apply to the particular dispute. Onslow Salt argued that the non-binding nature of the dispute resolution process was relevant because it meant that the process was not binding and therefore not a prerequisite to commencing court proceedings. The Corporation argued that the nature of the dispute resolution process was irrelevant because the clause was a condition precedent to the commencement of proceedings. The court held that the non-binding nature of the dispute resolution process was not relevant to the exercise of the court's discretion to stay the proceedings. The court also held that the primary judge had not erred in deciding that the dispute resolution clause did not apply to the particular dispute because it only applied to disputes concerning the interpretation, application or enforcement of the state agreement, and the dispute was not about that.
The court dismissed the appeal and ordered that Onslow Salt pay the Corporation's costs of and incidental to the appeal, to be taxed in default of agreement. The court held that the primary judge had not erred in refusing the stay of proceedings because the dispute resolution clause did not apply to the particular dispute and because the Corporation had substantial merits in its case. The court also held that the non-binding nature of the dispute resolution process was not relevant to the exercise of the court's discretion to stay the proceedings. The court noted that the dispute resolution clause was a condition precedent to the commencement of proceedings, but that did not mean that the process had to be binding. The court also noted that the Corporation had substantial merits in its case because it alleged that Onslow Salt and the State had breached their statutory and contractual obligations under the Native Title Act 1993 (Cth). The court concluded that the appeal should be dismissed and that Onslow Salt should pay the Corporation's costs of and incidental to the appeal.
Orders
Orders of the court
1. The appeal be dismissed.
2. The appellant pay the first respondent's costs of and incidental to the appeal, to be taxed in default of agreement.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Buurabalayji Thalanyji Aboriginal Corporation (Corporation) is the holder as trustee of native title rights on behalf of the Thalanyji people for an area to the south of Onslow in Western Australia. Under the terms of a state agreement, Onslow Salt Pty Ltd was granted a mining lease over an area located to the south west of Onslow and near the coast. The mining lease area is within the native title area. In July 2017, the Corporation commenced proceedings against Onslow Salt and the State of Western Australia concerning activities in the native title area. Onslow Salt complained that the proceedings had been commenced in breach of the requirements of a dispute resolution clause. It made an application for a stay of the proceedings on that basis. The application was refused: Buurabalayji Thalanyji Aboriginal Corporation v Onslow Salt Pty Ltd [2017] FCA 1240. Leave was given for Onslow Salt to appeal against that decision. We heard the appeal on 18 July 2018 and made orders dismissing the appeal with costs. These are our reasons for those orders.The nature of the proceedings In the proceedings before the primary judge, the Corporation claimed, amongst other things, that:(1)in 2011, Onslow Salt entered into agreements with Chevron Australia Pty Ltd;(2)the agreements purported to provide for flood mitigation works to be undertaken by Chevron which involved the removal of up to 10 million cubic metres of fill from the salt mining area;(3)the agreements were a sham;(4)what had actually been agreed was that Onslow Salt would grant a licence to Chevron to excavate fill for Chevron's Wheatstone project;(5)an approval was required from the relevant Minister for work to be undertaken in the mining area;(6)a purported approval was obtained from the Minister under the terms of the state agreement for flood mitigation works;(7)the approval was invalid;(8)acting on the purported approval, Onslow Salt allowed Chevron to remove fill from the mining lease area and received at least $70 million from Chevron;(9)the approval of the removal of fill could only proceed with notification to the Corporation and negotiation of an indigenous land use agreement under the Native Title Act 1993 (Cth) with Onslow Salt or the State;(10)the purpose of Onslow Salt in making the sham agreement was to avoid negotiation of an indigenous land use agreement with the Corporation;(11)the State knew of the purpose of Onslow Salt and the failure by the State to notify the Corporation occurred in breach of a statutory duty;(12)alternatively, if the State did not know of the purpose of the agreement then Onslow Salt engaged in misleading and deceptive conduct in obtaining the approval from the Minister without disclosing the true purpose;(13)even if it did not know of the purpose of Onslow Salt, the State had a statutory duty in dealing with native title rights and in breach of that duty negligently failed to notify the Corporation; and (14)by its conduct in seeking and obtaining the approval in the manner in which it did, Onslow Salt tortiously interfered with the native title rights and economic interests of the Corporation.