Supreme Court
New South Wales
Medium Neutral Citation: CPB Contractors Pty Limited v Transport for NSW [2025] NSWSC 1005 Hearing dates: 27 August 2025 Date of orders: 4 September 2025 Decision date: 04 September 2025 Jurisdiction: Equity - Technology and Construction List Before: Hammerschlag CJ in Eq Decision: Paragraphs of the Second Further Amended Technology and Construction List Statement are struck out
Catchwords: PRACTICE AND PROCEDURE – Practice Note SC Eq 3 – CONTRACTS – Construction – Application to strike out paragraphs of a Technology and Construction List Statement pleading a claim in contract on the basis that no reasonable cause of action is disclosed – Whether such an application should be entertained – Where plaintiff claims an entitlement to delay costs for delay or disruption to it carrying out work on a substantial contract to the upgrade of a highway – Where the Contract, on its proper construction, makes no provision for the Claim – HELD – Claim struck out
Legislation Cited: Civil Procedure Act 2005 (NSW) s 15
Practice Note SC Eq 3
Cases Cited: Aon Risk Services Australia Ltd v Australian National University (2009) 239 CLR 175; [2009] HCA 27
Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99; [1973] HCA 36
Baffico v YMCA of Great Lakes Inc [2014] NSWCA 61
David William Pallas & Julie Ann Pallas as trustees for the Pallas Family Superannuation Fund v Lendlease Corporation Limited; Martin John Fletcher v Lendlease Corporation Limited [2019] NSWSC 1631
Electricity Generation Corporation Ltd v Woodside Energy Ltd (2014) 251 CLR 640; [2014] HCA 7
General Steel Industries Inc v Commissioner for Railways (NSW) (1964) 112 CLR 125; [1964] HCA 69
Harrington v Browne (1917) 23 CLR 297; [1917] HCA 36
HNOE Limited v Angus & Julia Stone Pty Ltd [2024] NSWCA 271
Lepcanfin Pty Ltd v Lepfin Pty Ltd (2020) 102 NSWLR 627; [2020] NSWCA 155
McCann v Switzerland Insurance Australia Ltd (2000) 203 CLR 579; [2000] HCA 65
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104; [2015] HCA 37
Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451; [2004] HCA 35
Vothv Manildra Flour Mills Pty Ltd (1990) 171 CLR 538; [1990] HCA 55
Wilkie v Gordian Runoff Ltd (2005) 221 CLR 522; [2005] HCA 17
Zhu v Treasurer of the State of New South Wales (2004) 218 CLR 530; [2004] HCA 56
Category: Procedural rulings Parties: CPB Contractors Pty Limited (Plaintiff/Respondent)
Transport for NSW (Defendant/Applicant)Representation: Counsel:
Solicitors:
R Dick SC / E Ball (Plaintiff/Respondent)
N Kidd SC / M Lyons (Defendant/Applicant)
HWL Ebsworth (Plaintiff/Respondent)
Ashurst (Defendant/Applicant)
File Number(s): 2022/00221645 Publication restriction: Nil
JUDGMENT
Introduction
-
The plaintiff is a construction company. The defendant is Transport for New South Wales, a New South Wales government agency. They are embroiled in a substantial building dispute about an upgrade to the Pacific Highway between Woolgoolga and Ballina on the NSW North Coast.
Keep reading for free
Create a free CaseChat account to read CPB Contractors Pty Limited v Transport for NSW and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] NSWSC 1005
- Decision Date
CaseChat Overview and Summary
The court examined the contract terms carefully to assess if there was any basis for CPB Contractors' claim. The contract in question did not contain any provisions that allowed for the recovery of delay costs, either directly or by implication. Consequently, the court found that CPB Contractors had not disclosed a reasonable cause of action for their claim. The court held that the application to strike out the relevant paragraphs of the Statement of Claim was appropriate, as the claim for delay costs was not supported by the contract terms.
Given that the claim for delay costs was not substantiated by the contract, the court struck out the relevant paragraphs of the Statement of Claim. This decision underscored the importance of adhering to the contract terms when making claims, particularly in construction contracts. The court’s ruling highlighted that claims must be grounded in the explicit provisions of the contract, and where such provisions are absent, the claim is not tenable.
Background
Background to the litigation
The matter came before the court following an application by Transport to strike out certain paragraphs of CPB's Technology and Construction List Statement. CPB had filed a statement of claim asserting an entitlement to delay costs, which Transport contested. The application to strike out was based on the argument that the contract did not provide for the recovery of delay costs and that CPB's claim disclosed no reasonable cause of action. The court had to determine whether such an application should be entertained and whether the claim could proceed.
Decision
Reasons for decision
1. Whether the court should entertain an application to strike out paragraphs of a Technology and Construction List Statement pleading a claim in contract on the basis that no reasonable cause of action is disclosed.
2. Whether the contract makes any provision for the recovery of delay costs claimed by CPB.
3. Whether the claim for delay costs disclosed a reasonable cause of action under the contract.
Held
1. The court decided that an application to strike out paragraphs of a Technology and Construction List Statement pleading a claim in contract on the basis that no reasonable cause of action is disclosed should be entertained.
2. The court held that the contract does not make any provision for the recovery of delay costs claimed by CPB.
3. The court concluded that the claim for delay costs did not disclose a reasonable cause of action under the contract and therefore, the application to strike out was allowed.
Ratio Decidendi
Legal Principle Established
The court examined the application to strike out paragraphs of the Technology and Construction List Statement pleading a claim in contract. It was noted that under Practice Note SC Eq 3, such an application can be entertained where no reasonable cause of action is disclosed. The plaintiff, CPB Contractors Pty Limited, claimed an entitlement to delay costs for delays or disruptions encountered during the execution of a substantial contract for the upgrade of a highway. The court focused on the absence of any specific provision in the contract for the recovery of such delay costs. It was held that the contract, when properly construed, did not provide for the claim of delay costs. Consequently, the court concluded that the claim for delay costs did not disclose a reasonable cause of action under the contract, leading to the decision to strike out the claim. The binding legal principle established here is that an application to strike out can be entertained when a claim does not disclose a reasonable cause of action based on the terms of the contract.