Kostos Pty Ltd v Vellios; Vellios v Kostos Pty Ltd

Link copied
Case Copied 76 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Kostos Pty Ltd v Vellios; Vellios v Kostos Pty Ltd [2019] NSWCATCD 13
Hearing dates: 18, 19 December 2017
Date of orders: 08 May 2019
Decision date: 08 May 2019
Jurisdiction:Consumer and Commercial Division
Before: F Corsaro SC, Senior Member
Decision:

In Application HB 17/21359, order:

 

1. The Respondents (the Owners, Dimitri Vellios and Vicki Vellios) are to immediately pay the Applicant (the Builder, Kostos Pty Ltd) the amount of $55,708.79 including GST.

 

In Application HB 17/38120, order:

 

1. The Respondent (the Builder, Kostos Pty Ltd) is to immediately to pay the Applicants (the Owners, Dimitri Vellios and Vicki Vellios) the amount of $17,052 including GST with the amount of Builder’s liability to the Owners to be set off by the Owners against the Owners liability to the Builder by the Tribunal’s order in HB 17/21359.

 

2. The Builder must carry out all of the item of work identified in the report of Mr Gerard Todarello of Precision Inspections dated 31 July 2017 (the Todarello Report) other than items 6.34, 6.35, 6.49, 6.61 and 6.69.

 

3. In Application HB 17/21359 and in Application HB 17/38120 any application for costs is to be determined as follows

 

(1) The Builder is to file and serve written submissions on the issue of costs within 14 days from the date of this decision. Such submissions are to include reference to whether or not the Builder agrees to costs being determined on the papers in accordance with s 50 (2) of the Civil and Administrative Tribunal Act 2013 (NSW);

 

(2) The Owner is to file and serve any written submissions on the issue of costs in response within 14 days after service of the Builder’s submissions

(3) Subject to the submissions of the parties, the issue of costs may be determined on the papers and without further oral hearing in accordance with s 50 (2) of the Civil and Administrative Tribunal Act 2013 (NSW).
Cases Cited: Antworks Pty Ltd and Brendon Chhong Lee v Shixin (Cindy) Lee [2015] NSWCATAP 53
Bittania Pty Ltd v Parkline Constructions Pty Ltd [2009] NSWSC 1302
Bradshaw v Complete Coating Commercial Pty Ltd trading as CCC Civil [2017] NSWCATAP 209
Built Interiors Pty Ltd v Three Dinosaurs Pty Ltd [2003] NSWCA 290.
Kurmond Homes Pty Ltd v Marsden [2018] NSWCATAP 23
Leung v Alexakis [2018] NSWCATAP 11
Liebe v Molloy (1906) 4 CLR 347
Mobil Oil Australia Ltd v Kosta [1970] ALR 253
Morgan v Allen [1971] Tas SR 285
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104.
Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221
Richard Evans v Astley [1911] AC 674
Trimis v Mina [1999] NSWCA 140
Update Constructions Pty Ltd v Rozelle Care Centre Ltd (1990) 20 NSWLR 251
Xu v Jinhong Design & Constructions Pty Ltd [2011] NSWCA 277
Category:Principal judgment
Parties:

Proceedings HB 17/21359:
Kostos Pty Ltd (Applicant)
Dimitri Vellios and Vicki…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Kostos Pty Ltd v Vellios; Vellios v Kostos Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] NSWCATCD 13
Decision Date

CaseChat Overview and Summary

Kostos Pty Ltd, the builder, and Dimitri and Vicki Vellios, the homeowners, were the parties to a dispute heard by the Civil and Administrative Tribunal in New South Wales. The builder sought payment of $55,708.79, while the homeowners sought payment of $17,052 from the builder, as well as an order for the builder to rectify certain defects in the building works. The dispute arose from the construction of a residential building, and the quality of the works performed by the builder.

The legal issues before the Tribunal were whether the builder was entitled to the payment of $55,708.79, whether the homeowners were entitled to payment of $17,052 from the builder, and whether the builder was liable to rectify certain defects in the building works. The Tribunal also needed to determine the issue of costs in both applications.

The Tribunal found that the builder was entitled to the payment of $55,708.79, and that the homeowners were entitled to payment of $17,052 from the builder. The Tribunal also found that the builder was liable to rectify certain defects in the building works, other than items 6.34, 6.35, 6.49, 6.61 and 6.69 identified in the Todarello Report. The Tribunal ordered the immediate payment of $55,708.79 by the homeowners to the builder, and the immediate payment of $17,052 by the builder to the homeowners. The Tribunal also ordered the builder to rectify the identified defects, and made orders in relation to the issue of costs.

The Tribunal ordered that the builder is to immediately pay the homeowners $17,052, and that the homeowners are to pay the builder $55,708.79. The Tribunal also ordered the builder to carry out the identified works, other than the specified items. The Tribunal further ordered that the issue of costs may be determined on the papers and without further oral hearing, subject to the submissions of the parties.

Orders

Orders of the court

In Application HB 17/21359, order:

1. The Respondents (the Owners, Dimitri Vellios and Vicki Vellios) are to immediately pay the Applicant (the Builder, Kostos Pty Ltd) the amount of $55,708.79 including GST.

In Application HB 17/38120, order:

1. The Respondent (the Builder, Kostos Pty Ltd) is to immediately to pay the Applicants (the Owners, Dimitri Vellios and Vicki Vellios) the amount of $17,052 including GST with the amount of Builder’s liability to the Owners to be set off by the Owners against the Owners liability to the Builder by the Tribunal’s order in HB 17/21359.

2. The Builder must carry out all of the item of work identified in the report of Mr Gerard Todarello of Precision Inspections dated 31 July 2017 (the Todarello Report) other than items 6.34, 6.35, 6.49, 6.61 and 6.69.

3. In Application HB 17/21359 and in Application HB 17/38120 any application for costs is to be determined as follows

(1) The Builder is to file and serve written submissions on the issue of costs within 14 days from the date of this decision. Such submissions are to include reference to whether or not the Builder agrees to costs being determined on the papers in accordance with s 50 (2) of the Civil and Administrative Tribunal Act 2013 (NSW);

(2) The Owner is to file and serve any written submissions on the issue of costs in response within 14 days after service of the Builder’s submissions

(3) Subject to the submissions of the parties, the issue of costs may be determined on the papers and without further oral hearing in accordance with s 50 (2) of the Civil and Administrative Tribunal Act 2013 (NSW).

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.