CITATION: CONCRETE CONSTRUCTIONS GROUP v LITEVALE PTY LTD & ORS (NO 2) [2003] NSWSC 411 HEARING DATE(S): 10 December 2002 JUDGMENT DATE:
21 May 2003JUDGMENT OF: Mason P at 1 DECISION: See [76] CATCHWORDS: RESTITUTION - whether Defendant developer was unjustly enriched - "free acceptance" - where Plaintiff's services were neither volunteered nor provided "officiously" - whether Defendants, as reasonable persons, would have realised that the Plaintiff expected to be paid - Referee's conclusion supported by chain of correspondence - CONTRACT - Responsibility for payment to third party power supplier - Plaintiff's obligations under Design and Construction Contract-where Defendant purported to make payment on behalf of Plaintiff - whether Defendant was entitled to deduct that amount from its total payment to Plaintiff - PROCEDURAL FAIRNESS - whether unjust to now allow Defendants to raise claim - where matter already addressed by Plaintiff before Referee and ruled upon in Defendant's favour - mathematical oversight of Referee PARTIES :
CONCRETE CONSTRUCTIONS GROUP v LITEVALE PTY LTD & ORS FILE NUMBER(S): SC 055058/1997 COUNSEL: Plaintiff: R W Hunt
Defendant: F Corsaro SCSOLICITORS: Plaintiff: Corrs Chambers Westgarth
Defendant: Deacons
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY & CONSTRUCTION LISTMASON P
Wednesday 21 May 2003
JUDGMENTSC 055058/97 CONCRETE CONSTRUCTIONS GROUP v LITEVALE PTY LTD & ORS (No 2)
1 MASON P: Most issues in these proceedings were addressed in my earlier reasons for judgment (Concrete Constructions Group v Litevale Pty Ltd & Ors [2002] NSWSC 670 ((2002) 170 FLR 290; (2002) ATPR (Digest) 46-224), the “main judgment”).
2 The parties have filed additional submissions in support of their remaining contentions. These are:
• Plaintiff’s outline of submissions on issues 5 and 14, dated 1 November 2002 (PS 6)
• Defendant’s outline of the existing contentions and submissions in relation to acceleration and Northpower, dated 1 November 2002 (DS 5)
• Plaintiff’s outline of submissions in reply to defendant’s written submissions, dated 15 November 2002 (PS 7)
• Plaintiff’s outline of submissions on general principles in relation to costs, dated 19 November 2002 (PS 8)
Issue 5• Defendants’ provisional outline of submissions in relation to costs, dated 4 November 2002 (DS 6).
3 In the proceedings before me concerning adoption of the Referee’s Report, the issue of the plaintiff’s challenge to the Referee’s rejection of a particular restitutionary claim was raised (Issue 5).
4 Additional costs were incurred by the plaintiff in accelerating completion of the Works. The Referee held that there was a discussion at a meeting on 26 April 1995 when the defendants’ representative asked the plaintiff’s representative whether the plaintiff could complete to enable the Centre to open prior to December 1995. The plaintiff’s representative said “Yes, we can make it”, but did not state that it would cost more money. Practical completion was achieved by 30 November 1995 and this involved additional expenditure by the plaintiff.
5 The plaintiff sought to recoup this outlay by claiming the cost under a collateral contract…
Keep reading for free
Create a free CaseChat account to read Concrete Constructions Group v Litevale Pty Ltd & Ors (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] NSWSC 411
- Decision Date
CaseChat Overview and Summary
The court examined the nature of the services provided by CCG to determine if there was an expectation of payment, and whether Litevale, as a reasonable person, should have recognised this expectation. The chain of correspondence and the terms of the Design and Construction Contract were pivotal in understanding the intent behind the services rendered. The court also considered the procedural fairness of allowing Litevale to raise the issue of the third-party payment, given that it had already been addressed and ruled upon by the referee. The analysis revealed a mathematical oversight by the referee, which needed correction.
The High Court concluded that CCG's services were not provided as a "free acceptance" and that Litevale, as a reasonable person, would have understood that payment was expected. Regarding the third-party payment, the court determined that Litevale was not entitled to deduct that amount from its total payment to CCG. The court also found that it was not unjust to allow Litevale to raise the claim, as the matter had already been addressed in the proceedings below. The court's decision rectified the mathematical oversight of the referee, resulting in a revised quantum of damages awarded to CCG.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.