New South Wales
Court of Appeal
CITATION: Al-Atabi v Zaidi [2009] NSWCA 433 HEARING DATE(S): 13/7/09
JUDGMENT DATE:
23 December 2009JUDGMENT OF: McColl JA at 1; Handley AJA at 68; Sackville AJA at 69 DECISION: Appeal dismissed with costs. CATCHWORDS: CONTRACTS – general contractual principles – construction and interpretation of contracts – lump-sum contract in respect of building work – claim for variations – whether work in variations claim part of work covered by lump-sum contract – whether waiver of contractual variations procedure – whether variations subject of implied or express contract LEGISLATION CITED: Environmental Planning and Assessment Act 1979 (NSW) CATEGORY: Principal judgment CASES CITED: Al-Atabi v Zaidi [2008] NSWDC 128
Concrete Constructions Group v Litevale Pty Ltd & Ors (No 2) [2003] NSWSC 411
Fox v Percy [2003] HCA 22, (2003) 214 CLR 118
GEC Marconi Systems Pty Limited v BHP Information Technology Pty Limited [2003] FCA 50
Liebe v Molloy [1906] HCA 67; (1906) 4 CLR 347
Smith v Leon Dupuy Dozer Hire [2000] VSC 212
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd [2004] HCA 52; (2004) 219 CLR 165
Trimis v Mina [1999] NSWCA 140PARTIES: Muhanad Al-Atabi - Appellant
Attia Zaidi - First Respondent
Mohammad Ali Abbas - Second Respondent
Salma Raza - Third Respondent
Hasan Zaidi - Fourth RespondentFILE NUMBER(S): CA 40305 of 2008 COUNSEL: PT Taylor SC with DS Weinberger for the Appellant
EA White for the RespondentsSOLICITORS: Maccallum Lawyers for the appellant
Dominic Stanfords for the respondentsLOWER COURT JURISDICTION: District Court LOWER COURT FILE NUMBER(S): DC 1170 of 2007 LOWER COURT JUDICIAL OFFICER: Johnstone DCJ LOWER COURT DATE OF DECISION: 29 May 2008 LOWER COURT MEDIUM NEUTRAL CITATION: [2008] NSWDC 128
McCOLL JACA 40305/08
DC 1170/07
HANDLEY AJA
SACKVILLE AJA
Wednesday 23 December 2009
Muhanad Al-Atabi v Attia Zaidi & Ors
Judgment
1 McCOLL JA: The appellant, Mr Muhanad Al-Atabi, a licensed builder who traded under the business name “Civil Choice”, took proceedings in the District Court seeking payment allegedly due in respect of work he carried out for the first three respondents, Attia Zaidi, Mohammad Ali Abbas and Salma Raza, to construct eight townhouses on property they owned in Mount Druitt. The fourth respondent, Hasan Zaidi, represented the first three respondents in their dealings with the appellant.
2 The central issue at trial was what was the agreed contract price and, in particular, whether the appellant was entitled to amounts he claimed were due in respect of variations. Its resolution turned on which of three documents brought into existence in or around mid 2004 constituted the contract between the parties. The appellant claimed that the contract was a cost plus agreement for $1.1 million. He claimed amounts due for variations to the contract pursuant to two documents, one described as the “Variations Document”, dated 23 January 2006 which enumerated 30 items and claimed $742,092.45, the other entitled “Variation Advice” dated 20 March 2005 in the amount of $98,725.00. He also claimed…
Continue reading Al-Atabi v Zaidi
Sign in free to access the full text
- AGLC
- Al-Atabi v Zaidi [2009] NSWCA 433
- Case
- [2009] NSWCA 433
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the additional work constituted variations to the original contract, or if it was work that the builder was already obliged to perform under the terms of the lump-sum agreement. Further, the court had to consider whether the owner had waived the contractual procedures for authorising variations, and whether the variations, if they were indeed variations, were the subject of an express or implied contract separate from the original lump-sum agreement.
The Court of Appeal, in dismissing the appeal, found that the work in question was not outside the scope of the original lump-sum contract. The judges applied general principles of contract construction, focusing on the clear terms of the written agreement. They concluded that the builder had not established that the additional work was not included in the original scope, nor had they demonstrated a waiver of the contractual requirements for variations. Consequently, there was no basis for an implied or express contract for variations. The appeal was dismissed with costs.
Orders
Orders of the court
Appeal dismissed with costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.