| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL COURT
TECHNOLOGY ENGINEERING AND CONSTRUCTION LIST
S ECI 2017 0068
| CONTRACT CONTROL SERVICES PTY LTD (ACN 007 453 965) | Plaintiff |
| v | |
| DEPARTMENT OF EDUCATION AND TRAINING (ABN 52 705 101 522) | First Defendant |
| MAX TONKIN (as adjudicator in an adjudication under the Building and Construction Industry Security of Payment Act 2002 (Vic) between Contract Control Services Pty Ltd and Department of Education and Training) | Second Defendant |
---
JUDGE: | Digby J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 27 June 2017 |
DATE OF JUDGMENT: | 30 August 2017 |
CASE MAY BE CITED AS: | Contract Control Services v DET |
MEDIUM NEUTRAL CITATION: | [2017] VSC 507 |
---
CONTRACTS – Building Contract – Whether incorrect exclusion of non-claimable second class variations – Whether the Construction Contract contained a method for resolving disputes within the meaning of s 10A(3)(d)(ii) of the Building and Construction Industry Security of Payment Act 2002 (Vic) – SSC Plenty Road v Construction Engineering [2016] VSCA 119 – SSC Plenty Road v Construction Engineering [2015] VSC 631 – Branlin Pty Ltd v Totaro [2014] VSC 492.
ADMINISTRATIVE LAW – Judicial review – Decision of adjudicator appointed under the Building and Construction Industry Security of Payment Act 2002 (Vic) – Whether certiorari should be granted to quash the decision.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr M A Robins QC | KCL Law |
| For the Defendant | Mr M Roberts QC | Corrs Chambers Westgarth |
HIS HONOUR:
Summary of Application
By Originating Process dated 16 March 2017, the plaintiff, Contract Control Services Pty Ltd (CCS) seeks relief in the nature of Certiorari in relation to an adjudication determination made by the second defendant, Max Tonkin (the Adjudicator) dated 7 March 2017 pursuant to the Building and Construction Industry Security of Payment Act 2002 (Vic) (the Act).
CCS seeks declarations that:
(a) clauses 47.2 and 47.2A of the Construction Contract are not methods of resolving disputes within the meaning given by s 10A(3)(d)(ii) of the Act;
(b) insofar as the claimed amount in the Adjudication Application includes claims for second class variations, that such claims are claimable variations within the meaning of s 10A(3) of the Act; and
(c) the Adjudicator’s determination to the effect that second class variations are not claimable variations and are excluded by s 10B(2)(a) and/or (b) is contrary to law.
CCS further seeks an order remitting the Adjudication Application back to the Adjudicator to be determined according to law.
Outline of Agreed Facts[1]
[1]In this proceeding the plaintiff and the first defendant by an Agreed Statement of Facts dated 23 June 2017, agreed to the facts referred to in paragraphs [4]-[13] of these Reasons for Judgment.
Contract
On or about 13 August 2013, CCS and the first defendant, Department of Education and Training (DET) entered into a Construction Contract in the form of a written contract executed by them (Construction Contract) pursuant to which CCS was to provide construction works and related goods and services to DET for the…
Keep reading for free
Create a free CaseChat account to read Contract Control Services v Det and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2017] VSC 507
- Decision Date
CaseChat Overview and Summary
The court examined the statutory provisions and relevant case law to determine if the exclusion of the non-claimable second class variations was appropriate. It also assessed whether the contract included a method for resolving disputes, as required by section 10A(3)(d)(ii) of the Act. The court needed to determine if the adjudicator's decision was subject to judicial review and, if so, whether certiorari should be granted to quash it. The court's analysis involved a detailed interpretation of the contract terms and the relevant statutory provisions, as well as a review of the adjudicator's decision-making process. The court's decision hinged on its interpretation of the legislation and the principles established in previous cases.
The Court of Appeal found that the exclusion of the non-claimable second class variations was incorrect, and the contract did not contain a method for resolving disputes as required by section 10A(3)(d)(ii) of the Act. The court held that the adjudicator's decision was legally flawed and subject to judicial review. As a result, the court granted certiorari to quash the adjudicator's decision. The court's reasoning was grounded in the statutory provisions and relevant case law, which established the criteria for excluding variations and the requirements for a dispute resolution method. The court's decision emphasised the importance of adhering to the statutory provisions and ensuring that contracts include appropriate dispute resolution mechanisms.
The final orders of the court were that the exclusion of the non-claimable second class variations was incorrect, and the contract did not contain a method for resolving disputes as required by section 10A(3)(d)(ii) of the Act. The court quashed the adjudicator's decision and remitted the matter to the adjudicator for reconsideration in light of the court's findings. The court's decision underscored the importance of ensuring that building contracts comply with statutory requirements and include appropriate dispute resolution mechanisms. The outcome of the case highlights the need for careful drafting of contracts and adherence to statutory provisions to avoid similar disputes in the future.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi