CITATION: BUILT INTERIORS PTY LTD v THREE DINOSAURS PTY LTD & ANOR [2003] NSWCA 290 HEARING DATE(S): 12, 13 August 2003 JUDGMENT DATE:
3 October 2003JUDGMENT OF: Mason P at 1; Meagher JA at 82; Ipp JA at 83 DECISION: Appeal dismissed with costs. CATCHWORDS: Building contracts - contractual and restitutionary claims for variations - contractual procedures for claiming variations not followed - work involved was part and parcel of contract work - Jones v Dunkel - architect not called or his absence explained at trial - witness was available to either party - fresh evidence sought to be tendered on appeal was available at trial and not likely to affect result of appeal - evidence rejected - implied term for acceleration costs not available on facts (ND) PARTIES :
BUILT INTERIORS PTY LTD v THREE DINOSAURS PTY LTD & ANOR FILE NUMBER(S): CA 41061/02 COUNSEL: Appellant: D A Doyle (Sol) / J Cheung (Sol) /
M Michael (Sol)
Respondent: E OlssonSOLICITORS: Appellant: The Builders' Lawyer
Respondent: E H Tebbutt & Sons
LOWER COURTJURISDICTION: District Court LOWER COURT FILE NUMBER(S): DC 8523/00 LOWER COURT
JUDICIAL OFFICER :Patten DCJ
CA 41061 of 2002
DC 8523 of 2000MASON P
MEAGHER JA
IPP JAFriday 3 October 2003
JUDGMENT
1 MASON P: The appellant (hereafter the Builder) contracted with the respondents (hereafter the Proprietors) to redevelop a site at Strawberry Hills. The work consisted of interior alterations and fit-out of an art gallery, photographic studio, workshop, offices and showroom.
2 The Proprietors had retained an Architect, the firm of Engelen Moore (the Architect). A principal of that firm, Mr Ian Moore had the ultimate oversight of the project, but it was an assistant architect Ms Meller who was the nominated project architect.
3 The formal contract was executed on 25 August 1998 in the form of the Lump Sum Contract for Simple Building Works Edition 2. That Contract contains standard terms and incorporates plans and specifications.
4 The contract price was $616,143. Possession was to be given by 31 August 1998 with practical completion to occur by 23 November 1998. The time frame was tight. Hard negotiations had seen some last minute modifications to the contract works and reduction in the lump sum.
5 The Contract provided for the Builder to submit progress claims for payment to the Architect every two weeks. Progress certificates were to be issued within five days of receipt. Unlike some building contracts, the Contract did not stipulate that progress claims were deemed accepted if they were not rejected.
6 “Variations” were defined in cl 1.2 as:
- Any of the following:
- Increases or decreases in or omissions from the Works.
- Changes in the character or quality of any material or work.
- Changes in the levels, lines, positions or dimensions of any part of the Works.
- Execution of additional work.
- New fees or charges, increases or decreases in fees or charges referred to in…
Keep reading for free
Create a free CaseChat account to read Built Interiors Pty Ltd v Three Dinosaurs Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] NSWCA 290
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the Court of Appeal were: (1) whether the work performed by the appellant constituted variations to the original building contract, and if so, whether the appellant could recover payment for this work despite not adhering to the contractual variation procedures; (2) whether the appellant was entitled to payment on a quantum meruit basis; and (3) whether there was an implied term in the contract entitling the appellant to costs for acceleration of the works. The court also considered an application to adduce fresh evidence on appeal.
The Court of Appeal held that the work in question was part and parcel of the original contract works and did not constitute variations. Consequently, the appellant could not claim payment for these works as variations, nor could it claim on a quantum meruit basis, as the work was performed under the existing contract. The court applied the principle from *Jones v Dunkel* regarding the drawing of inferences from the absence of a witness, noting that the architect, who was available to either party, was not called by the appellant. Furthermore, the court rejected the application to adduce fresh evidence on appeal, finding that it was available at trial and unlikely to affect the outcome. The claim for acceleration costs was also dismissed.
The appeal was dismissed with costs.
Orders
Orders of the court
Appeal dismissed with costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.