Contract Control Services v Det

Link copied
Case Copied 37 min read
IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE
COMMERCIAL COURT

TECHNOLOGY ENGINEERING AND CONSTRUCTION LIST

S ECI  2017 0068

CONTRACT CONTROL SERVICES PTY LTD (ACN  007 453 965) Plaintiff
v  
DEPARTMENT OF EDUCATION AND TRAINING
(ABN 52 705 101 522)
First Defendant
MAX TONKIN (as adjudicator in an adjudication under the Building and Construction Industry Security of Payment Act 2002 (Vic) between Contract Control Services Pty Ltd and Department of Education and Training) Second Defendant

---

JUDGE:

Digby  J

WHERE HELD:

Melbourne

DATE OF HEARING:

27 June 2017

DATE OF JUDGMENT:

30 August 2017

CASE MAY BE CITED AS:

Contract Control Services v DET

MEDIUM NEUTRAL CITATION:

[2017] VSC 507

---

CONTRACTS – Building Contract – Whether incorrect exclusion of non-claimable second class variations – Whether the Construction Contract contained a method for resolving disputes within the meaning of s 10A(3)(d)(ii) of the Building and Construction Industry Security of Payment Act 2002 (Vic) – SSC Plenty Road v Construction Engineering [2016] VSCA 119 – SSC Plenty Road v Construction Engineering [2015] VSC 631 – Branlin Pty Ltd v Totaro [2014] VSC 492.

ADMINISTRATIVE LAW – Judicial review – Decision of adjudicator appointed under the Building and Construction Industry Security of Payment Act 2002 (Vic) – Whether certiorari should be granted to quash the decision.

---

APPEARANCES:

Counsel Solicitors
For the Plaintiff Mr M A Robins QC KCL Law
For the Defendant Mr M Roberts QC Corrs Chambers Westgarth

HIS HONOUR:

Summary of Application

  1. By Originating Process dated 16 March 2017, the plaintiff, Contract Control Services Pty Ltd (CCS) seeks relief in the nature of Certiorari in relation to an adjudication determination made by the second defendant, Max Tonkin (the Adjudicator) dated 7 March 2017 pursuant to the Building and Construction Industry Security of Payment Act 2002 (Vic) (the Act).

  1. CCS seeks declarations that:

(a) clauses 47.2 and 47.2A of the Construction Contract are not methods of resolving disputes within the meaning given by s 10A(3)(d)(ii) of the Act;

(b)  insofar as the claimed amount in the Adjudication Application includes claims for second class variations, that such claims are claimable variations within the meaning of s 10A(3) of the Act; and

(c)   the Adjudicator’s determination to the effect that second class variations are not claimable variations and are excluded by s 10B(2)(a) and/or (b) is contrary to law.

  1. CCS further seeks an order remitting the Adjudication Application back to the Adjudicator to be determined according to law.

Outline of Agreed Facts[1]

[1]In this proceeding the plaintiff and the first defendant by an Agreed Statement of Facts dated 23 June 2017, agreed to the facts referred to in paragraphs [4]-[13] of these Reasons for Judgment.

Contract

  1. On or about 13 August 2013, CCS and the first defendant, Department of Education and Training (DET) entered into a Construction Contract in the form of a written contract executed by them (Construction Contract) pursuant to which CCS was to provide construction works and related goods and services to DET for the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Contract Control Services v Det and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2017] VSC 507
Decision Date

CaseChat Overview and Summary

The matter in Contract Control Services v Det involved a dispute between Contract Control Services and Det, regarding a building contract. The central issue was whether certain second class variations were incorrectly excluded from the claim, and whether the contract contained a method for resolving disputes as per section 10A(3)(d)(ii) of the Building and Construction Industry Security of Payment Act 2002 (Vic). Additionally, the case examined whether certiorari should be granted to quash the adjudicator's decision. The Court of Appeal was tasked with interpreting the relevant legislation and determining the validity of the adjudicator's decision. The court considered the principles established in SSC Plenty Road v Construction Engineering and Branlin Pty Ltd v Totaro, among other authorities. The central question was whether the adjudicator's decision, which upheld the exclusion of the second class variations, was legally sound and whether the contract contained a method for resolving disputes.

The court examined the statutory provisions and relevant case law to determine if the exclusion of the non-claimable second class variations was appropriate. It also assessed whether the contract included a method for resolving disputes, as required by section 10A(3)(d)(ii) of the Act. The court needed to determine if the adjudicator's decision was subject to judicial review and, if so, whether certiorari should be granted to quash it. The court's analysis involved a detailed interpretation of the contract terms and the relevant statutory provisions, as well as a review of the adjudicator's decision-making process. The court's decision hinged on its interpretation of the legislation and the principles established in previous cases.

The Court of Appeal found that the exclusion of the non-claimable second class variations was incorrect, and the contract did not contain a method for resolving disputes as required by section 10A(3)(d)(ii) of the Act. The court held that the adjudicator's decision was legally flawed and subject to judicial review. As a result, the court granted certiorari to quash the adjudicator's decision. The court's reasoning was grounded in the statutory provisions and relevant case law, which established the criteria for excluding variations and the requirements for a dispute resolution method. The court's decision emphasised the importance of adhering to the statutory provisions and ensuring that contracts include appropriate dispute resolution mechanisms.

The final orders of the court were that the exclusion of the non-claimable second class variations was incorrect, and the contract did not contain a method for resolving disputes as required by section 10A(3)(d)(ii) of the Act. The court quashed the adjudicator's decision and remitted the matter to the adjudicator for reconsideration in light of the court's findings. The court's decision underscored the importance of ensuring that building contracts comply with statutory requirements and include appropriate dispute resolution mechanisms. The outcome of the case highlights the need for careful drafting of contracts and adherence to statutory provisions to avoid similar disputes in the future.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established